Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD00-00475
StatusFinaled
Name INTERWEST MANAGEMENT ASSOC.
Site Address 2308 W OVERLAND RD
Project Name 
Customer Number 
ePlanReviewNo
Description
To convert an 847 sq.ft. dwelling to office with associated parking and requirements to comply with DRH99-00148. Existing 578 sq.ft. detached garage to remain in same use. Work to include paving parking area, construction of an accessible ramp and entrance, construction of new unisex accessible restroom, removal of architectual barriers within office space to create an accessible route throughout office area, removal and replacement of the rear stairs and handrail, per approved plans on file. (P.C.#138-00) DRH99-00148/CVA97-00015 *RMH*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes2/25/20002/25/20003/29/2001 DONE
Permanent occupancy UNPAID FEE  10/30/2000 DONE
Perm. Occ. Cert. #8449 issued 10-30-00 to Interwest Management Assoc.
Permanent Occupancy 10/26/200010/26/2000 DONE
Details
Code Occupancy Approval  10/17/2000 PASS
ALL CONDITIONS HAVE BEEN MET UNDER DRH99-00148, FINAL OCCUPANCY SIGNED OFF.
BLD-Final10/12/200010/13/200010/13/2000PPASS
DetailsJim Storey
FN OCC ---LINDA ###-####
BLD-Final9/15/20009/18/20009/18/2000PFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/15/2000 at 14:51:32. Contact: ###-####. need window handle for rail clearance/ need p/z sign off and public works verifacation. 9/18/2000 2:51:11 PM
FIRE-Final Inspection7/18/20007/21/20007/21/2000APASS
DetailsRick Jackson
linda Edson ###-#### Door hardware not correct- she will fix for structureal inspection. 7/21/00 12:54:41 PM
BLD-Final7/18/20007/21/20007/21/2000ANR
DetailsJim Storey
###-#### - Linda Epson *** Fire is also going out for a final
BLD-Concrete5/10/20005/10/20005/10/2000PPASS
Details
for handicap ramp---brad-###-#### cell ok to pour the ramp 5/10/00 4:26:06 PM
Override - Parcel Holds  3/28/2000  
Issue PAID IN FULL permit  3/28/2000 DONE
Plan resubmittals received  3/23/2000 PASS
DetailsRon Hill
PLANS/APPL TAKEN TO FRONT DESK  3/23/2000 PASS
DetailsRon Hill
Inspection Record Card- Bld  3/23/2000 DONE
Print Occupancy Form  3/23/2000 DONE
Telephone call  3/23/2000 DONE
talked to peggy to verify plans are ready--also told her we needed achd
Plan assigned to (R_H)2/28/2000 3/23/2000 PASS
Details
3/23/2000 07:59:51 RMH - activity updated through activity BLDA022 from case BLD00-00475.
Routing - PLAN CHECK3/22/2000 3/23/2000 PASS
DetailsRon Hill
Routing - FIRE3/17/20003/22/20003/22/2000 PASS
DetailsBill Alexander
Plan resubmittals received  3/22/2000 PEND
DetailsRon Hill
received plan sheets A1 & A2
Plan Review Completed(1st rev)  3/22/2000 FAIL
DetailsBill Alexander
Failed by UBC plan reviewer
Telephone call  3/21/2000 FAIL
DetailsRon Hill
Spoke with architect abnout requirements on phone, 11:30 AM
Plan Reviewer's activity  3/20/2000 PEND
DetailsRon Hill
Talked to architect about requirements over phone 2:45 3-20-00.
Routing - PLAN CHECK3/9/2000 3/17/2000 FAIL
DetailsRon Hill
Route to public works Brian Murphy then to fire.
Plan Reviewer's activity  3/17/2000 FAIL
DetailsRon Hill
Faxed requirements to the arcitect. Route to public works (Brian Murphy) then to fire.
Routing - PLANNING3/8/2000 3/9/2000 PASS
Approve per DRH99-148
Routing - PUBLIC WORKS2/28/2000 3/8/2000 PASS
Telephone call  3/6/2000 DONE
SHE COULD PAY FOR BLD99-01596 AT THE TIME OTHER PERMIT IS READY TO PICK UP...LH
Plan routing begun/TENANTS  2/28/2000 DONE
Route to PUBLIC WORKS, PLANNING, PLAN CHECK and FIRE.
Pending Assignment by MYS2/28/2000 2/28/2000 DONE
DetailsMarlene Southard
Application received  2/25/2000  
Override - Parcel Holds  2/25/2000  
Plans ACCEPTED BY PLAN TECH  2/25/2000 DONE