INSP-Final Inspection | 7/29/2020 | 7/30/2020 | 7/30/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Final Inspection | 7/29/2020 | 7/30/2020 | 7/29/2020 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Carlisle Inspection cancelled from web by: Brian Carlisle
|
INSP-Sprinkler Rough-in/Hydro | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PASS |
Troy Cobbley
|
|
|
Second floor Rough in passed and piping can be covered and second floor hydro witnessed.
Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in/Hydro | 6/12/2020 | 6/15/2020 | 6/15/2020 | A | PART |
Troy Cobbley
|
|
|
First floor rough in passed. Piping can be covered. The second floor high/lobby and west stairs are not done yet. Hydro on first floor was witnessed with no pressure loss. Second floor hydro have a visible loss on the guage and not all piping is cut in. Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in/Hydro | 6/11/2020 | 6/11/2020 | 6/11/2020 | P | PASS |
Troy Cobbley
|
|
|
Second floor rough-in passed. Sprinkler piping can be covered except for the west stairway which was not done. Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 5/15/2020 | 5/18/2020 | 5/18/2020 | A | PASS |
Troy Cobbley
|
|
|
Pool Room is ok for cover. Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 5/15/2020 | 5/15/2020 | 5/15/2020 | P | PASS |
Troy Cobbley
|
|
|
Up stairs rec room sprinkler piping is ok for cover.. Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 5/11/2020 | 5/12/2020 | 5/12/2020 | A | PASS |
Troy Cobbley
|
|
|
Void spaces for blown insulation are ok for cover., The room upstairs is not finished yet. Will need another inspection scheduled. . Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 3/23/2020 | 3/23/2020 | 3/23/2020 | P | PASS |
Troy Cobbley
|
|
|
Hangers changed to approved attachment, flexible cplgs added at rise up and two additional heads added on the back side of duct work. One additional hard lid is ok for cover.
We fixed deficiencies would like to have it rechecked. Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 3/19/2020 | 3/20/2020 | 3/20/2020 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed for the overhead mains and piping. I need verification that "side sammys" can be used on the trusses. Piping in some of the hard lids is ok for cover as marked on the plans. Additional cover inspections will be needed when the remaining sprinkler drops have been installed.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 2/27/2020 | 2/28/2020 | 2/28/2020 | P | FAIL |
Jim Page
|
|
|
Notated city approved drawings with red ink area where upright heads are overspaced,inspection stopped after notation.
Rough in for first floor. Phone #: ###-#### Inspection requested via web by Sam Ball
|