Case Summary (BLD) | | | 6/16/2008 | | DONE |
|
|
|
|
Fee Review-notes | 1/26/2000 | 1/26/2000 | 3/30/2000 | | DONE |
|
|
|
|
Letter of compliance | | | 3/17/2000 | | DONE |
|
|
|
Letter of Compliance #18381 issued 3-17-00.
|
BLD-Final | 3/14/2000 | 3/15/2000 | 3/15/2000 | P | PASS |
|
|
|
jim ###-#### fn signed the perm col 03/16/2000 7:54:20 AM
|
BLD-Final | 3/6/2000 | 3/7/2000 | 3/7/2000 | A | FAIL |
|
|
|
Jim; ###-#### accessability floor diff at new restroom to new ramp and no exit sign at the main exit. not approved for occ. 3/8/00 8:47:32 AM
|
FIRE-Final Inspection | 3/6/2000 | 3/6/2000 | 3/6/2000 | P | PASS |
Rick Jackson
|
|
|
Jim; ###-####
|
BLD-Framing/Rough-in | 2/17/2000 | 2/18/2000 | 2/18/2000 | P | PASS |
Jim Storey
|
|
|
Jim Campell ###-#### Frame passed archieved ceiliing engineering C/N pending welding approval from special indp. 2/22/00 10:12:37 AM
|
Issue PAID IN FULL permit | | | 2/17/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/15/2000 | | 2/16/2000 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
Plan assigned to (JCB) | 1/27/2000 | | 2/16/2000 | | PASS |
Jason Blais
|
|
|
|
Plan resubmittals received | | | 2/16/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEET A2.0. ROUTED TO JASON BLAIS. KMM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/16/2000 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/16/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/16/2000 | | DONE |
|
|
|
|
Telephone call | | | 2/16/2000 | | DONE |
|
|
|
called John Price at ###-#### and gave him fees permit ready for pick up
|
Routing - FIRE | 2/14/2000 | 2/15/2000 | 2/15/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 2/15/2000 | | DONE |
|
|
|
PLAN RESUBMITTALS RECEIVED FROM PRICE ARCHITURE,NJOHN PRICE SHEETS A2.0 AND A3.0, FORWARDED SAME TO JASON BLAIS. 2/15/00 DAR
|
Plan Review Completed(1st rev) | | | 2/15/2000 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 1/31/2000 | | 2/14/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to fire dept.
|
Plan resubmittals requested | | | 2/14/2000 | | PEND |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLUMBING | 1/28/2000 | | 1/31/2000 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 1/28/2000 | | 1/28/2000 | | DONE |
|
|
|
|
Routing Off Site - C.D.H | 1/28/2000 | | 1/28/2000 | | DONE |
|
|
|
|
Pending Assignment by MYS | 1/26/2000 | | 1/27/2000 | | DONE |
Marlene Southard
|
|
|
|
Routing Off Site - C.D.H | 1/27/2000 | | 1/27/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/27/2000 | | DONE |
|
|
|
|
Plan routing begun/TENANTS | | | 1/27/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE.
|
Application received | | | 1/26/2000 | | |
|
|
|
|