BLD-Final | 5/25/2000 | 5/26/2000 | 5/26/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 05/25/2000 at 15:49:27. Contact: ###-####. C/C #19517. 5/30/00 9:48:29 AM
|
BLD-Final | 5/24/2000 | 5/25/2000 | 5/25/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 05/24/2000 at 17:37:45. Contact: ###-####. C/N...need electri. final misc. energy code. 5/26/00 12:18:44 PM
|
BLD-Framing/Rough-in | 4/13/2000 | 4/14/2000 | 4/14/2000 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 04/13/2000 at 17:51:14. Contact: ###-####. Energy code pass 4/14/00 1:42:46 PM
|
BLD-Energy code compliance | 4/14/2000 | 4/14/2000 | 4/14/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 04/14/2000 at 09:50:40. Contact: ###-####. Energy code pass 4/14/00 1:43:19 PM
|
BLD-Framing/Rough-in | 4/12/2000 | 4/13/2000 | 4/13/2000 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 04/12/2000 at 17:26:49. Contact: ###-####. C/N...truss bracing & supports 4/13/00 1:06:47 PM
|
BLD-Framing/Rough-in | 4/11/2000 | 4/12/2000 | 4/12/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 04/11/2000 at 16:11:15. Contact: ###-####. C/N..need electr. & truss. eng. 4/13/00 11:37:52 AM
|
BLD-Framing/Rough-in | 4/6/2000 | 4/7/2000 | 4/7/2000 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 04/06/2000 at 17:43:25. Contact: ###-####. Shear ok 4/7/00 2:49:45 PM
|
BLD-Framing/Rough-in | 3/31/2000 | 4/3/2000 | 4/3/2000 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 03/31/2000 at 16:58:14. Contact: ###-####. No plans. 4/3/00 1:36:30 PM
|
BLD-Framing/Rough-in | 3/30/2000 | 3/30/2000 | 3/30/2000 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/30/2000 at 10:02:36. Contact: ###-####. Not ready 3/31/00 8:50:58 AM
|
BLD-Foundation | 3/13/2000 | 3/13/2000 | 3/13/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 03/13/2000 at 09:31:18. Contact: ###-####.
|
BLD-Footing | 3/10/2000 | 3/10/2000 | 3/10/2000 | P | PART |
Jim Sly
|
|
|
jack ###-#### Footing appears ok. 3/14/00 11:18:09 AM
|
BLD-Footing | 3/9/2000 | 3/9/2000 | 3/9/2000 | P | FAIL |
Jim Sly
|
|
|
###-#### Not ready. 3/14/00 11:02:04 AM
|
Issue PAID IN FULL permit | | | 3/7/2000 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 3/2/2000 | 3/2/2000 | 3/2/2000 | | PASS |
Dan Overy
|
|
|
3/2/2000 08:48:50 DJO - activity updated through activity BLDA022 from case BLD00-00437.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/2/2000 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/2/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/2/2000 | | DONE |
|
|
|
|
Telephone call | | | 3/2/2000 | | DONE |
|
|
|
talked to heather to verify plans are ready
|
Plan Review Report | | | 3/2/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 3/2/2000 | | |
|
|
|
|
Routing - PUBLIC WORKS | 2/22/2000 | 2/22/2000 | 2/23/2000 | | DONE |
|
|
|
|
Routing - PLANNING | 2/22/2000 | 2/22/2000 | 2/23/2000 | | DONE |
|
|
|
|
Application received | | | 2/22/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 2/23/2000 | 2/23/2000 | | | PEND |
|
|
|
|
Pending Assignment by DJO | 2/22/2000 | | | | PEND |
Dan Overy
|
|
|
|