Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD00-00572
StatusFinaled
Name BOB GOLDBERG
Site Address 445 W MCGREGOR
Project NameLEVEL 3 COMMUNICATIONS
Customer Number 
ePlanReviewNo
Description
LEVEL (3) COMMUNICATIONS * TO CONSTRUCT A 4,512 SF,TYPE II-N, ONE STORY MASONRY BUILDING. INCLUDING MASONRY EQUIPMENT YARD. . DRH00-00032 PC#172-00 GRADING PERMIT BLD00-00576. NOTE: THIS BUILDING IS CONSIDERED AS NON-OCCUPIED SWITCH GEAR EQUIPMENT ONLY. A LETTER OF COMPLETION WILL BE ISSUED WHEN THE PROJECT HAS OBTAINED FINAL APPROVALS FROM ALL DEPARTMENTS AND AGENCIES. FUTURE OCCUPANCY WILL REQUIRE RESTROOM FACILITIES WHICH ARE CONNECTED TO THE PUBLIC SANITARY SEWER SYSTEM.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes3/7/20003/7/20007/25/2000 DONE
Letter of compliance  7/17/2000 DONE
Letter of Compliance #18527 issued 7-17-00.
BLD-Final7/13/20007/14/20007/14/2000APASS
DetailsJim Storey
tom ###-#### fn apt. 8:30 am monday. 7/14/2000 4:24:17 PM
FIRE-Final Inspection7/10/20007/11/20007/11/2000PPASS
DetailsRick Jackson
Mike ###-#### for time set by the both of you 1:15pm
Override - Parcel Holds  7/10/2000  
FIRE-Final Inspection7/6/20007/7/20007/7/2000AFAIL
DetailsRick Jackson
Mike ###-#### Fire alarms not complete- dact no wired; need to test alarms; address. 7/10/00 10:23:55 AM
FIRE-Final Inspection7/6/20007/7/20007/6/2000ACANC
DetailsRick Jackson
###-#### Disp set to [CANC] by a contractor via Hello! on 07/06/2000 at 11:17:44.
Override - Parcel Holds  7/6/2000  
Override - Parcel Holds  7/6/2000  
Code Occupancy Approval  6/26/2000 PASS
PROPERTY IN COMPLIANCE WITH DRH00-00032, LARGE AREAS SEEDED WITH NO VEGETATION YET (MAY TAKE A LOT OF TIME), BUT THE REQUIRED TREES AND SPRINKLER SYSTEMS IN PLACE, PARKING ALL MARKED AS REQUIRED. FINAL SIGNED OFF.
Print Occupancy Form  6/22/2000 DONE
BLD-Framing/Rough-in5/12/20005/15/20005/15/2000APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 05/12/2000 at 14:33:15. Contact: ###-####. interior framing ok. 5/15/00 11:26:30 AM
FIRE-Conference5/2/20005/1/20005/1/2000 PART
DetailsRick Jackson
reviewed hydrant location
BLD-Foundation4/25/20004/26/20004/26/2000PPASS
DetailsJim Storey
masonry Kelly ###-####
BLD-Foundation4/24/20004/25/20004/25/2000APASS
DetailsJim Storey
Kelly ###-#### 3 rd lift ok special insp. reports ok on site . 4/25/00 9:18:14 AM
BLD-Concrete4/20/20004/21/20004/21/2000APART
DetailsRuss Owen
###-#### Work requires special inspection and I am not able (Time wise) to do this inpsection today. 4/21/00 1:53:31 PM
BLD-Framing/Rough-in4/14/20004/14/20004/14/2000PPART
DetailsJim Storey
concrete re-inforcement--###-#### kelly placed w/special insp on sat. work in progess apears ok. 4/14/00
BLD-Footing4/10/20004/11/20004/11/2000APASS
DetailsJim Storey
###-#### placed with special insp. pending reportr. 4/11/00
BLD-Footing4/7/20004/10/20004/10/2000APASS
DetailsJim Storey
Kelly ###-#### late morning placed w/special insp on sat. pending report. 4/10/00
BLD-Framing/Rough-in4/3/20004/4/20004/4/2000PPART
DetailsJim Storey
re-bar stem wall Kelly ###-#### wallls ok pending special insp. report. 4/4/00
Routing Off Site - A.C.H.D3/31/20003/31/20003/31/2000 DONE
see achd permit number for letter
BLD-Footing3/29/20003/30/20003/30/2000APART
DetailsJim Storey
###-####
BLD-Footing3/29/20003/30/20003/30/2000APART
DetailsJim Storey
###-####
(F) Reprint permit  3/30/2000 DONE
Issue PAID IN FULL permit  3/29/2000 DONE
Plan assigned to (MLO)3/7/2000 3/27/2000 DONE
DetailsMike Otto
PLANS/APPL TAKEN TO FRONT DESK  3/27/2000 DONE
Inspection Record Card- Bld  3/27/2000 DONE
Telephone call  3/27/2000 DONE
left message gave dollar amount also achd is due.
Plan resubmittals received  3/25/2000 DONE
RECEIVED PLAN RESUBMITTALS AT 4:00 PM FROM DAVID EVANS AND ASSOCIATES., MIKE STARKER STRUCTURAL CACULATIONS AND TWO OF SHEET SO1. 3/24/00 DAR PLANS RECEIVED AFTER 4:00 PM ARE LOGGED IN ON THE FOLLOWING DAY. MLO
Routing Off Site - STRUCTURAL3/15/2000 3/20/2000 FAIL
contacted pdq to take plans to outside eng. kmm
RECEIVED STRUCTURAL REVIEW COMMENTS. ROUTED TO MIKE O. KMM CORRECTIONS FAXED TO ARCHITECT IN PORTLAND. MLO
Plan resubmittals requested  3/20/2000 FAIL
STRUCTURAL CORRECTIONS
Routing - FIRE3/15/20003/16/20003/16/2000 PASS
DetailsBill Alexander
NEED BATTERY INFORMATION BEFORE FINAL.
Plan Review Completed(1st rev)  3/16/2000 PASS
DetailsBill Alexander
Routing - PLAN CHECK3/13/2000 3/15/2000 PASS
Plan resubmittals received  3/14/2000 DONE
RECEIVED 5 SETS OF RESUBMITTALS,SHEETS C02, E02,E03,AND E07, FORWARDED SAME TO MIKE OTTO. 3/14/00 DAR
Routing - PLUMBING3/10/2000 3/13/2000 PASS
Routing - PUBLIC WORKS3/7/2000 3/10/2000 DONE
Routing - PLANNING3/10/2000 3/10/2000 PASS
Approve subject to final approval of landscape plan by Planning and Forestry.
Plan assigned to (MYS)3/7/20003/7/20003/7/2000 PASS
DetailsMarlene Southard
Plans ACCEPTED BY PLAN TECH  3/7/2000 DONE
Received Certificate of Value  3/7/2000 DONE
Plan routing begun/NEW & ADDTN  3/7/2000 DONE
Application received  3/7/2000  
Recd Pcfee & Taken To Pln CK