Permit Information
Permit NumberBLD00-00254
StatusFinaled
Name MCLEOD USA SWITCH FACILITY
Site Address 314 S 6TH ST
Project Name 
Customer Number 
ePlanReviewNo
Description
To remodel the West end, 19,762 sq.ft. area of an existing 44,973 sq.ft. warehouse building, separated from remaining 25,211 s.f. by existing 4-hour area separation wall, per approved plans on file. The tenant space use is for telephone exchange equipment, with support areas. Work to include new interior structural steel beams & columns with concrete pads for support of new HVAC RTU's. Interior wood frame walls with sheetrock cover; accessible ramp, landings, restrooms & route to required accessible areas. Rated corridor system construction per owners design, serves as part of FM200 operation requirements. NOTE: Interior demolition issued under BLD00-00262. Roofing permit issued under BLD99-03658 to Quality Tile Roofing. An FM 200 fire suppression system is being installed for protection of specialized equipment. DRH#99-0270; CUP#99-00163 (P.C.#088-00) / drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/24/20036/24/20036/24/2003 DONE
Permanent Occupancy 11/14/200011/14/2000 DONE
Details
BLD-Final11/13/200011/14/200011/14/2000APASS
DetailsCarl Dependahl
Paul, ###-#### ext. 1022, ok for c/o 11/14/2000 2:52:37 PM
Permanent occupancy  11/14/2000 DONE
Perm. Occ. Cert. #8469 issued 11-14-00 to the McLeod USA Switch Facillity.
Code Occupancy Approval  11/9/2000 PASS
Meets co9mpliance with DRH99-00270 Pass.
Fee Review-notes2/3/20002/3/200010/24/2000 DONE
BLD-Final8/31/20009/1/20009/1/2000PPART
Details
MATTHEW WUITSCHICK-- ###-#### -mid-afternoon, please signe dthe temp col 9/1/2000 4:21:54 PM
Temporary occupancy  9/1/2000 PART
Temp. Occ. Cert. #4057 issued 9-1-00 to the McLeod USA Switch Facility.
FIRE-Final Inspection8/31/20008/31/20008/31/2000PPASS
DetailsRick Jackson
Scheduled by Inspector: 409 On 8/31/2000
BLD-Conference8/29/20008/29/20008/29/2000APART
Details
Added by Inspector: 338 On 8/29/2000 with mat on the phone he is need ing bond for pz, and problem with public works may result in having the dry well re excavated to allow proper inspection.
FIRE-Alarm Testing8/17/20008/17/20008/17/2000AFAIL
DetailsRick Jackson
Added by Inspector: 409 On 8/17/2000 strobes not synchronized in FM areas; batteries not installed; dialer not ready; smoke detectors at supply air diffusers
BLD-Framing/Rough-in8/2/20008/2/20008/2/2000PPART
Details
ceiling grid matt wuitschick ###-#### ok to drop in ceiling tiles 8/2/2000 4:04:26 PM
BLD-Framing/Rough-in5/11/20005/15/20005/15/2000PPART
Details
Scheduled by a contractor via Hello! on 05/11/2000 at 13:06:43. Contact: ###-####. made ok to cover behind other agencies, ceilings painted and in process of installing light fixtures and ele panels and switch gear 5/15/00 4:13:31 PM
BLD-Framing/Rough-in4/24/20004/24/20004/24/2000PPART
Details
Scheduled by Inspector: 338 On 4/24/00 ok to cover with ele and plm ok's 4/24/00 3:48:33 PM
BLD-Framing/Rough-in4/20/20004/20/20004/20/2000PPART
Details
###-#### made ok to cover with ele and plm signoffs 04/24/2000 7:25:07 AM
BLD-Concrete3/31/20003/31/20003/31/2000PPART
Details
###-#### r-bars placed ok with sp insp approvals 03/31/2000
BLD-Conference3/23/20003/23/20003/23/2000PPART
Details
pre-const insp--matt ###-#### need to inspect the engineered required attachments for the roof diaphram 03/24/2000 8:47:11 AM
Issue PAID IN FULL permit  3/23/2000 DONE
Inspection Record Card- Bld  3/22/2000 DONE
Print Occupancy Form  3/22/2000 DONE
Telephone call  3/22/2000 DONE
TALKED TO MATT TO VERIFY PLANS ARE READY
Routing - PLAN CHECK3/16/2000 3/21/2000 PASS
RECEIVED RESUBMITTALS & INSERTED INTO PLANS. QUICK REVIEW WITH PERRY PAINE, STRUCTURAL INSPECTOR. ROUTING FOR ISSUANCE OF PERMIT.
Plan resubmittals received  3/21/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM TKDA TWO SETS OF SHEETS C-1,LA-1, LA-2, A-1, A-4,A-6,M-5,E-9. FORWARDED SAME TO DAN STUART. 3/21/00 DAR
PLANS/APPL TAKEN TO FRONT DESK  3/21/2000 PASS
ROUTING TO FRONT DESK FOR ISSUANCE OF PERMIT.
Plan assigned to (DRS)2/4/2000 3/21/2000 PASS
DetailsDan Stuart
3/21/2000 17:51:52 DRS - activity updated through activity BLDA022 from case BLD00-00254.
Routing - FIRE3/15/20003/16/20003/16/2000 PASS
DetailsBill Alexander
Telephone call  3/15/2000 DONE
Conference call with Bryan Hanson, Joel Rector, Mike Stek & Tony May concerning the remaining plan review clarifications to be provided for review and approval for this project. I will route the plans back to Fire Code analysis for re-review while waitin for response.
Telephone call  3/14/2000 DONE
Phone call with Peter Brozek, TKDA, asking how the plan review was going on resubmittals. He had gathered the project designers to a conference room (mechnical, electrical, structural & design) to review questions he had heard that I had concerning the resubmittals. I told him I was no through with the re-review but most items I had noted so far were items the cover letter said I received in the re-submittal and had no been part of the package, or changes that were said to have been made to or noted on the plans but were not. We reviewed some of the questions, sheets that were missing and mechanical sheet details for fire-smoke dampers and placement. After a short review, Peter appologized for the misinformation given and I said I would fax a copy of my comments to him on 3/14/00 and we could talk about them on 3/15/00 to clarify what is required to complete my portion of the review.
Plan resubmittals requested  3/14/2000  
Faxed copy of comments concerning review of first re-submittals, noting items not addressed or not included or still incomplete, made on TKDA's response cover letter. Additional clarifications and details required. Will also review by phone tommorrow at noon as prearranged by phone today.
Routing - PLAN CHECK3/2/2000 3/14/2000 FAIL
Inserted the resubmittal sheets as part of plans & reviewed for response to plan review comments. Found that items said to have been sent as part of package, Sheet C-1, LA-1 & LA-2 were not sent; some items said to have been removedd from or noted on plans were not; noted differences between structural engineering design calcs & details and details put on plans; etc. Re-submittals for further clarification still required. Will route plans to fire code analyst for their re-review while waiting for response.
Plan resubmittals received  3/13/2000 DONE
RECEIVED REVISED SHEETS S-1, S-2, S-3, S-1, S-2, S-3, LA-3, A-1, A-2, A-3, A-4, A-5, A-6, M-2, M-4, M-5, M-7, M-8, E-1, E-2, E-3, E-4, E-5, E-5, E-8, E-9, E-10, E-11, E-12, E-13, E-14, E-15. ONE COPY OF RESPONSE LETTER AND TWO COPIES OF STRUCTURAL DESIGN CALCULATIONS. ROUTED TO DAN S. KMM
Routing - FIRE3/2/20003/2/20003/2/2000 FAIL
DetailsBill Alexander
Plans do not coordinate for UFC review. Need Hydrant flow verification.
Routing - PLAN CHECK2/29/2000 3/2/2000 FAIL
Resubmittals required. Mailed & faxed copy of plan review comments to Peter Brozek, TKDA, for response. Routing plans to Fire Code analysts for review.
Plan resubmittals requested  3/2/2000 FAIL
Faxed & amiled copy of plan review comments to Peter Brozek, TKDA, for his response & resubmittal of corrected clarified plans.
Plan Review Completed(1st rev)  3/2/2000 FAIL
DetailsBill Alexander
Routing - PLUMBING2/22/2000 2/29/2000 DONE
Routing - PLANNING2/9/2000 2/22/2000 DONE
Passed on to DR. MARTY SANTOYA PASSED THIS PROJECT ON 2/22/00 DAR
Plan resubmittals received  2/11/2000 DONE
RECEIVED ONE SET OF PLAN RESUBMITTALS FROM TKDA SHEETS T-1, A-1,LA-1 AND LA-3, FORWARDED SAME TO DAN STUART. 2/11/00 DAR
Routing - PUBLIC WORKS2/4/2000 2/9/2000 PASS
Telephone call  2/8/2000 DONE
Called to inquire about one copy of resubmittals we received for sheet T-1; A-1; LA-1; LA-3 showing revisions. I ask Todd Erdelberg??? if the plans were in response to a question asked by other reviewing agency, and if so who so I could get the plan to them. If not I would need an additional copy with a cover letter stating what was being changed and the area to be reviewed for change. I reviewed the concerns I had about latch side clearance; landing size at door; handrails for accessible ramps to include height, return & extensions; the intermediate guardrail spacing to be such that a 4" sphere can not pass through. Ask him to have Brian Hanson call me if he had questions. I would need to stamped copies for review an insertion into plans.
2/8/2000 - 2 p.m. - Brian Murphy, PW came and got me to review questions he had with the McCleod site project and the means & design of handling the runnoff of the parking area and any other areas that drained into the proposed parking area. Brian ask that I have a representative of TKDA Architects / Engineers that designed or knows about the drainage design, call him to review. Brian needs three additional copies of the site plan drainage design details & clacs after discussion with Craig Ruhland, designer. Mr. Ruhland to call Mr. Murphy tommorrow (2/9/00) per Mr.Brian Hanson, TKDA.
Received Certificate of Value  2/7/2000 DONE
Received signed cert. of value, and signed arch./eng. record declaration form. Put one in file and gave two to Dan S. KMM
Plan resubmittals received  2/7/2000 DONE
RECEIVED ONE COPY OF REVISED SHEETS T-1, A-1, LA-1, LA-3 SHEETS WERE NOT STAMPED OR SIGNED. ROUTED TO DAN STUART. KMM
Pending Assignment by MYS2/3/2000 2/4/2000 DONE
DetailsMarlene Southard
Plan routing begun/TENANTS  2/4/2000 DONE
Route to PUBLIC WORKS, PLANNING, PLUMBING, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  2/3/2000 DONE
DENSITY REDUCTION SURVEY IS NOT RECORDED, PLANS TO BE PROCESSED AS IF ALL INFORMATION WAS IN AND CORRECT. PERMIT WILL NOT BE ISSUED UNTIL ALL REQUIRED CONDITIONS ARE MET. 2/3/00 DAR
Application received  2/3/2000