Fee Review-notes | 2/1/2000 | 2/1/2000 | 5/16/2000 | | DONE |
|
|
|
additional value from subs
|
Permanent occupancy UNPAID FEE | | | 4/21/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8199 issued 4-21-00 to Applied materials, Inc.
|
FIRE-Final Inspection | 4/20/2000 | 4/20/2000 | 4/20/2000 | A | PASS |
Rick Jackson
|
|
|
|
BLD-Final | 4/19/2000 | 4/19/2000 | 4/19/2000 | P | PASS |
Jim Storey
|
|
|
###-#### final ok. 4/20/00
|
Permanent Occupancy | | 4/18/2000 | 4/18/2000 | | DONE |
|
|
|
|
Permanent Occupancy | | 4/18/2000 | 4/18/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/18/2000 | 4/18/2000 | 4/18/2000 | P | FAIL |
Rick Jackson
|
|
|
###-#### Sprinkler heads overspaced. 4/20/00 8:17:19 AM
|
BLD-Final | 4/18/2000 | 4/18/2000 | 4/18/2000 | P | FAIL |
Jim Storey
|
|
|
###-####
|
BLD-Framing/Rough-in | 3/28/2000 | 3/28/2000 | 3/28/2000 | P | PASS |
Jim Storey
|
|
|
###-####
|
BLD-Framing/Rough-in | 3/27/2000 | 3/27/2000 | 3/27/2000 | P | FAIL |
Tom Arcoraci
|
|
|
dan ###-#### See C/N 3/28/00 9:02:56 AM
|
BLD-Framing/Rough-in | 3/24/2000 | 3/24/2000 | 3/24/2000 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/24/2000 at 08:25:36. Contact: . work covered w/o approval all trades floor patch placed w/o inap rated sys. 3/24/00 4:47:18 PM
|
Issue PAID IN FULL permit | | | 3/13/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/1/2000 | | 3/10/2000 | | PASS |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM DENNIS FITZGEARLD,2 SETS OF SHEETS A-1 AND A-2 AND A ARCHITECT/ENGINEER OF RECORD FORM, FORWARDE DSAME TO JASON BLAIS. SHEET A-2 NOT SIGNED BY ARCHITECT, ADVISED DENNIS FITZGEARLD OF SAME. 3/6/00 DAR
Plans approved and taken to front desk.
|
Plan assigned to (JCB) | 2/4/2000 | | 3/10/2000 | | PASS |
Jason Blais
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/10/2000 | | |
|
|
|
|
Print Occupancy Form | | | 3/10/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/10/2000 | | DONE |
|
|
|
|
Telephone call | | | 3/10/2000 | | DONE |
|
|
|
left message gave dollar amount
|
Plan resubmittals received | | | 3/6/2000 | | DONE |
|
|
|
|
Routing - FIRE | 2/29/2000 | 3/1/2000 | 3/1/2000 | | PASS |
Sam Rogers
|
|
|
|
Plan Review Completed(1st rev) | | | 3/1/2000 | | FAIL |
Sam Rogers
|
|
|
|
Routing - PLAN CHECK | 2/7/2000 | | 2/29/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to fire dept.
|
Plan resubmittals requested | | | 2/29/2000 | | PEND |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PUBLIC WORKS | 2/4/2000 | | 2/7/2000 | | DONE |
|
|
|
|
Pending Assignment by MYS | 2/4/2000 | | 2/4/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 2/4/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 2/2/2000 | | DONE |
|
|
|
Architect/engineer of record form missing, Dennis Fiitzgearld will submit. 2/2/00 DAR
|
Application received | | | 2/1/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|