BLD-Final | 9/14/2000 | 9/15/2000 | 9/15/2000 | A | PASS |
Jim Sly
|
|
|
Cal, ###-#### - I have the card & all approvals : ) OK for perm occ. 9/15/2000 10:13:57 AM
|
Permanent Occupancy | | 9/15/2000 | 9/15/2000 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/15/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8380 issued 9-15-00 to the D G Turf Farm and Nursery.
|
Telephone call | | | 9/8/2000 | | DONE |
|
|
|
Talked w/Avery Nelson re: status of occ. cert.
|
Fee Review-notes | 1/21/2000 | 1/21/2000 | 7/25/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/30/2000 | 5/30/2000 | 5/30/2000 | P | PASS |
Joe Tawney
|
|
|
Cal ###-#### Reinsp ok for perm. occ. 5/31/00 9:23:44 AM
|
BLD-Final | 5/30/2000 | 5/30/2000 | 5/30/2000 | P | PART |
Jim Sly
|
|
|
Cal ###-#### C/N..obtain perm. occ. status within 90 days...ok for temp. occ. 5/31/00 4:28:09 PM
|
Temporary occupancy | | | 5/30/2000 | | PART |
|
|
|
Temp. Occ. Cert. #4020 issued 5-30-00 to D G Turf Farm & Nursery.
|
FIRE-Final Inspection | 5/25/2000 | 5/26/2000 | 5/26/2000 | P | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 05/25/2000 at 16:45:18. Contact: ###-####.
|
BLD-Final | 5/25/2000 | 5/26/2000 | 5/26/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 05/25/2000 at 16:46:00. Contact: ###-####. NR 5/30/00 9:46:52 AM
|
FIRE-Conference | 5/24/2000 | 5/24/2000 | 5/24/2000 | P | PART |
Joe Tawney
|
|
|
cal--- ###-#### for conf Conf. on exiting and door hardware 5/25/00 9:00:33 AM
|
Code Occupancy Approval | | | 5/24/2000 | | FAIL |
|
|
|
Temporary - Bonded for stripping, h/c ramp & sign and some sprinkler system and landscaping.
|
BLD-Final | 5/22/2000 | 5/24/2000 | 5/23/2000 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 05/22/2000 at 19:02:15. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 05/23/2000 at 14:29:55.
|
FIRE-Final Inspection | 5/18/2000 | 5/19/2000 | 5/19/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 05/18/2000 at 16:17:33. Contact: ###-####. Final fail C/N issued. 5/22/00 10:57:14 AM
|
BLD-Framing/Rough-in | 4/27/2000 | 4/28/2000 | 4/28/2000 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/27/2000 at 16:40:35. Contact: ###-####. C/N ok per Sly. 5/1/00 3:25:53 PM
|
BLD-Framing/Rough-in | 4/25/2000 | 4/26/2000 | 4/26/2000 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 04/25/2000 at 16:47:20. Contact: ###-####. Shear ok 4/26/00 3:32:16 PM
|
BLD-Framing/Rough-in | 4/20/2000 | 4/20/2000 | 4/20/2000 | P | FAIL |
Tom Arcoraci
|
|
|
###-#### No app. plans ext. 4/21/00 9:23:05 AM
|
BLD-Conference | 4/14/2000 | 4/17/2000 | 4/17/2000 | A | PART |
Jim Sly
|
|
|
Framing conf. 4/18/00 10:38:18 AM
|
BLD-Framing/Rough-in | 4/7/2000 | 4/10/2000 | 4/10/2000 | A | PASS |
Jim Sly
|
|
|
flat work insp--- mike ###-#### Footing at front porch columns ok 4/11/00 11:18:42 AM
|
BLD-Foundation | 3/27/2000 | 3/28/2000 | 3/28/2000 | A | PASS |
Jim Sly
|
|
|
Mike Miller ###-####
|
Print Occupancy Form | | | 3/22/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/22/2000 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/22/2000 | | DONE |
|
|
|
|
Routing - FIRE | 3/17/2000 | 3/21/2000 | 3/21/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing Off Site - STRUCTURAL | 3/21/2000 | 3/21/2000 | 3/21/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 3/21/2000 | | 3/21/2000 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
Plan assigned to (JCB) | 1/27/2000 | | 3/21/2000 | | PASS |
Jason Blais
|
|
|
|
Routing - PLUMBING | 3/15/2000 | | 3/17/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/29/2000 | | 3/15/2000 | | PEND |
|
|
|
Permit approval dependent on structural, plumbing, and fire approvals. Plans routed to these depts.
|
Plan resubmittals received | | | 3/10/2000 | | DONE |
|
|
|
PLAN RESUBMITTALS RECEIVED FROM MIKE FAIRCHILD AND PINNACLE ENGINEERING A-1 THROUGH A-7 AND A-4.1 AND CACULATIONS, FORWARDED SAME TO JASON BLAIS. 3-10-00 DAR
|
Routing - FIRE | 2/25/2000 | 2/29/2000 | 2/29/2000 | | FAIL |
Bill Alexander
|
|
|
UFC issues (reference report).
|
Plan Review Completed(1st rev) | | | 2/29/2000 | | FAIL |
Bill Alexander
|
|
|
|
Plan resubmittals requested | | | 2/25/2000 | | PEND |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLAN CHECK | 1/31/2000 | | 2/25/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to fire dept.
|
Routing Off Site - STRUCTURAL | 1/27/2000 | | 2/15/2000 | | FAIL |
|
|
|
SENT PLANS TO CONSULTANTING ENGINEER VIA PDQ. 1/27/00 DAR
Structural report sent to architect. Plan resubmittals required for further review.
|
Plan resubmittals received | | | 2/4/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS SHEET C1.3, INCORPORATED THEM INTO THE PLANS. 2/4/00 DAR
|
Routing - PUBLIC WORKS | 2/1/2000 | | 2/1/2000 | | DONE |
|
|
|
|
Routing - PLANNING | 1/28/2000 | | 1/28/2000 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 1/27/2000 | | 1/28/2000 | | FAIL |
|
|
|
REQUIRES PROOF OF LEGAL LAND DIVISION AND INCOMPLETE LEGAL DESCRIPTION. PER BRIAN M. KMM
|
Pending Assignment by MYS | 1/21/2000 | | 1/27/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 1/27/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLANNING, PLAN CHECK, FIRE and STRUCTURAL ENGINEER.
|
Plans ACCEPTED BY PLAN TECH | | | 1/26/2000 | | DONE |
|
|
|
|
Application received | | | 1/21/2000 | | |
|
|
|
|
Routing - PLUMBING | 1/28/2000 | | | | FAIL |
|
|
|
|