Fee Review-notes | 3/16/2000 | 3/16/2000 | 10/24/2000 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 10/3/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8421 issued 10-3-00 to Millenium Condominiums.
|
Permanent Occupancy | | 9/27/2000 | 9/27/2000 | | DONE |
|
|
|
|
BLD-Final | 9/26/2000 | 9/27/2000 | 9/27/2000 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/26/2000 at 09:44:14. Contact: ###-####.
|
FIRE-Final Inspection | 9/26/2000 | 9/26/2000 | 9/26/2000 | P | PASS |
Joe Tawney
|
|
|
###-####. Final OK for permanant occupancy 9/27/2000 8:07:41 AM
|
Code Occupancy Approval | | | 9/26/2000 | | PASS |
|
|
|
ALL CONDITIONS HAVE BEEN MET FINAL SIGNED OFF
|
Print Occupancy Form | | | 9/1/2000 | | DONE |
|
|
|
|
BLD-Conference | 7/19/2000 | 7/19/2000 | 7/19/2000 | P | PASS |
Carl Dependahl
|
|
|
RE: mec check; is accurate? Will call Gale insul. (doesn't check out w/our program).
|
BLD-Energy code compliance | 7/18/2000 | 7/18/2000 | 7/18/2000 | P | PART |
Carl Dependahl
|
|
|
JED-- ###-####--ENERGY CODE --BLD #2 Verify accurate mec-check 7/19/00 9:59:57 AM
|
BLD-Energy code compliance | 7/17/2000 | 7/17/2000 | 7/17/2000 | P | FAIL |
Carl Dependahl
|
|
|
jed ###-#### Keep C/N, need mec. check, complete corrections. 7/18/00 2:09:20 PM
|
BLD-Framing/Rough-in | 7/12/2000 | 7/13/2000 | 7/13/2000 | P | FAIL |
Carl Dependahl
|
|
|
jed ###-#### C/N fireblocks, mec, check 7/14/00 9:27:33 AM
|
BLD-Framing/Rough-in | 7/13/2000 | 7/13/2000 | 7/13/2000 | P | FAIL |
Carl Dependahl
|
|
|
dry wall nailing jed ###-####
|
BLD-Framing/Rough-in | 7/10/2000 | 7/11/2000 | 7/11/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 07/10/2000 at 17:50:51. Contact: ###-####. OK to side only 7/12/00 10:29:34 AM
|
BLD-Framing/Rough-in | 7/10/2000 | 7/10/2000 | 7/10/2000 | P | FAIL |
Carl Dependahl
|
|
|
shear wall lee ###-#### C/N: nail sills, etc. 7/11/00 11:35:55 AM
|
BLD-Framing/Rough-in | 7/7/2000 | 7/7/2000 | 7/7/2000 | P | FAIL |
Carl Dependahl
|
|
|
Jed ###-#### shear wall insp Unable to inspect, recall (called builder). 7/10/00 10:26:53 AM
|
BLD-Framing/Rough-in | 6/1/2000 | 6/2/2000 | 6/2/2000 | A | PART |
Carl Dependahl
|
|
|
###-#### Party wall gyp. ok @ 2nd fl. 6/5/00 10:54:23 AM
|
BLD-Framing/Rough-in | 5/18/2000 | 5/19/2000 | 5/19/2000 | A | PART |
Carl Dependahl
|
|
|
###-#### Int. "party" walls @ 1st fl. ok 5/22/00 10:52:24 AM
|
BLD-Foundation | 5/5/2000 | 5/5/2000 | 5/5/2000 | P | PART |
Carl Dependahl
|
|
|
Jed ###-####
|
BLD-Footing | 5/3/2000 | 5/3/2000 | 5/3/2000 | P | PASS |
Jim Storey
|
|
|
###-####
|
BLD-Footing | 5/1/2000 | 5/2/2000 | 5/2/2000 | A | PASS |
Jim Storey
|
|
|
###-#### wall so. 5/2/00 8:59:35 AM 5/2/00 9:06:30 AM
|
Issue PAID IN FULL permit | | | 5/1/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/28/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/28/2000 | | DONE |
|
|
|
|
Telephone call | | | 4/28/2000 | | DONE |
|
|
|
talked to lee gave dollar amount ###-####
|
Routing - PLAN CHECK | 4/12/2000 | | 4/27/2000 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 3/16/2000 | | 4/27/2000 | | PASS |
Mike Phillips
|
|
|
4/27/2000 12:03:07 M_P - activity updated through activity BLDA022 from case BLD00-00674.
|
Plan Reviewer's activity | | | 4/27/2000 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 4/27/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2000 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/27/2000 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/25/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES REVISED SHEETS A-2 A-3, A-4, A-5, A-6, A-7, A-8, A-9 ROUTED TO MIKE P. KMM
|
Routing - FIRE | 4/7/2000 | 4/12/2000 | 4/12/2000 | | PASS |
Bill Alexander
|
|
|
On condtition-need Hydrant flow verification.
|
Plan Review Completed(1st rev) | | | 4/12/2000 | | FAIL |
Bill Alexander
|
|
|
|
Plan resubmittals requested | | | 4/7/2000 | | FAIL |
|
|
|
Additional information required for further review.
|
Routing - PLAN CHECK | 3/23/2000 | | 4/7/2000 | | |
|
|
|
Routing to fire
|
Routing - PLUMBING | 3/21/2000 | | 3/23/2000 | | DONE |
|
|
|
|
Routing - PLANNING | 3/20/2000 | | 3/21/2000 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 3/17/2000 | | 3/20/2000 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 3/17/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/17/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 3/16/2000 | | DONE |
|
|
|
|
Application received | | | 3/16/2000 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | | | |
|
|
|
|