Final | 9/11/2019 | 9/12/2019 | 9/12/2019 | A | PASS |
Jack Reynolds
|
|
|
DAVID IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER - final ok
|
Final | 7/1/2019 | 7/2/2019 | 7/2/2019 | A | PART |
Brian Scoles
|
|
|
PADRAIC IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- need to secure gas piping to supports east roof section- drip legs can not be in contact with roof need to shorten- will look at this on other mechanical contractors inspection when walking roof
|
Mec-Aging Inspection | 6/17/2019 | 6/17/2019 | 6/17/2019 | | CANC |
Brian Scoles
|
|
|
contractor needs to call in inspection when ready
|
Mec-Aging Inspection | 3/18/2019 | 3/18/2019 | 3/18/2019 | | CANC |
Brian Scoles
|
|
|
WIP-
|
Mec-Aging Inspection | 12/17/2018 | 12/17/2018 | 12/17/2018 | | CANC |
Brian Scoles
|
|
|
WIP
|
Pressure Test | 9/14/2018 | 9/17/2018 | 9/17/2018 | A | PASS |
Brian Scoles
|
|
|
JOB CONTACT - DAVID ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- 60lb gas pass whole system- need inert tape on all penetrations- need to secure all gas piping on roof to supports
|