Fee Review-notes | 2/22/2000 | 2/22/2000 | 10/24/2000 | | DONE |
|
|
|
final cert from gc project 154,764.00 e23,543 p1,362 m 14,496
|
Permanent occupancy | | | 10/19/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8439 issued 10-19-00 to Morrison-Knudsen Corp.
|
Permanent Occupancy | | 10/18/2000 | 10/18/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/17/2000 | 10/18/2000 | 10/18/2000 | A | PASS |
Joe Tawney
|
|
|
Tony Shiverick ###-#### rEINSP ok FOR PERMANANT OCCUPANCY 10/18/2000 12:16:11 PM
|
BLD-Final | 10/17/2000 | 10/18/2000 | 10/18/2000 | P | PASS |
Tom Arcoraci
|
|
|
Tony ###-####
|
Temporary occupancy | | | 9/8/2000 | | PART |
|
|
|
Temp. Occ. Cert. #4059 issued 9-8-00 to Morrison-Knudsen Corp.
|
BLD-Final | 9/6/2000 | 9/7/2000 | 9/7/2000 | P | FAIL |
Carl Dependahl
|
|
|
TONY ###-#### FN OCC, need fire ok 9/7/2000 3:48:23 PM
|
FIRE-Final Inspection | 9/6/2000 | 9/7/2000 | 9/7/2000 | P | FAIL |
Joe Tawney
|
|
|
TONY ###-#### FIRE FN Reinsp Fail 9/8/2000 7:50:41 AM
|
BLD-Final | 6/7/2000 | 6/8/2000 | 6/8/2000 | A | PART |
Alan Hauser
|
|
|
Tony ###-####
Temp occ only still needs ramp fixed
|
BLD-Final | 6/1/2000 | 6/1/2000 | 6/1/2000 | A | FAIL |
Carl Dependahl
|
|
|
Per GS & conf. w/Tony Shiverick. Need complying exits as shown. Add'l guardrail const. req'd. ok to use bldg. if WIP.
|
BLD-Final | 5/23/2000 | 5/25/2000 | 5/25/2000 | P | FAIL |
Carl Dependahl
|
|
|
###-#### Complete C/N, recall: exit door hdwr & landing. 5/26/00 12:15:46 PM
|
FIRE-Final Inspection | 5/24/2000 | 5/25/2000 | 5/25/2000 | A | PART |
Joe Tawney
|
|
|
###-#### Reinsp. ok for temp. occ. Door hardware and valve tamper in pit. 5/25/00 1:39:41 PM
|
FIRE-Final Inspection | 5/23/2000 | 5/24/2000 | 5/24/2000 | A | CANC |
Joe Tawney
|
|
|
###-#### Contractor scheduled for 5/25/00. PDS error 5/25/00 9:00:50 AM
|
BLD-Final | 5/19/2000 | 5/22/2000 | 5/22/2000 | P | FAIL |
Carl Dependahl
|
|
|
Tony; ###-####. C/N- ADA, landings, fire, door hdwr. 5/23/00 2:34:33 PM
|
FIRE-Final Inspection | 5/18/2000 | 5/19/2000 | 5/19/2000 | A | FAIL |
Joe Tawney
|
|
|
###-#### Final fail C/N issued. 5/22/00 10:56:55 AM
|
BLD-Final | 5/18/2000 | 5/19/2000 | 5/19/2000 | P | FAIL |
Carl Dependahl
|
|
|
###-#### N/R, recall 5/22/00 11:38:41 AM
|
BLD-Final | 5/15/2000 | 5/16/2000 | 5/16/2000 | P | FAIL |
Carl Dependahl
|
|
|
tony --###-#### fn
|
BLD-Framing/Rough-in | 4/13/2000 | 4/14/2000 | 4/14/2000 | A | PART |
Tom Arcoraci
|
|
|
###-#### See old C/notice 4/14/00 1:51:08 PM
|
FIRE-Sprinkler Rough-in | 4/11/2000 | 4/12/2000 | 4/12/2000 | P | PART |
Joe Tawney
|
|
|
doug ###-#### pager # r/i Ok sprkl. R/I & hydro test. Attach earthquake bracing to top of trusses or submit calc. 4/13/00 8:51:50 AM
|
BLD-Concrete | 4/6/2000 | 4/7/2000 | 4/7/2000 | A | PART |
Carl Dependahl
|
|
|
###-#### Slab/ramp 4/7/00 2:45:25 PM
|
BLD-Concrete | 4/5/2000 | 4/6/2000 | 4/6/2000 | A | FAIL |
Jim Sly
|
|
|
###-#### NR 4/6/00 3:00:34 PM
|
BLD-Framing/Rough-in | 3/30/2000 | 4/4/2000 | 4/4/2000 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/30/2000 at 13:29:41. Contact: ###-####. Ramp fnd. wall ok to pour 4/4/00 1:28:01 PM
|
BLD-Framing/Rough-in | 4/3/2000 | 4/4/2000 | 4/4/2000 | A | FAIL |
Russ Owen
|
|
|
re-bar Tony Shervik ###-#### ramp C/N, detail for lid, etc. 4/4/00 1:28:13 PM
|
Routing - PLANNING | 3/15/2000 | 3/15/2000 | 3/16/2000 | | DONE |
|
|
|
approved (see notes in building permit plans signature block).
|
Plan resubmittals received | | | 3/16/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM CSHQA, FORWARDED SAME TO JASON ONE LETTER FROM MORRISON KNUDSEN CORP. AND ONE COPY OF ALTA SURVEY FOR AMRESCO COMMERICAL LENDING CORPORATION. FORWARDED SAME TO JASON BLAIS. 3/16/00 DAR
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/16/2000 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/16/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/16/2000 | | DONE |
|
|
|
|
Telephone call | | | 3/16/2000 | | DONE |
|
|
|
TALKED TO SHERRI TO VERIFY PLANS ARE READY
|
Issue PAID IN FULL permit | | | 3/16/2000 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 2/25/2000 | | 3/16/2000 | | PASS |
Jason Blais
|
|
|
|
Routing - PLAN CHECK | 3/14/2000 | | 3/16/2000 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
Plan resubmittals received | | | 3/15/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM CSHQA ARCHITECTS, JOHN MAULIN, 2 SETS OF SHEETS A2.0, A2.1,A2.2,A6.2,A8.1, FORWARDED SAME TO JASON BLAIS. 3/15/00 DAR
|
Routing - FIRE | 3/10/2000 | 3/14/2000 | 3/14/2000 | | PASS |
Sam Rogers
|
|
|
|
Plan Review Completed(1st rev) | | | 3/14/2000 | | FAIL |
Sam Rogers
|
|
|
|
Routing - PLAN CHECK | 2/28/2000 | | 3/10/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to fire dept. for review.
|
Plan resubmittals requested | | | 3/10/2000 | | PEND |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PUBLIC WORKS | 2/25/2000 | | 2/28/2000 | | DONE |
|
|
|
|
Pending Assignment by MYS | 2/22/2000 | | 2/25/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 2/25/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 2/23/2000 | | DONE |
|
|
|
|
Application received | | | 2/22/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|