Permit Information
Permit NumberPLM17-04821
StatusFinaled
Name RM MECHANICAL
Site Address 8000 S FEDERAL WAY
Project NameMicron B39 CUP
Customer Number 
ePlanReviewNo
Description
Install a new IW & HFW treatment system
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final3/28/20193/29/20193/29/2019APASS
DetailsDaryl Spivey
Good Afternoon, This is to walk the recently completed Duct Drain Piping and request the Final for this Permit. The Project is complete aside a couple minor Punch List Items. Thank you Eric... Phone #: ###-#### Inspection requested via web by RM Mechanical
PLM-Aging Inspection3/28/20193/28/20193/28/2019 PASS
DetailsDaryl Spivey
wip
Pressure Test12/27/201812/27/201812/27/2018PPART
DetailsEric Strole
Good Morning, This Inspection is for an Overflow Line that stems from two HFW Tanks, combines the two and connects to the IW Trench Piping. Anytime that works for you will be fine with us. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section complete is marked in test result book.
Pressure Test12/21/201812/21/201812/21/2018PPART
DetailsEric Strole
Good Morning, This is the same HFW Line as the AM this morning, back on Test. Thank you Eric... Phone #: ###-#### Inspection requested via web by RM Mechanical-Section complete is marked in test result book.
Pressure Test12/21/201812/21/201812/21/2018AFAIL
DetailsEric Strole
Good Morning, We will have a very small portion of HFW Poly Pro Piping on Test this morning. Let me know when you''re available... may be a short day? Thank you Eric... Phone #: ###-#### Inspection requested via web by RM Mechanical-Test fail.
Pressure Test12/18/201812/19/201812/19/2018PPART
DetailsEric Strole
Good Morning, This Inspection is for a fairly large portion of the HFW System. This Line is the continuation above the Tanks in the Waste Bay. Should have it on Pressure by Noon today. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section complete is marked in test result book.
Pressure Test12/18/201812/18/201812/18/2018PCANC
DetailsEric Strole
Good Morning, This Inspection is for a fairly large portion of the HFW System. This Line is the continuation above the Tanks in the Waste Bay. Should have it on Pressure by Noon today. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical
Pressure Test12/17/201812/17/201812/17/2018APART
DetailsEric Strole
Good Morning,
This Inspection is to confirm two HFW Lines that are incorporated into One Test... we will have it up to Test Pressure later this morning. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Sections inspected are marked in test result book.
Pressure Test12/13/201812/13/201812/13/2018PPART
DetailsEric Strole
Good Morning, This is an HFW Test from the Filter Press to the HFW Tank 701 in the Waste Bay. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section complete are marked in test result book
Pressure Test11/20/201811/21/201811/21/2018APART
DetailsEric Strole
pressure test
###-#### rm mech-Sections complete are marked in test result book.
Pressure Test11/20/201811/20/201811/20/2018PCANC
DetailsMatt Wrobel
Good Morning, This inspection request is for a portion of the HFW System from B-51 terminating in the Waste Bay of B-39. Feel free to call when you get here. Thank you, Eric. Phone #: 208-830
-1288 Inspection requested via web by RM Mechanical
rescheduled
Pressure Test11/6/201811/6/201811/6/2018PPART
DetailsEric Strole
This Inspection is for a small portion of IW from the Sump in the 90 Day Accumulation Room. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section complete is marked in test result book.
Pressure Test10/11/201810/11/201810/11/2018PPART
DetailsDaryl Spivey
ride along with Eric
Pressure Test10/11/201810/11/201810/11/2018PPART
DetailsEric Strole
This Inspection is of Drainage Piping from a Scrubber Unit. It''s Gravity Drains that Tie Into the Main. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section complete is marked in test result book.
Pressure Test10/9/201810/9/201810/9/2018PPART
DetailsEric Strole
Good Morning, This Pressure Test is of a DIRC Line from B-51, Trestle to B-39 where it picks up the IW Line to the Waste Bay. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section passed is marked in test result book.
Pressure Test10/3/201810/3/201810/3/2018PPART
DetailsEric Strole
Good Morning, This Inspection is of the Safety Shower Drain Piping from the Trestle Showers to the Indirect Trench Drains in B-51 and B-39. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section complete is marked in test result book.
Pressure Test10/2/201810/2/201810/2/2018PPART
DetailsEric Strole
Good Morning, This Inspection is for Gravity IW within the Trenches in the Waste Bay. Lines terminate in the Deep Sump Pit. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section complete is marked in test result book.
Pressure Test9/27/20189/27/20189/27/2018PPART
DetailsEric Strole
Good Morning, This is a very small section of IW from two Fan Units on the Rooftop, tying into Gravity Drain IW Main. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section complete is marked in test result book.
Pressure Test9/25/20189/25/20189/25/2018PPART
DetailsEric Strole
This Inspection is of two different IW Tests. One is Pumped IW from the 90 Day Accumulation Room, the other is Gravity from Condensate Drains. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Sections complete is marked in test result book.
Pressure Test9/20/20189/20/20189/20/2018PNR
DetailsEric Strole
This Test is of the IW coming into B-39, terminating in the Waste Bay. Anytime this afternoon is fine Eric. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical
Pressure Test9/19/20189/19/20189/19/2018PCANC
DetailsEric Strole
Good Morning, This Test is of an IW Line coming into B-39, terminating near Tanks 101 and 201. We briefly discussed it yesterday. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical
Pressure Test9/18/20189/18/20189/18/2018PPART
DetailsEric Strole
Good Morning, This Inspection request is for an IW System that is mainly made up of Trench Piping, and small Drains from AHU Units. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section inspected is marked in test result book.
Pressure Test9/12/20189/12/20189/12/2018APART
DetailsEric Strole
This Test is of the IW Drain from the Fan Coil Units on the Mezzanine and the Scrubber Units in the Waste Bay. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section inspected is marked in test result book.
Pressure Test9/7/20189/7/20189/7/2018APART
DetailsBill VanDegrift
Good Morning, This Inspection is of a small portion of IW, AHU and MAU Units on the Mezzanine. This is located in the Ovivo Bay. Thank you. Phone #: ###-#### Inspection test ok equested via web by RM Mechanical
Pressure Test8/24/20188/24/20188/24/2018PPART
DetailsEric Strole
IW in H2SO4 Room. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section inspected is marked in test result book.
Pressure Test8/16/20188/17/20188/17/2018APART
DetailsEric Strole
This Test confirmation is a portion of IW in the Chiller Bay. One portion is pumped, the other is Gravity, incorporated into one Test. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanicall-Section inspected is marked in test result book.
Pressure Test8/9/20188/9/20188/9/2018PPART
DetailsEric Strole
This Test Inspection is of the Pumped IW Line out of the Compressor Bay.
Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section inspected is marked in test result book.
Pressure Test8/8/20188/8/20188/8/2018PPART
DetailsEric Strole
This Test is of the Pumped IW Sump in the Boiler Bay. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section inspected is marked in test result book.
Pressure Test7/31/20188/1/20188/1/2018APART
DetailsEric Strole
This Test is of the IW Trench Piping in the Boiler Bay, terminating at the Sump. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section inspected is marked in test result book.
Pressure Test7/19/20187/19/20187/19/2018PPART
DetailsEric Strole
This is a small portion of Pumped IW to a Gravity Header in the Ovivo Bay. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section inspected is marked in test result book.
Pressure Test7/18/20187/19/20187/19/2018APART
DetailsEric Strole
This is a small portion of Pumped IW to a Gravity Header in the Ovivo Bay. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Need to come back in afternoon to verify test.
Pressure Test7/18/20187/18/20187/18/2018PCANC
DetailsEric Strole
This is a small portion of IW connecting to Gravity Header. Thank you.
Phone #: ###-#### Inspection requested via web by RM Mechanical
Pressure Test7/9/20187/9/20187/9/2018PPART
DetailsEric Strole
RAW-ACF-IW Test
Phone #: ###-#### Inspection requested via web by RM Mechanical-Section inspected is marked in test result book.
Pressure Test7/6/20187/9/20187/9/2018APART
DetailsEric Strole
One short, Pumped IW Line and one small portion of an ACF System tying into the Gravity IW. I will have both on pressure by 8:00am Monday. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section inspected is marked in test result book.
Pressure Test6/28/20186/28/20186/28/2018APART
DetailsEric Strole
I would like to walk IW and Inspect, here in B-39 with Mr. Strole. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanicall-Sections inspected are marked in test result book.
Pressure Test6/11/20186/12/20186/12/2018APART
DetailsEric Strole
This Test is of IW-Trench Piping in the Compressor Bay. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section inspected is marked in test result book.
Pressure Test6/7/20186/8/20186/8/2018APART
DetailsBill VanDegrift
IW Chiller Bay Trench Phone #: ###-#### Inspection requested via web by RM Mechanical
Pressure Test5/23/20185/23/20185/23/2018PPART
DetailsEric Strole
IW TNK01/02 Suction Piping and Tank interconnect. Phone #: ###-#### Inspection requested via web by RM Mechanical-Section inspected is marked in test result book.
Pressure Test5/15/20185/15/20185/15/2018APART
DetailsEric Strole
IW Cooling Tower Drains Phone #: ###-#### Inspection requested via web by RM Mechanical-Section of IW tested is marked in test result book.
Pressure Test5/9/20185/10/20185/10/2018APASS
DetailsEric Strole
IW OFF-SPEC 8x12 Primary and Secondary. Phone #: ###-#### Inspection requested via web by Melissa Kaae-Inner containment of 14x8 IW pass.
Pressure Test5/9/20185/9/20185/9/2018PPART
DetailsEric Strole
IW OFF-SPEC 8x12 Primary and Secondary. Phone #: ###-#### Inspection requested via web by Melissa Kaae-Outer containment of 14x8 IW pass.
Pressure Test5/7/20185/8/20185/8/2018APART
DetailsEric Strole
IW GRAVITY FROM AREA 1 TO WASTE TANKS. IW PUMP DISCHARGE FROM SUMP04 TO CONNECTION IN WASTE BAY Phone #: ###-#### Inspection requested via web by Melissa Kaae-Sections tested and inspected are marked in test result book.
Pressure Test5/3/20185/3/20185/3/2018APART
DetailsEric Strole
IW Off-Spec Primary and Secondary Phone #: ###-#### Inspection requested via web by Melissa Kaae-Test on primary 14x20 IW pass.
Pressure Test5/2/20185/2/20185/2/2018PCANC
DetailsEric Strole
IW Off-Spec 12"x8" Phone #: ###-#### Inspection requested via web by Melissa Kaae
Pressure Test5/1/20185/2/20185/2/2018ACANC
DetailsEric Strole
W Off Spec Secondary Containment Phone #: ###-#### Inspection requested via web by Melissa Kaae
Pressure Test5/1/20185/1/20185/1/2018PPART
DetailsEric Strole
IW Off Spec Secondary Containment Phone #: ###-#### Inspection requested via web by Melissa Kaae-Test on outer containment of of 14x20 IW pass.
Pressure Test4/25/20184/26/20184/26/2018PPART
DetailsEric Strole
IW Gravity Outfall From TNK401 to Civil Connection Phone #: ###-#### Inspection requested via web by Melissa Kaae-Section of IW tested is marked in test result book.
Pressure Test4/26/20184/26/20184/26/2018APART
DetailsEric Strole
IWN TNK01 and 24" Tank Interconnect to TNK02, TNK03, and TNK04 Phone #: ###-#### Inspection requested via web by Melissa Kaae-Section tested is marked in test result packet.
Pressure Test4/25/20184/25/20184/25/2018PCANC
DetailsEric Strole
IW Gravity Outfall From TNK401 to Civil Connection Phone #: ###-#### Inspection requested via web by Melissa Kaae
Other12/19/201712/20/201712/20/2017APART
DetailsEric Strole
IW - Double Contained to Off-Spec Phone #: ###-#### Inspection requested via web by Melissa Kaae-IW Double Contained stup in and out of building pass.
Other12/8/201712/8/201712/8/2017PCANC
DetailsEric Strole
IW Sinks Lvl 30 East Mech. IW Lvl. 20 East Mech Chem room Phone #: ###-#### Inspection requested via web by Melissa Kaae