BLD-Final | 8/17/2000 | 8/18/2000 | 8/18/2000 | A | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 08/17/2000 at 12:54:05. Contact: ###-####. passed 8/17/2k by 340 8/18/2000 10:49:43 AM
|
BLD-Energy code compliance | 7/5/2000 | 7/5/2000 | 7/5/2000 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/05/2000 at 11:17:46. Contact: ###-####.
|
BLD-Framing/Rough-in | 6/30/2000 | 6/30/2000 | 6/30/2000 | A | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 06/30/2000 at 07:14:46. Contact: ###-####. c/n issued 6/30/00 11:20:56 AM
|
BLD-Framing/Rough-in | 6/29/2000 | 6/29/2000 | 6/29/2000 | P | FAIL |
Tony Young
|
|
|
steve ###-#### no truss specs on job c/n left 7/3/00 8:42:16 AM
|
BLD-Framing/Rough-in | 6/15/2000 | 6/15/2000 | 6/15/2000 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/15/2000 at 07:03:35. Contact: ###-####. Ok to side 6/15/00 1:43:23 PM
|
BLD-Final | 5/9/2000 | 5/10/2000 | 5/10/2000 | A | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 05/09/2000 at 12:47:54. Contact: ###-####. called in the wrong permit # 5/10/00 9:51:35 AM
|
BLD-Final | 5/8/2000 | 5/8/2000 | 5/8/2000 | P | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 05/08/2000 at 07:23:18. Contact: ###-####. no such building or address 5/9/00 11:07:58 AM
|
BLD-Foundation | 4/18/2000 | 4/19/2000 | 4/19/2000 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/18/2000 at 18:12:19. Contact: ###-####. Fnd. walls. 4/19/00 1:42:51 PM
|
BLD-Footing | 4/18/2000 | 4/18/2000 | 4/18/2000 | A | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/18/2000 at 07:06:18. Contact: ###-####. Work not done 4/18/00 2:00:41 PM
|
BLD-Footing | 4/18/2000 | 4/18/2000 | 4/18/2000 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/18/2000 at 09:52:12. Contact: ###-####. Appears ok no plans 4/19/00 9:56:13 AM
|
Telephone call | | | 4/18/2000 | | DONE |
|
|
|
talked to stacy gave dollar amount
|
BLD-Footing | 4/17/2000 | 4/17/2000 | 4/17/2000 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/17/2000 at 07:01:22. Contact: ###-####. Nothing at the site 4/17/00 1:23:09 PM
|
Issue PAID IN FULL permit | | | 4/11/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/31/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/31/2000 | | DONE |
|
|
|
|
Telephone call | | | 3/31/2000 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (SAM) | 3/23/2000 | | 3/31/2000 | | PASS |
Steve Munroe
|
|
|
3/31/2000 13:30:34 SAM - activity updated through activity BLDA022 from case BLD00-00649.
|
Pending Assignment by DJO | 3/15/2000 | | 3/23/2000 | | DONE |
Dan Overy
|
|
|
|
Routing - PUBLIC WORKS | 3/15/2000 | 3/15/2000 | 3/15/2000 | | DONE |
|
|
|
|
Routing - PLANNING | 3/15/2000 | 3/15/2000 | 3/15/2000 | | DONE |
|
|
|
|
Application received | | | 3/15/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 3/16/2000 | 3/16/2000 | | | PEND |
|
|
|
|
Telephone call | | | | | PEND |
|
|
|
03/27/00 1:10 Called and talked to Scott with Prestige about needing engineering for the rear of the house plus having Riley double checking the garage. (I noticed 25 feet of trib, not the 10 feet in calcs). I also talked to Riley and he wanted me to have Prestige bring him the plans so he could check the plans.
|
Plan Reviewer's activity | | | | | |
|
|
|
3/31/00 11:15 I recieved engineering for the rear bay. I called and talked to Chris with AHJ. I left a message for Riley to call me on the garage front hold-downs. Riley called me back and every thing is okay. 3/31/00 11:50
|
Print Pending Permit.LaserJet4 | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|