BLD-Final | 8/28/2000 | 8/29/2000 | 8/29/2000 | A | PASS |
Alan Hauser
|
|
|
c/c#19280 8/29/2000 12:18:19 PM
|
BLD-Final | 8/24/2000 | 8/24/2000 | 8/24/2000 | P | FAIL |
Russ Owen
|
|
|
Nick; ###-#### Needs handrail to code. 8/25/2000 9:50:10 AM
|
BLD-Energy code compliance | 5/19/2000 | 5/22/2000 | 5/22/2000 | P | PASS |
Russ Owen
|
|
|
nick ###-#### energy code insp. Reasigned to 407 by 325.
|
Override - Parcel Holds | | | 5/19/2000 | | |
|
|
|
|
BLD-Framing/Rough-in | 5/16/2000 | 5/17/2000 | 5/17/2000 | P | FAIL |
Russ Owen
|
|
|
###-#### C/N posted 5/18/00 3:04:37 PM
|
BLD-Framing/Rough-in | 5/16/2000 | 5/16/2000 | 5/16/2000 | P | CANC |
Russ Owen
|
|
|
###-#### Will recall when ready 5/17/00 1:55:25 PM
|
Override - Parcel Holds | | | 5/16/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 5/16/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 5/16/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 5/16/2000 | | |
|
|
|
|
BLD-Framing/Rough-in | 5/15/2000 | 5/15/2000 | 5/15/2000 | P | PASS |
Russ Owen
|
|
|
Ok to side.
|
BLD-Framing/Rough-in | 5/15/2000 | 5/15/2000 | 5/15/2000 | A | FAIL |
Russ Owen
|
|
|
Left a C/N, has engineer approval items on his correction list?
|
BLD-Framing/Rough-in | 5/12/2000 | 5/15/2000 | 5/15/2000 | A | PART |
Bob Archibald
|
|
|
###-#### shear wall. Reasigned to Russ.
|
Override - Parcel Holds | | | 5/15/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 5/12/2000 | | |
|
|
|
|
Plan Reviewer's activity | | | 5/2/2000 | | DONE |
|
|
|
FLOOD PLAIN ELEVATION CERTIFICATE SUBMITTED BY STEVE SWEET, P.E. AND APPROVED BY JIM WYLLIE. COPY ON FILE IN PLAN REVIEW OFFICE.
|
BLD-Framing/Rough-in | 5/1/2000 | 5/1/2000 | 5/1/2000 | A | FAIL |
Russ Owen
|
|
|
Need engineers calcs and clean plans. Also noted corrections with wall to roof connections.
|
Override - Parcel Holds | | | 5/1/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 5/1/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 4/28/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 4/28/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 4/28/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 4/28/2000 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/24/2000 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/24/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 3/24/2000 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/24/2000 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 3/4/2000 | | 3/24/2000 | | PASS |
Steve Munroe
|
|
|
3/24/2000 14:41:41 SAM - activity updated through activity BLDA022 from case BLD00-00494.
|
Additional plans submitted | | | 3/23/2000 | | PEND |
|
|
|
New engineering with plan update submitted by Jay with Dakota at 16:00 on the 23rd of March.
|
BLD-Foundation | 3/21/2000 | 3/22/2000 | 3/22/2000 | P | PART |
Bob Archibald
|
|
|
###-#### late pm. 2&3 rows #4 horizontal.Straps being placed, no one on site.
|
BLD-Foundation | 3/22/2000 | 3/22/2000 | 3/22/2000 | A | PART |
Wes Worcester
|
|
|
Incomplete- hold downs being placed appears ok.
|
Override - Parcel Holds | | | 3/22/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 3/22/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 3/21/2000 | | |
|
|
|
|
BLD-Footing | 3/17/2000 | 3/20/2000 | 3/20/2000 | A | PART |
Bob Archibald
|
|
|
###-#### as per Tim Hogland this inspection shall be done at 10 am. Early start, setbacks/soil appear OK.
|
Override - Parcel Holds | | | 3/17/2000 | | |
|
|
|
|
Plan Reviewer's activity | | | 3/6/2000 | | PEND |
|
|
|
Called and left a message for Doug Unger to call me. I have questions on the engineering. First and second floor NOT matching what is drawn. I also called and left a message with Brian to have Jay, with Dakota, to call me. 3/6/00 8:15
10:45 3/15/00 Recieved a call from Jay with Dakota. He was concerned that this project might affect his working relationship with the city. I informed him that it would not and that we are not picking on Nemec or him. This is just a house that we/I have concerns with on the engineering and that I want to make sure that it is structurally sound. I told him that I would keep him informed as I find things out.
|
Pending Assignment by DJO | 2/28/2000 | | 3/4/2000 | | DONE |
Dan Overy
|
|
|
|
Routing - PUBLIC WORKS | 2/28/2000 | 2/28/2000 | 3/1/2000 | | DONE |
|
|
|
|
Routing - PLANNING | 2/28/2000 | 2/28/2000 | 3/1/2000 | | DONE |
|
|
|
|
Application received | | | 2/28/2000 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/10/2000 | 3/10/2000 | | | PEND |
|
|
|
Set to consulting engineer to review.
|
Routing - PLAN CHECK | 3/1/2000 | 3/1/2000 | | | PEND |
|
|
|
|
Early Start Permit | | | | | PEND |
|
|
|
early start issued per tim hogland 3/17/00 pe
|
Case Summary (BLD) | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|