Fee Review-notes | 6/24/2003 | 6/24/2003 | 6/24/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/13/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8191 issued 4-13-00 to Idaho Banking Company (addn.)
|
FIRE-Final Inspection | 4/12/2000 | 4/12/2000 | 4/12/2000 | P | PASS |
Joe Tawney
|
|
|
don ###-#### fn fire Reinsp. ok for perm. occ. 4/13/00 8:51:59 AM
|
BLD-Final | 4/12/2000 | 4/12/2000 | 4/12/2000 | P | PASS |
Carl Dependahl
|
|
|
don ----###-#### fn occ Card to cont. 4/17/00 1:30:55 PM
|
FIRE-Final Inspection | 4/10/2000 | 4/11/2000 | 4/11/2000 | A | FAIL |
Joe Tawney
|
|
|
Don Bryant, ###-#### Final fail C/N issued 4/11/00 1:54:19 PM
|
Permanent Occupancy | | 4/11/2000 | 4/11/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/6/2000 | 4/7/2000 | 4/7/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 04/06/2000 at 12:48:15. Contact: ###-####. Final fail not ready for inspection 4/7/00 2:50:51 PM
|
BLD-Other | 4/3/2000 | 4/4/2000 | 4/4/2000 | A | PART |
Carl Dependahl
|
|
|
Don Bryan - ###-#### - ceiling grid Grid ok 4/4/00 1:28:59 PM
|
BLD-Framing/Rough-in | 3/20/2000 | 3/20/2000 | 3/20/2000 | P | PART |
Carl Dependahl
|
|
|
Don, ###-#### Brace walls per plan chk @ final 3/21/00 9:29:39 AM
|
Plan assigned to (R_H) | 2/25/2000 | | 3/20/2000 | | PASS |
|
|
|
3/20/2000 07:17:03 RMH - activity updated through activity BLDA022 from case BLD00-00462.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2000 | | PASS |
Ron Hill
|
|
|
|
Print Occupancy Form | | | 3/20/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/20/2000 | | DONE |
|
|
|
|
Telephone call | | | 3/20/2000 | | DONE |
|
|
|
called marv ###-#### told him $ amount
|
Issue PAID IN FULL permit | | | 3/20/2000 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 3/17/2000 | | PASS |
Ron Hill
|
|
|
|
Routing - FIRE | 3/14/2000 | 3/16/2000 | 3/16/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 3/16/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM BRS TWO SHEET OF SHEET A-2 FORWARDED SAME TO RON HILL. 3/16/00 DAR
|
Plan Review Completed(1st rev) | | | 3/16/2000 | | FAIL |
Bill Alexander
|
|
|
Failed by the UBC plan reviewer.
|
Routing - PLAN CHECK | 2/28/2000 | | 3/14/2000 | | FAIL |
Ron Hill
|
|
|
Route to fire department
|
Plan Reviewer's activity | | | 3/14/2000 | | FAIL |
Ron Hill
|
|
|
Faxed and mailed requirements to the architect, Route to fire department for approvals.
|
BLD-Framing/Rough-in | 3/9/2000 | 3/9/2000 | 3/9/2000 | P | PART |
Carl Dependahl
|
|
|
###-####\\idaho banking co Ext. walls 3/14/00 10:57:17 AM
|
Routing - PUBLIC WORKS | 2/25/2000 | | 2/28/2000 | | DONE |
|
|
|
|
Telephone call | | | 2/25/2000 | | DONE |
|
|
|
talked to nicole no dollar amount told her this was a early start for foundation only
|
Plan routing begun/TENANTS | | | 2/25/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 2/25/2000 | | DONE |
|
|
|
ARCHITECT/ENGINEER OF RECORD FORM NOT SIGNED. FAX TO W.H. MOORE FOR SIGNATURE. 2/25/00 DAR
|
Pending Assignment by MYS | 2/25/2000 | | 2/25/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan Reviewer's activity | | | 2/25/2000 | | DONE |
|
|
|
ISSUES A PARTIAL PERMIT ON 2/25/00 AT THE REQUEST OF THE CONTRACTOR.
|
Application received | | | 2/24/2000 | | |
|
|
|
|