Permit Information
Permit NumberBLD00-00286
StatusFinaled
Name CM COMPANY
Site Address 2081 W COMMERCE AVE
Project NameBOISE CASCADE-HANGER
Customer Number 
ePlanReviewNo
Description
TO CONSTRUCT A NEW 61, 505 SQ. FT., TYPE II-N, FULLY FIRE SPRINKLERED TWO STORY AIRCRAFT PASSENGER AND SERVICE HANGARS WITH OPERATIONS OFFICES, STORAGE AREAS, AND SHOP AREAS FOR BOISE CASCADE CORPORATION. BUILDING IS SEPARATED BY A TWO HOUR AREA SEPARATION WALL FOR AREA. FIRE SPRINKLERS ARE DESIGNED IN ACCORDANCE WITH NFPA 409. GRADING UNDER PERMIT BLD00-00986, FOUNDATION UNDER PERMIT BLD00-01303. FIRE SPRINKLERS USED FOR AREA. FIRST FLOOR 55,461 SQ. FT. SECOND FLOOR IS 6,044 SQ. FT.
DRH99-00203 PC#100-00
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes2/8/20002/8/20003/21/2001 DONE
Permanent occupancy UNPAID FEE  3/8/2001 DONE
Perm. Occ. Cert. #8588 issued 3-8-01 to the Boise Cascade Hangar.
Permanent Occupancy 3/7/20013/7/2001 DONE
Details
BLD-Final3/6/20013/7/20013/7/2001APASS
DetailsJim Storey
fn occ-- bruce--- ###-####
FIRE-Final Inspection2/28/20013/2/20013/2/2001APASS
DetailsRick Jackson
Scheduled by Inspector: 409 On 2/28/2001 3:28:20 PM retest alarms
BLD-Final3/2/20013/2/20013/2/2001PFAIL
DetailsJim Storey
###-#### door hardware and closers. 3/5/2001 10:02:10 AM
FIRE-Final Inspection2/27/20012/28/20012/28/2001PFAIL
DetailsRick Jackson
###-#### alarms not working properly will retest on 3/2/01 2/28/2001 3:37:49 PM
BLD-Conference2/5/20012/6/20012/6/2001PPASS
DetailsJim Storey
Bruce ###-#### a prearranged conference at 1:30 reviewed hardware isues for compliance/ observed fire pump test. 2/6/2001 5:19:07 PM
Code Occupancy Approval  1/30/2001 PASS
all conditions have been met that I was able to verify with snow on ground, found parking lot marked and vegitation all in place, final occupancy signed off.
BLD-Framing/Rough-in1/23/20011/24/20011/24/2001APART
DetailsJim Storey
###-#### ceilling ok all but wall at battery rm needs perimtor wires and fire stopping. 1/24/2001 12:18:00 PM
BLD-Framing/Rough-in12/6/200012/7/200012/7/2000APART
DetailsJim Storey
###-####bld#3 ok for ceilling drop pending fire sprinklre rough in. 12/7/2000 10:57:08 AM
BLD-Framing/Rough-in11/9/200011/13/200011/13/2000APART
DetailsJim Storey
BRUCE ###-#### FR INSP
BLD-Foundation10/26/200010/26/200010/26/2000PPART
DetailsJim Storey
grade beam foundation bruce ###-####placed w/special insp.pending report. 10/26/2000 3:51:15 PM
BLD-Concrete10/18/200010/19/200010/19/2000APART
DetailsJim Storey
###-#### grade beam placed w/special insp. pending report. 10/19/2000 10:36:50 AM
BLD-Foundation10/16/200010/17/200010/17/2000APART
DetailsJim Storey
grade beam Bruce ###-#### placed w/spec 10/17/2000 9:56:43 AMial insp. pending report. 10/17/2000 9:57:02 AM
BLD-Footing10/13/200010/13/200010/13/2000PPART
DetailsJim Storey
FT INSP BRUCE ###-#### covered w special insp. pending report. 10/13/2000 4:35:19 PM
BLD-Framing/Rough-in10/11/200010/11/200010/11/2000PFAIL
DetailsJim Storey
bruce ###-####oversized firedoor/flushbolts approved by plan review not allowed. 10/11/2000 4:28:06 PM
BLD-Footing10/2/200010/3/200010/3/2000APART
DetailsJim Storey
###-#### placed with special insp. pend report. 10/3/2000 3:44:55 PM
BLD-Framing/Rough-in10/2/200010/2/200010/2/2000PPART
DetailsJim Storey
###-#### shafts 3 locations ok thru horrizontal assembly. 10/2/2000 9:16:21 AM
BLD-Framing/Rough-in9/20/20009/20/20009/20/2000PPART
DetailsJim Storey
###-#### framing west end and ceilling of h occ ok for cover pending others .9/20/2000 5:20:05 PM 9/20/2000 5:21:06 PM
BLD-Framing/Rough-in9/20/20009/20/20009/20/2000PPART
DetailsJim Storey
###-#### framing west end and ceilling of h occ ok for cover pending others .9/20/2000 5:20:05 PM 9/20/2000 5:21:06 PM
BLD-Concrete9/12/20009/13/20009/13/2000APART
DetailsJim Storey
bruce ###-#### masonary covered with special insp. pending report. 9/13/2000 8:02:51 AM
BLD-Concrete9/11/20009/12/20009/12/2000APART
DetailsJim Storey
masonry insp Bruce ###-#### pending s/i report. 9/12/2000 11:17:46 AM
BLD-Conference9/11/20009/12/20009/12/2000AFAIL
DetailsJim Storey
bruce ###-#### for conf engineering changes must have submatals. wall rated location change submitals req./ 2 hr parepet change submatal required. 9/12/2000 11:19:38 AM
BLD-Foundation8/28/20008/29/20008/29/2000APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/28/2000 at 15:29:35. Contact: . placed with special insp. 8/29/2000 7:54:49 AM
BLD-Footing8/28/20008/28/20008/28/2000PPART
DetailsJim Storey
ft bruce ###-#### covered w/s/i. 8/28/2000 6:12:02 PM
BLD-Foundation8/21/20008/22/20008/22/2000APART
DetailsJim Storey
masonry Bruce ###-#### placed w/spical insp. pending report. 8/22/2000 10:25:37 AM
BLD-Foundation8/22/20008/22/20008/22/2000PPART
DetailsJim Storey
###-#### covered by special insp. pending report. 8/22/2000 2:59:06 PM
BLD-Concrete8/18/20008/18/20008/18/2000PPART
DetailsJim Storey
masonary Bruce ###-#### placed in the am. 8/18/2000 2:38:24 PM
BLD-Concrete8/15/20008/16/20008/16/2000PPART
DetailsJim Storey
BRUCE--###-#### CONCRET covered w/s/i 8/16/2000 2:01:32 PM
BLD-Conference8/14/20008/15/20008/15/2000APART
DetailsJim Storey
BRUCE-- ###-#### CONF-- genral walk thru west side framing and steel erection in progess. 8/15/2000 11:02:47 AM
BLD-Foundation8/9/20008/10/20008/10/2000APART
Details
Bruce ###-#### masonry and foundation with 8/10/2000 2:38:40 PM footings for retaining wall at the north and east elev. bond at the 12 ft 8/10/2000 3:08:40 PM
BLD-Foundation8/8/20008/9/20008/9/2000APART
Details
bruce---- ###-#### masonary insp pending sp isp approvals 8/9/2000 11:11:29 AM
BLD-Foundation8/9/20008/9/20008/9/2000PPART
Details
bruce--- ###-#### masonary insp no answer from bruce 8/9/2000 6:33:27 PM
BLD-Foundation8/7/20008/8/20008/8/2000APART
Details
masonry Bruce ###-#### pending sp insp approvals 8/8/2000 2:05:26 PM
Plan resubmittals received  8/3/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM LOMBARD CONRAD, FORWARDE SAME TO DAVID MILLER AND MIKE OTTO, THREE SETS OF LPE - 1 AND CACULATIONS. 8/3/00 DAR
BLD-Foundation7/31/20007/31/20007/31/2000PPART
DetailsJim Storey
bruce-- ###-#### found insp elavator pit walls ok. 7/31/2000 2:04:13 PM
BLD-Conference7/26/20007/28/20007/28/2000APASS
DetailsJim Storey
Bruce ###-#### conference at 9am 2hr resole of code idems bld and fire. 7/28/2000 11:06:35 AM
BLD-Footing7/27/20007/28/20007/28/2000APASS
DetailsJim Storey
###-####
BLD-Foundation7/21/20007/24/20007/24/2000APART
DetailsJim Storey
masonry Bruce ###-#### pending s/i report. 7/24/2000 12:36:10 PM
BLD-Foundation7/21/20007/24/20007/24/2000PPART
DetailsJim Storey
Bruce ###-####
BLD-Foundation7/20/20007/21/20007/21/2000APART
DetailsJim Storey
masonry Bruce ###-#### pending report. 7/21/2000 9:59:23 AM
BLD-Concrete7/17/20007/18/20007/18/2000APART
DetailsJim Storey
###-#### pending report s/i. 7/18/2000 3:16:50 PM
BLD-Concrete7/14/20007/17/20007/17/2000APASS
DetailsJim Storey
###-#### slab on grade ok pending report on concrete. 7/17/2000 9:21:55 AM
BLD-Concrete7/13/20007/14/20007/14/2000PPART
DetailsJim Storey
BRUCE--- ###-#### CONCRETE pending s/i report. 7/14/2000 2:29:46 PM
BLD-Foundation7/13/20007/13/20007/13/2000PPART
DetailsJim Storey
masonary bruce ###-#### pending s/i report. 7/13/00 1:10:28 PM
BLD-Concrete7/11/20007/12/20007/12/2000PPART
DetailsJim Storey
###-#### RE-BAR INSP
BLD-Concrete7/10/20007/11/20007/11/2000APART
DetailsJim Storey
bruce ###-#### masonary groute insp pending s/i report. 7/11/00 1:46:22 PM
BLD-Concrete7/7/20007/10/20007/10/2000APART
DetailsJim Storey
###-#### pending report s/i 7/10/00 10:41:54 AM
BLD-Foundation7/6/20007/7/20007/7/2000APART
Details
re-bar for grout Bill ###-#### pending sp insp approvals 7/7/00 12:26:40 PM
BLD-Concrete7/7/20007/7/20007/7/2000PPART
Details
###-#### with psecial insp approvals 7/7/00 3:39:14 PM
BLD-Concrete7/5/20007/6/20007/6/2000APART
Details
###-#### with sp insp pending 7/6/00 9:04:14 AM
BLD-Footing7/5/20007/5/20007/5/2000PPART
Details
Bill ###-#### with sp insp pending 7/6/00 9:03:17 AM
BLD-Foundation6/30/20007/3/20007/3/2000APART
DetailsJim Storey
###-#### pending s/i report 7/10/00 10:39:15 AM
BLD-Concrete6/29/20006/30/20006/30/2000APART
DetailsJim Storey
masonary ###-####
BLD-Foundation6/29/20006/29/20006/29/2000PPART
DetailsJim Storey
bruce ###-#### foundation wall
BLD-Footing6/27/20006/28/20006/28/2000APART
DetailsJim Storey
bRUCE ###-#### pending report s/i. 6/27/00 2:32:12 PM pending report s/i. 6/28/00 10:29:19 AM
BLD-Concrete6/27/20006/28/20006/28/2000APART
DetailsJim Storey
masonary ###-#### bruce pending report s/i. 6/27/00 2:31:46 PM pending report s/i 6/28/00 10:28:44 AM
BLD-Concrete6/26/20006/27/20006/27/2000APART
DetailsJim Storey
masonry ###-#### pending report. 6/27/00 2:29:51 PM
BLD-Foundation6/23/20006/26/20006/26/2000APART
DetailsJim Storey
bruce-- ###-#### masonary insp
(F) Reprint permit  6/20/2000 DONE
Issue PAID IN FULL permit  6/19/2000 DONE
Telephone call  5/25/2000 DONE
left mess for david moe that permit is ready
Routing - PLAN CHECK5/23/2000 5/24/2000 PASS
PLANS/APPL TAKEN TO FRONT DESK  5/24/2000 DONE
Inspection Record Card- Bld  5/24/2000 DONE
Print Occupancy Form  5/24/2000 DONE
Plan assigned to (MLO)3/3/2000 5/24/2000 PASS
DetailsMike Otto
5/24/2000 10:09:38 MLO - activity updated through activity BLDA022 from case BLD00-00286.
Plan Reviewer's activity  5/23/2000 FAIL
SENT FAX TO TOM BROPHY - HAVE NOT RECEIVED
Plan resubmittals received  5/23/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM LOMBARD CONRAD ARCHITECTS, TOM BROPHY THREE SETS OF SHEETS M1.2,E2.0BF, E2.0BL, FORWARDED SAME TO MIKE OTTO. 5/23/00 DAR
Plan resubmittals received  5/19/2000 DONE
RECEIVED THREE COPIES OF REVISED ARCH. DRAWINGS A2.0, A2.1, A2.2, A2.3, P1.1. ONE COPY OF LCA CORRECTION RESPONSE LETTER, ONE FLEMING STEEL COMPANY HANGAR DOOR RESPONSE LETTER AND FOUR COPIES OF ENGINEERING INC. AND EDIAM ASSOC. SUPPLEMENTAL SKETCHES. ROUTED TO MIKE O. KMM
Routing - PLAN CHECK5/19/2000 5/19/2000 FAIL
architect submitted revised mechancial and electrical plans on letter size paper with no stamps and signatures from the engineers. Architect and mechanical engineer contacted by phone. MLO
Plan resubmittals requested  5/19/2000 FAIL
.Provide full size stamped and signed mech. and electrical sheets. MLO
Routing - FIRE5/16/20005/16/20005/16/2000 PASS
DetailsBill Alexander
Upon approval of UBC pending requirements.
Received Certificate of Value  5/10/2000 DONE
RECEIVED REVISED CERT. OF VALUE MINUS FOUNDATION. * PROJECT VALUE $5,334,464 ELECT. $511,317 PLUMB. $545,1888 MECH. $291,316 FIER SPRINKLER $325,610 PUT ONE IN FILE AND ROUTED TWO TO MIKE O. KMM
Routing - PLAN CHECK5/6/2000 5/8/2000 FAIL
PLAN CORRECTIONS GENERATED FROM REQUIREMENTS IN HAZARDOUS MATERIAL ANALYSIS WHICH WERE NOT INCLUDED IN THE PLANS. CORRECTIONS MAILED AND FAXED TO ARCHITECT.
Additional plans submitted  5/4/2000 DONE
RECEIVED HAZARDOUS MATERIALS SURVEY FROM LOMBARD - CONRAD, TWO COPIES, FORWARDED SAME TO MIKE OTTO, 5/4/00 DAR
Routing Off Site - STRUCTURAL5/1/2000 5/3/2000 PASS
SENT RESUBS MITTALS TO CONSULTANTING ENGINEER VIA PDQ
Meeting  5/3/2000 PEND
Had meeting with Tom Brophy and Sam Burrows to go over second exit from repair shop. To meet code building design needs to be changed. Architect presented a modification using alarms when exit door becomes blocked. Building Official rejected modifications. Architect contacted by fax with Building Officials determination. MLO
Plan resubmittals requested  5/1/2000 FAIL
EXIT FROM H OCCUPANCY AND HAZMAT INFO
Plan resubmittals received  4/28/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM TOM BROPHY, LOMBARD CONRAD AARCHITECTS, SMALL DOCUMENTS,STRUCTURAL CACULATIONS, THREE SETS OF SHEETS A2.1,A2.3,S2.1.S2.2,S2.4,S2.5,S4.1,S5.1, S5.2. FORWARDED SAME TO MIKE OTTO. 4/28/00 DAR
Routing - PLAN CHECK4/28/2000 4/28/2000 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT ON EXIT FROM H OCCUPANCY. STILL LACKING HAZMAT INFO. MLO
Routing - FIRE4/13/20004/14/20004/14/2000 FAIL
DetailsBill Alexander
Still outstanding UFC issues missing.
Plan resubmittals requested  4/13/2000 FAIL
ubc corrections
Routing - PLAN CHECK4/12/2000 4/13/2000 FAIL
resubs- ADDITONAL CORRECTIONS ON EXITING, OCCUPANCY SEPARATION AND LACK OF HAZMAT DATA AS REQUESTED IN PRIOR REVIEW. MLO
Plan resubmittals requested  4/12/2000 FAIL
additional structural corrections.
Routing Off Site - STRUCTURAL4/3/2000 4/12/2000 FAIL
Contacted pdq to take resubmitted plans received on 3-30-00 to outside engineering. KMM Received E-Mail with corrections from engineer. Faxed corrections to architect. MLO
Plan resubmittals received  4/11/2000 DONE
RECEIVED THREE COPIES OF REVISED ARCHITECTURAL, STRUCTURAL, MECHANICAL, AND ELECT. DRAWINGS. ONE COPY OF LCA CORRECTION RESPONSE LETTER. ONE COPY OF REVISED 08817 SPECIFICATION TO PROJECT MANUAL. ONE COPY OF BOISE CASCADE RESPONSE LETTER. AND ONE COPY OF ABS RESPONSE LETTER. ROUTED TO MIKE O. KMM
Routing - PLUMBING4/3/2000 4/6/2000 DONE
PLANS RETURNED TO PLAN CHECK
Routing - FIRE3/24/20003/30/20003/30/2000 FAIL
DetailsBill Alexander
Many UFC and some NFPA 409 fire related issues.
Plan Review Completed(1st rev)  3/30/2000 FAIL
DetailsBill Alexander
Meeting  3/30/2000 PEND
HAD MEETING WITH ARCHITECT AND FIRE DEPT. WENT OVER PLAN REVIEW CORRECTION LIST FROM 3/24/2000. MLO
Plan resubmittals received  3/30/2000 DONE
RECEIVED ONE COPKY OF ENGINEERING INC. RESPONSE LETTER. THREE AHJ STRUCTURAL CALC'S & RESPONSE LETTER. THREE STAPLEY ENG. STRUCT. REVIEW CALC'S FOR HANGER DORRS. ONE COPY OF BOISE CASADE AVIATION OPERATIONS MSDS SHEET. THREE FLEMING STEEL DRAWINGS FOR HANGAR DOORS AND THREE AHJ STRUCTURAL DRAWINGS ( REVISED). ROUTED TO MIKE O. KMM
Plan resubmittals requested  3/24/2000 FAIL
UBC CORRECTIONS
Routing - PLAN CHECK3/15/2000 3/24/2000 FAIL
CORRECTIONS FAXED AND MAILED TO ARCHITECT. MLO
Routing - PLANNING3/9/2000 3/15/2000 PASS
Approve per DRH99-203
Plan resubmittals requested  3/15/2000 FAIL
STRUCTURAL CORRECTIONS.
Plan resubmittals received  3/14/2000 DONE
PLAN RESUBMITTALS RECEIVED FROM ENGINEERING INCORPORATED FOR BILL VANDEGRIFT, 2 SETS OF P1.1, FORWARDED SAME TO MIKE OTTO
Routing Off Site - STRUCTURAL2/24/2000 3/14/2000 FAIL
SENT SET OF PLANS TO CONSULTANTING STRUCTURAL ENGINEER, ADVISED CONSULTANTING ENGINEER THAT SEVERAL SEALS AND SIGNATURES WERE MISSING AND THE BUILDING DEPARTMENT WAS IN THE PROCESS OF CORRECTINT THAT PROBLEM. 2/24/00 CORRECTIONS FAXED TO ARCHITECT. MLO
Routing - PLUMBING3/2/2000 3/9/2000 FAIL
Routing - PUBLIC WORKS2/24/2000 3/2/2000 DONE
Routing Off Site - A.C.H.D3/2/20003/2/20003/2/2000 PASS
as per letter sent from M. Neal Newhouse staff attorney-no impact fees due. mps
Case Summary (BLD)  2/24/2000 PEND
Case Summary (BLD)  2/23/2000 DONE
Plans ACCEPTED BY PLAN TECH  2/14/2000 PEND
E;ECTRIC DOOR PLANS PICKED UP BY CM COMPANY TO TAKE TO JAN WELCH AT STAPLEY ENGINEERING FOR REVIEW, STAMPING AND SEALING. 2/14/00 DAR
Plans ACCEPTED BY PLAN TECH  2/9/2000  
Plan assigned to (JCM)2/9/2000 2/9/2000 DONE
DetailsJohn Menard
Plan assigned to (MYS)2/8/20002/8/20002/8/2000 DONE
DetailsMarlene Southard
Application received  2/8/2000  
Recd Pcfee & Taken To Pln CK  2/8/2000 DONE
Plans ACCEPTED BY PLAN TECH  2/8/2000 FAIL
3 MORE CIVIL SHEETS REQUIRED FOR PUBLIC WORKS, SHEETS C1.0 AND C1.1 NOT STAMPED AND SIGNED. SHOP DRAWINGS FOR PRE-ENGINEERED BUILDING PAGE 11 NOT STAMPED AND SIGNED.SHOP DRAWINGS FOR ELECTRIC DOORS - NONE ARE STAMPED AND SIGNED BY AN ENGINEER. 1TOM BROPHY NOTIFIED OF THESE DEFICIENCIES. 2/9/10 DAR
RECEILVED 3 SETS OF CIVIL PLANS AND 3 SETS OF STORM DRAINAGE CACULATIONS AND 2 PAGE 11'S OF THE SHOP DRAWINGS 2/22/00 DAR
PRINT ACTIONS