Permit Information
Permit NumberBLD00-00257
StatusExpired
Name ROCKY MOUNTAIN COMMUNICATIONS
Site Address 1501 S FEDERAL WAY (4TH FLR)
Project NameVIEW POINT-3RD/4TH FLRS
Customer Number 
ePlanReviewNo
Description
(ROCKY MOUNTAIN COMMUNICATIONS) This building is NOT fire sprinklered. To construct building improvements on the 3rd (6,400 square feet) and 4th (6,400 square feet) floors of an existing 5 story building. Only the 4th floor will be occupied by this office tenant. Work is to include upgrading 4 existing restrooms to be accessible to the disabled, constructing interior nonbearing walls, repairing openings in floors, sealing joints between floors and exterior walls, modifying the mechanical system, and installing suspended ceilings all per approved drawings and plan review conditions on file. PC-087-00 **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes2/3/20002/3/20007/15/2002 DONE
BLD-Final4/27/20004/28/20004/28/2000APART
DetailsJim Storey
Ken Beck ###-#### temp ok pending saftey glazing and plump. 4/28/00 9:55:15 AM
FIRE-Final Inspection4/26/20004/27/20004/27/2000APASS
DetailsRick Jackson
###-####
BLD-Framing/Rough-in4/6/20004/7/20004/7/2000APASS
DetailsJim Storey
###-#### ceiling grid
BLD-Framing/Rough-in3/24/20003/27/20003/27/2000APART
Details
ken ###-#### ok to cover walls need full ceiling grid insp 03/27/2000 3:42:41 PM
Override - Parcel Holds  3/21/2000  
Issue PAID IN FULL permit  3/21/2000 DONE
PLANS/APPL TAKEN TO FRONT DESK  3/20/2000 PASS
Inspection Record Card- Bld  3/20/2000 DONE
Print Occupancy Form  3/20/2000 DONE
Telephone call  3/20/2000 DONE
TALKED TO JERRY TEAL TO VERIFY PLANS ARE READY
Plan assigned to (CJW)2/7/2000 3/20/2000 PASS
DetailsCarl Westfall
3/20/00 13:48:44 CJW - activity updated through activity BLDA022 from case BLD00-00257.
Routing - PLAN CHECK3/9/2000 3/20/2000 PASS
Plan Reviewer's activity  3/20/2000 PASS
Drawings approved, with conditions, after resubmittal review.
Plan resubmittals received  3/17/2000 PEND
RECEIVED PLAN RESUBMITTALS FROM JERRY TEAL ARCHITECT, TWO OF SHEETS A2-1 AND A2-2, FORWARDED SAME TO CARL WESTFALL. 3/17/00 DAR
Routing - FIRE3/6/20003/8/20003/8/2000 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  3/8/2000  
DetailsBill Alexander
Failed plan check, Carl Westfall.
Routing - PLAN CHECK2/9/2000 3/3/2000  
Plan Reviewer's activity  3/3/2000  
UBC plan review started March 1, 2000 and finished March 3, 2000. A response from the architect is required. See the conditions list.
Plan resubmittals received  2/22/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM TEALY WHITWORTH ARCHITECTS,PLUMBING AND MECHANICAL SHEETS, FORWARDED SAME TO CARL WESTFALL. 2/22/00 DAR
Routing - PUBLIC WORKS2/7/2000 2/9/2000 PASS
Pending Assignment by MYS2/3/2000 2/7/2000 DONE
DetailsMarlene Southard
Plan routing begun/TENANTS  2/7/2000 DONE
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  2/4/2000 DONE
Received Certificate of Value  2/4/2000 DONE
Application received  2/3/2000  
Case Summary (BLD)     
Plan Review Report