DOC - Permit Finaled | 1/22/2001 | 1/22/2001 | 1/22/2001 | P | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 1/22/2001 2:17:39 PM
|
BLD-Final | 7/20/2000 | 7/21/2000 | 7/21/2000 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 07/20/2000 at 08:05:25. Contact: ###-####. L/C issued 7/24/00 1:02:07 PM
|
BLD-Final | 7/6/2000 | 7/7/2000 | 7/7/2000 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 07/06/2000 at 08:35:53. Contact: ###-####. Add 9169 Lancelot Bld00-01378 pass 7/10/00 10:21:43 AM
|
BLD-Energy code compliance | 6/5/2000 | 6/5/2000 | 6/5/2000 | P | FAIL |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 06/05/2000 at 09:48:00. Contact: ###-####. $42.00 reinspection. 6/6/00 11:31:21 AM
|
BLD-Framing/Rough-in | 6/2/2000 | 6/2/2000 | 6/2/2000 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/02/2000 at 07:22:43. Contact: ###-####. C/N posted 6/5/00 10:59:12 AM
|
BLD-Framing/Rough-in | 5/15/2000 | 5/15/2000 | 5/15/2000 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 05/15/2000 at 08:42:59. Contact: ###-####. Conf. on framing. 5/16/00 9:57:30 AM
|
BLD-Framing/Rough-in | 5/11/2000 | 5/12/2000 | 5/12/2000 | A | FAIL |
Carl Dependahl
|
|
|
###-#### Need detail for cricket. 5/15/00 11:10:26 AM
|
BLD-Framing/Rough-in | 5/11/2000 | 5/11/2000 | 5/11/2000 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 05/11/2000 at 07:56:31. Contact: ###-####. Called contractor to reschedule insp. 5/12/00 8:52:53 AM
|
BLD-Framing/Rough-in | 4/25/2000 | 4/25/2000 | 4/25/2000 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 04/25/2000 at 08:50:56. Contact: ###-####. Ok to side see C/N on 1hr wall. 4/26/00 11:41:22 AM
|
BLD-Framing/Rough-in | 4/18/2000 | 4/19/2000 | 4/19/2000 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/18/2000 at 10:20:11. Contact: ###-####. "408's area"; need to complete 1hr. wall. 4/20/00 9:42:54 AM
|
BLD-Footing | 3/24/2000 | 3/27/2000 | 3/27/2000 | A | PART |
Tom Arcoraci
|
|
|
###-#### Provide plans at wall insp. 3/27/00 4:29:10 PM
|
BLD-Footing | 3/15/2000 | 3/16/2000 | 3/16/2000 | A | FAIL |
Tom Arcoraci
|
|
|
###-#### Need soils report 3/16/00 1:46:06 PM
|
BLD-Conference | 3/9/2000 | 3/9/2000 | 3/9/2000 | P | PART |
Tom Arcoraci
|
|
|
question for bearing of the soil. ted ###-#### Need soils report. 3/14/00 11:05:56 AM
|
Telephone call | | | 3/7/2000 | | DONE |
|
|
|
left mess that permit is ready
|
Issue PAID IN FULL permit | | | 3/7/2000 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 3/6/2000 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/6/2000 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/6/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/6/2000 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 2/16/2000 | | 3/6/2000 | | PASS |
Mike Phillips
|
|
|
3/6/2000 14:51:44 M_P - activity updated through activity BLDA022 from case BLD00-00358.
|
Routing - PUBLIC WORKS | 2/16/2000 | | 3/1/2000 | | DONE |
|
|
|
|
Routing - PLANNING | 2/16/2000 | | 3/1/2000 | | DONE |
|
|
|
duplex in ric zone requires a duplex application approval.
|
Application received | | | 2/16/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 2/16/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 2/16/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 3/1/2000 | 3/1/2000 | | | PEND |
|
|
|
|
Print Pending Permit.LaserJet4 | | | | | |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|