Permit Information
Permit NumberBLD00-00255
StatusFinaled
Name NEW SONG COMMUNITY CHURCH
Site Address 415 E PARKCENTER BLVD Unit: 108
Project NamePARKCENTER MALL- #108
Customer Number 
ePlanReviewNo
Description
Remodeling an existing 2,212 sq.ft. tenant space in existing covered mall building and changing use from office to A-3 assembly (church) and B (classrooms) per approved plans on file. Work to include demolishing some interior walls-doors-windows, new accessible restroom, accessible upgrades, new interior walls with doors, interior finish, suspended ceiling work, fire sprinkler work, some mechanical work including providing new added ventilation system, some plumbing work, and some electrical work. NOTE: This building is fully fire sprinklered for area increase. (P.C.#086-00) JCB CUP99-00151
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes2/3/20002/3/20003/22/2002 DONE
Permanent occupancy UNPAID FEE  2/7/2002 DONE
Perm. Occ. Cert. #9024 issued 2-7-02 to New Song Community Church.
Permanent Occupancy 2/6/20022/6/2002 DONE
Details
BLD-Final2/5/20022/6/20022/6/2002APASS
DetailsJim Storey
###-#### please call so he can meet you final ok card on site. 2/6/2002 9:54:37 AM
Code Occupancy Approval2/6/20022/6/20022/6/2002APASS
DetailsWm. Michael Meloy
Scheduled by Inspector: WMM On 2/6/2002 10:17:31 AM
FIRE-Final Inspection1/28/20021/28/20021/28/2002PPASS
DetailsRick Jackson
JIM , PLEASE CALL - DAVID ###-#### SO THAT HE CAN MEET YOU THERE ...DLD
CHANGE STATUS TO (ISS)  10/26/2001  
BLD-Framing/Rough-in8/9/20008/10/20008/10/2000APART
DetailsRuss Owen
David Reid ###-#### Hallway only needs plumbing prior to cover at restrooms. 8/11/2000 9:21:05 AM
BLD-Framing/Rough-in8/1/20008/1/20008/1/2000PPART
DetailsJim Storey
ALSO FIRE INSP FOR PM--DAVID-- ###-#### FR--CALL 1ST BEFORE INSP temp occ ok for mis critearia. 8/1/2000 2:25:55 PM
FIRE-Sprinkler Rough-in8/1/20008/1/20008/1/2000PPART
DetailsRick Jackson
FOR TP OCC--###-####-DAVID FIRE R/I--CALL 1ST BEFORE INSP okay to occupy - wall not installed per plans - may need sprinkler adjustments 8/1/2000 3:35:07 PM
FIRE-Final Inspection5/8/20005/15/20005/15/2000PFAIL
DetailsRick Jackson
David Reid- ###-#### please call first Exit signs; extinguisher. 5/17/00 1:42:22 PM
BLD-Final5/8/20005/15/20005/15/2000PFAIL
DetailsJim Storey
David Reid- ###-#### please call first
FIRE-Final Inspection5/9/20005/9/20005/9/2000AFAIL
DetailsRick Jackson
Exit sign; owner to review plans.
Issue PAID IN FULL permit  5/8/2000 DONE
Print Occupancy Form  3/27/2000 DONE
Inspection Record Card- Bld  3/27/2000 DONE
Telephone call  3/27/2000 DONE
left message plans were ready gave dollar amount
Routing - FIRE3/24/20003/24/20003/24/2000 PASS
DetailsSam Rogers
3/24-Bldg issues regarding exiting resolved.SLR
Routing - PLAN CHECK3/24/2000 3/24/2000 PASS
Plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  3/24/2000  
Plan assigned to (JCB)2/7/2000 3/24/2000 PASS
DetailsJason Blais
Routing - PLAN CHECK3/6/2000 3/24/2000 PEND
Permit approval dependent on fire dept. approval. Plans routed to fire dept.
Plan resubmittals received  3/21/2000 DONE
received two copies of revised sheets A0.0 A1.0, A2.0, A3.0. ROUTED TO JASON B. KMM
Plan resubmittals received  3/17/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM BRUCE POE, ARCHITECT, TWO SETS OF SHEETS A0.0, A1.0, A2.O, A3.0. FORWARDED SAME TO JASON BLAIS. 3/17/00 DAR
Routing - FIRE3/2/20003/3/20003/3/2000 FAIL
DetailsBill Alexander
Building issues which relate to egress.
Plan Review Completed(1st rev)  3/3/2000 FAIL
DetailsBill Alexander
Plan resubmittals requested  3/2/2000 PEND
Plan resubmittals and response required for further review.
Routing - PLAN CHECK2/18/2000 3/2/2000 FAIL
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to fire dept.
Routing - PLANNING2/9/2000 2/16/2000 PASS
Routing - PUBLIC WORKS2/7/2000 2/9/2000 PASS
Pending Assignment by MYS2/3/2000 2/4/2000 DONE
DetailsMarlene Southard
Plan routing begun/TENANTS  2/4/2000 DONE
Route to PUBLIC WORKS, PLANNING, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  2/3/2000 DONE
Received Certificate of Value  2/3/2000 DONE
Application received  2/3/2000  
Recd Pcfee & Taken To Pln CK     
Telephone Call