Fee Review-notes | 2/28/2000 | 2/28/2000 | 3/21/2001 | | DONE |
|
|
|
don't know who gc is need to ask tom or dan
|
Letter of compliance | | | 12/18/2000 | | DONE |
|
|
|
Letter of Compliance #21289 issued 12-18-00.
|
BLD-Final | 12/14/2000 | 12/15/2000 | 12/15/2000 | P | PASS |
Tom Arcoraci
|
|
|
FN OCC JAN- ###-#### 12/15/2000 3:48:29 PM ok for perm occ 12/15/2000 4:10:56 PM
|
FIRE-Final Inspection | 12/14/2000 | 12/15/2000 | 12/15/2000 | P | PASS |
Joe Tawney
|
|
|
JAN -- ###-#### FN FIRE Reinsp OK for certificate of completion 12/17/2000 8:32:51 PM
|
FIRE-Final Inspection | 12/11/2000 | 12/14/2000 | 12/14/2000 | A | FAIL |
Joe Tawney
|
|
|
FIRE FN-- JAN-- ###-#### Final Fail Smoke detector location and s/f damper access 12/14/2000 12:39:39 PM
|
BLD-Final | 12/11/2000 | 12/14/2000 | 12/14/2000 | P | NR |
Tom Arcoraci
|
|
|
JAN -###-#### FN OCC
|
BLD-Other | 10/27/2000 | 10/30/2000 | 10/30/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/27/2000 at 12:48:36. Contact: ###-####. conf w/ bldr..need consult w/ fire-safety foe t/o of phase 2. 10/30/2000 2:41:25 PM
|
FIRE-Conference | 10/27/2000 | 10/30/2000 | 10/30/2000 | A | PART |
Joe Tawney
|
|
|
###-####.Discussed Phase II project with Jan 10/31/2000 7:48:21 AM
|
BLD-Framing/Rough-in | 10/30/2000 | 10/30/2000 | 10/30/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/30/2000 phase 2 ok to cover; prior insp by 316
|
BLD-Framing/Rough-in | 10/26/2000 | 10/26/2000 | 10/26/2000 | P | NR |
Carl Dependahl
|
|
|
temp occ on phase 2 **Jan ###-####
|
BLD-Framing/Rough-in | 9/28/2000 | 9/29/2000 | 9/29/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 09/28/2000 at 13:37:21. Contact: .
|
BLD-Framing/Rough-in | 6/9/2000 | 6/12/2000 | 6/12/2000 | A | PART |
Jim Sly
|
|
|
jan ###-#### radiology please call\\ok to cover interior reading room walls only phase one
|
Issue PAID IN FULL permit | | | 4/18/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/3/2000 | | 4/3/2000 | | PASS |
|
|
|
Approved as noted and attached.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2000 | | PASS |
|
|
|
Routing for issuance of permit.
|
Print Occupancy Form | | | 4/3/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/3/2000 | | DONE |
|
|
|
|
Telephone call | | | 4/3/2000 | | DONE |
|
|
|
called ###-#### Mykel Davis left message that permit is ready
|
Plan assigned to (DRS) | 2/29/2000 | | 4/3/2000 | | PASS |
Dan Stuart
|
|
|
4/3/2000 06:39:46 DRS - activity updated through activity BLDA022 from case BLD00-00488.
|
Routing - FIRE | 3/28/2000 | 3/31/2000 | 3/31/2000 | | PASS |
Sam Rogers
|
|
|
|
Plan Review Completed(1st rev) | | | 3/31/2000 | | PASS |
Sam Rogers
|
|
|
|
Routing - PLAN CHECK | 3/3/2000 | | 3/27/2000 | | PEND |
|
|
|
Approved as noted and attached to plans. No resubmittals required. Routing to Fire Code Analyst for review. Copy of review comments to architect.
|
Routing - PLUMBING | 3/2/2000 | | 3/3/2000 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 2/29/2000 | | 3/2/2000 | | DONE |
|
|
|
|
Pending Assignment by MYS | 2/28/2000 | | 2/29/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 2/29/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE.
|
Application received | | | 2/28/2000 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/28/2000 | | DONE |
|
|
|
PLANS WERE FAXED TO US ON 2/24/2000 WITHOUT APPLICATION OR FEE CHECK. CONTACTED MYKEL DAVIS OF THIS NEED. 2/28/2000 RECEIVED APPLICATION WITH PLAN CHECK FEE CHECK. KMM
|
Received Certificate of Value | | | 2/28/2000 | | DONE |
|
|
|
|