Final | 3/3/2020 | 3/4/2020 | 3/4/2020 | A | PASS |
Jack Reynolds
|
|
|
Thank you Phone #: ###-#### Inspection requested via web by Aaron Johns - final ok
|
Rough-in | 2/26/2020 | 2/27/2020 | 2/27/2020 | A | PASS |
Jack Reynolds
|
|
|
Greg Phone #: ###-#### - R/I ok on enclosure of b vent - will need to see b vent tee installed at bottom of vent and access door in enclosure by final
|
Rough-in | 2/19/2020 | 2/19/2020 | 2/19/2020 | P | PART |
Jack Reynolds
|
|
|
301 - vent pipe clearances to framing ok - need to see clearances with insulation installed - vent piping specs should be followed for enclosure. having an access door to the vent and a b vent tee at the bottom for clean out
|
Final | 2/12/2020 | 2/12/2020 | 2/12/2020 | P | FAIL |
Jack Reynolds
|
|
|
Thank you Phone #: ###-#### Inspection requested via web by Aaron Johns - 2428.2.9 IRC 2012 any b vent exposed more than 5' to the outdoors shall be enclosed or chased and insulated to not less than R-8 / vent manufactures specs for being in an enclosure- need to add range and fireplace to permit - need air balance report - electrical needs finished at furnace and A/C - b vent needs 1" clearances - line set needs UV protection and locking installed on A/C - all penetrations need sealed - water heater needs sediment trap in gas line
|
Rough-in | 11/6/2019 | 11/7/2019 | 11/7/2019 | P | PASS |
Jack Reynolds
|
|
|
if you could call in advance so I can unlock the building that would be great it might be unlocked anyway thank you. Troy approved the new manual J and we have a new fire place installed and the duct seal done see you tomorrow Phone #: ###-#### Inspection requested via web by Aaron Johns - fireplace and HVAC R/I ok - need to add fireplace to permit
|
Rough-in | 11/1/2019 | 11/4/2019 | 11/4/2019 | A | FAIL |
Jack Reynolds
|
|
|
Thank you Phone #: ###-#### Inspection requested via web by Aaron Johns - Man j needs updated and approved by the City - fllor boots need sealed to floor - range vent needs sealed - If fireplace is staying it needs an inspection and installation instructions onsite
|
Pressure Test | 11/4/2019 | 11/4/2019 | 11/4/2019 | A | PASS |
Jack Reynolds
|
|
|
Thank you Phone #: ###-#### Inspection requested via web by Aaron Johns - 20lb gas pressure test ok - tagged meter location
|
Rough-in | 10/30/2019 | 10/31/2019 | 10/30/2019 | P | CANC |
Jack Reynolds
|
|
|
Thank you Phone #: ###-#### >> Inspection requested via web by Aaron Johns Inspection cancelled from web by: Aaron Johns
|