Final | 12/9/2019 | 12/9/2019 | 12/9/2019 | P | PASS |
Jack Reynolds
|
|
|
final ok occ card signed
|
Final | 11/25/2019 | 11/25/2019 | 11/25/2019 | P | PART |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by RaChelle Frisbee - TAB report ok. Will sign occ card once corrections are made and two other mech permits from others are finaled - all equipment needs set in its place and hood should hang not less than 6" beyond edge of equipment. one piece of equipment is outside of hoods edge. - both hoods need grease reservoirs installed in hood
|
Final | 11/14/2019 | 11/15/2019 | 11/15/2019 | A | PART |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by RaChelle Frisbee - need TAB report for final
|
Rough-in | 11/1/2019 | 11/4/2019 | 11/4/2019 | A | PASS |
Jack Reynolds
|
|
|
Ceiling cover. Thank you! Phone #: ###-#### Inspection requested via web by RaChelle Frisbee - ceiling cover R/I ok
|
Rough-in | 10/29/2019 | 10/30/2019 | 10/30/2019 | A | FAIL |
Jack Reynolds
|
|
|
ceiling cover Phone #: ###-#### Inspection requested via web by RaChelle Frisbee L-1 louvers for make up air to kitcken need ducted into ceiling. - return tap at ceiling in kitcken needs sealed - factory grease duct clearances ok
|
Rough-in | 7/22/2019 | 7/23/2019 | 7/23/2019 | P | PART |
Jack Reynolds
|
|
|
Hard lid cover. Thank you! Phone #: ###-#### Inspection requested via web by RaChelle Frisbee - hard lid only R/I cover ok on exhaust and heaters
|