INSP-Final Inspection | 6/18/2020 | 6/18/2020 | 6/18/2020 | P | PASS |
Jim Page
|
|
|
Final inspection for underground supply complete.
Please call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Supply line flush | 5/29/2020 | 6/1/2020 | 6/1/2020 | A | DONE |
Jim Page
|
|
|
Underground main line flush witnessed.
Scheduled for 9am with Stacy at Suez. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 5/27/2020 | 5/27/2020 | 5/27/2020 | P | DONE |
Jim Page
|
|
|
Hydrostsic test for underground supply witnessed, no pressure loss observed at gauge before backflow.
Underground hydro. Ready any time, call James before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 11/25/2019 | 11/26/2019 | 11/26/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, underground approved for cover.
Underground rough to cover. Please call before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 11/25/2019 | 11/25/2019 | 11/25/2019 | A | FAIL |
Jim Page
|
|
|
Bury depth of 54 inches to top of pipe not met. Attach bury wire to pipe, cover is not approved.
Call before heading out, underground rough to bury (hydro in warm weather or closer to final) Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|