Fee Review-notes | 4/10/2000 | 4/10/2000 | 7/25/2000 | | DONE |
|
|
|
|
Letter of compliance | | | 7/14/2000 | | DONE |
|
|
|
Letter of Compliance #18526 issued 7-14-00.
|
BLD-Final | 7/12/2000 | 7/13/2000 | 7/13/2000 | A | PASS |
Carl Dependahl
|
|
|
talk to a guy name andy on each one of these on fairview###-####
|
BLD-Final | 7/13/2000 | 7/13/2000 | 7/13/2000 | P | PASS |
Carl Dependahl
|
|
|
Add'l permit for "pedestrian tunnel" etc....ok.
|
BLD-Final | 7/11/2000 | 7/12/2000 | 7/12/2000 | P | NR |
Carl Dependahl
|
|
|
gene --###-#### fn Need P&Z, etc. 7/13/00 11:34:41 AM
|
BLD-Final | 6/6/2000 | 6/7/2000 | 6/7/2000 | P | FAIL |
Carl Dependahl
|
|
|
###-#### need elec "final", frame re-configuration @ facade ok to cover & remove pedestrian protection. recall when ready 6/19/00 11:35:01 AM
|
Plan Reviewer's activity | | | 6/5/2000 | | DONE |
|
|
|
Pinnacle Engineers designated by the owner as the Engineer of Record. Mark Knowles is no longer the Architect of Record.
|
CHANGE STATUS TO (R) | | | 6/5/2000 | | DONE |
|
|
|
Plan resub. ready to pick up..
|
Telephone call | | | 6/5/2000 | | DONE |
|
|
|
left message
|
BLD-Other | 5/31/2000 | 5/31/2000 | 6/1/2000 | | FAIL |
Carl Dependahl
|
|
|
Call from Michael Nigh with Petra and plan modification is being prepared by Pinicle Engineering and the are going to attempt to continue to use Mark Knowles and the Engineer of Record. I told Michael that we had stopped the work on the canopy and it was now in Plan Reviews hands and until we received a new approved plan and a corrected permit no work could be done on the canopy. He said they understood and would meet with Carl Westfall and get the plan modification in the approval process. gs
|
BLD-Other | 5/30/2000 | 5/30/2000 | 5/30/2000 | | PASS |
Carl Dependahl
|
|
|
Cronology of notice proceedure on this project.
5-16-2000. Carl Dependahl talked with Petra job superintendent. Permit not issued superintendent said they would stop work on the canopy.
5-17-2000 Call from archetect saying canopy lacked permit and they were working on it. Carol Montgomery and I stopped by and reviewed permit requirement with job superintendent (Petra). He stated that they were in the process of getting permit and that he new it was not what was on the plan that was submitted and agreed to stop.
5-18-2000 work not stopped Official stop work placed and double fee assessed.
Occupancy not permitted until matter is straightend out.
5-19-2000 Permit issued but not being constructed per the approved plan. Second stop work issued. Resubmit new plan for review and approval based on as built.
5-25-2000 Mark Knowles project architect sends letter stating they had not built what he designed and is giving 2 options or he is removing himself from the position as the architecht of record.
Options.1. Build the canopy as designed.
2. Assign the project to a new engineer of record. obtain new permit per code.
5-25-2000 I went to site met all interested parties. Jerry Frank, Mike Nigh, owners rep. Rick Haux. Explained any one cought working at this site would be taken by police into custody. They had worked over 2 verbal stop works and 2 written stop works.I instructed the contractor and the owner to meet with Marlene Southerd to explore any options. Rick Haux indicated that they were trying to open Memorial weeked.
5-25-2000 Met with Marlene 4:00 pm. She felt as though a code complying pedestrian walkway could be constructed and allow a temparary occupancy. I agreed and plans were to be submitted and Marlene would review them tomorrow a.m. and we would provide all inspections on the main building which has 2 permits which are not relevant to the problem. It was also determined that a $500 dollar resubmittal fee would be assessed as per building department policy and the fact that they new they were not building what was on the original submittal. Also Marlene would charge $42.00 per hour for her review of the pedestrian walkway submittal. If all of the above conditions were met we would permit a temparary occupancy if all inspection passed and no work what so ever could be done on the canopy until that issue was resolved.
5-26-2000 Warning citation given to Jerry Frank stating all inspections had to be preformed and approved and covered walkway to be compled or no occupancy.
This action necessary as contractor had failed to comply with prior notices.
Walkway was added to existing permit fees were paid and walkway construction was completed. Final Inspection for temparary occupancy were completed by all parties involved and a temparary occupancy was issued at 4:00 p.m. this date.
5-30-2000 Mark Knowles called and I explained what had been done and he agreed with the action. The next move will be the resubmittals from either Mr. Knowles or a new Architect of record and all will be reviewed by Carl Westfall.
|
Meeting | | | 5/26/2000 | | DONE |
|
|
|
Meeting with Jerry Frank (Petra), Michael Nigh (Petra), owner's rep Rich Haux, George Slane and Marlene S. George had Jerry sign a notice of violation. Discussion took place on how to proceed by obtaining approval for pedestrian protection, then to call George to coordinate to gain temporary occupancy. Plan modification form provided to the contractor. (MYS)
|
Plan Reviewer's activity | | | 5/26/2000 | | PASS |
|
|
|
Revised permit to include construction of pedestrian protection so temporary occupancy could be granted. MYS
|
Meeting | | | 5/25/2000 | | DONE |
|
|
|
Meeting in office with Jerry Frank (Petra), Michael Nigh (Petra), owner's rep Rick Haux and Marlene S. Discussed ramifications of filing the change of architect/engineer of record form and how it relates to current approved plans. Discussed pedestrian protection and how to submit plans. See letter on file rejecting structural design change from engineer other than Pinnacle addressed to Petra. (MYS)
|
BLD-Framing/Rough-in | 5/23/2000 | 5/23/2000 | 5/23/2000 | P | NR |
Carl Dependahl
|
|
|
Gene ###-#### Conf. w/westfall, too. need resub. 5/24/00 11:18:06 AM
|
BLD-Framing/Rough-in | 5/22/2000 | 5/22/2000 | 5/22/2000 | P | FAIL |
Carl Dependahl
|
|
|
###-#### please call before you go out THANKS Need "approved" resubmittal; will consult w/Carl W. &/or George. 5/23/00 2:35:10 PM
|
Issue PAID IN FULL permit | | | 5/18/2000 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 5/18/2000 | | |
|
|
|
|
Telephone call | | | 5/17/2000 | | DONE |
|
|
|
talked to gene to verify plans are ready
|
Routing - PLAN CHECK | 5/16/2000 | | 5/17/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/17/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 5/17/2000 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/19/2000 | | 5/17/2000 | | PASS |
Carl Westfall
|
|
|
5/17/00 08:12:12 CJW - activity updated through activity BLDA022 from case BLD00-00939.
|
Routing - FIRE | 5/16/2000 | 5/16/2000 | 5/16/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Reviewer's activity | | | 5/16/2000 | | PASS |
|
|
|
Drawings approved, with conditions, after resubmittal review.
|
Routing - PLAN CHECK | 5/5/2000 | | 5/16/2000 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Plan resubmittals received | | | 5/12/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM MARK KNOWLES. TWO SETS OF SHEETS AO,A2 AND A3, FORWARDED SAME TO CARL WESTFALL. 5/12/00 DAR
|
Routing - FIRE | 5/1/2000 | | 5/4/2000 | | |
Bill Alexander
|
|
|
Lack fire department access and hydrant verification fire flows per UFC
|
Plan Review Completed(1st rev) | | | 5/4/2000 | | |
Bill Alexander
|
|
|
Response required.
|
Routing - PLAN CHECK | 4/19/2000 | | 5/1/2000 | | |
|
|
|
Drawings reviewed but not approved.
|
Plan Reviewer's activity | | | 4/24/2000 | | |
|
|
|
UBC plan review started April 24, 2000. A fax was sent to the architect requiring additional information. The plan review is temporarily "on hold". The plan review was resumed and completed on May 1, 2000. A response is required from the architect. See the conditions list.
|
Routing - PLANNING | 4/19/2000 | | 4/19/2000 | | DONE |
|
|
|
|
Plan routing begun/TENANTS | | | 4/19/2000 | | DONE |
|
|
|
Route to PLANNING, PLAN CHECK and FIRE.
|
Routing - PUBLIC WORKS | 4/11/2000 | | 4/12/2000 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/11/2000 | | DONE |
|
|
|
|
Application received | | | 4/10/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/10/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | | | |
|
|
|
|