BLD-Final | 11/6/2000 | 11/7/2000 | 11/7/2000 | A | PASS |
Alan Hauser
|
|
|
c/c#19842 11/7/2000 12:11:49 PM
|
BLD-Final | 11/7/2000 | 11/6/2000 | 11/6/2000 | P | FAIL |
Russ Owen
|
|
|
Added by Inspector: 407 On 11/7/2000 failed exterior deck guardrail height spacings again.
|
BLD-Final | 11/3/2000 | 11/6/2000 | 11/6/2000 | A | FAIL |
Russ Owen
|
|
|
###-#### call first
|
BLD-Final | 11/2/2000 | 11/3/2000 | 11/3/2000 | P | FAIL |
Steven Webb
|
|
|
jim ###-#### fn: Ext. deck railings & nails in hangers. 11/3/2000 2:04:49 PM
|
BLD-Final | 11/2/2000 | 11/2/2000 | 11/2/2000 | P | CANC |
Steven Webb
|
|
|
fn occ jim ###-#### --cancel
|
BLD-Final | 10/31/2000 | 11/1/2000 | 11/1/2000 | P | FAIL |
Russ Owen
|
|
|
FN INSP- JIM ###-#### -RE-INSP C/n posted. 11/3/2000 10:42:57 AM
|
BLD-Final | 10/30/2000 | 10/31/2000 | 10/31/2000 | P | FAIL |
Russ Owen
|
|
|
###-####c/n posted. 11/1/2000 8:44:46 AM
|
BLD-Framing/Rough-in | 9/13/2000 | 9/14/2000 | 9/14/2000 | A | FAIL |
Russ Owen
|
|
|
JIm ###-#### reinspection
|
BLD-Framing/Rough-in | 9/13/2000 | 9/14/2000 | 9/14/2000 | A | FAIL |
Russ Owen
|
|
|
JIm ###-#### reinspection
|
BLD-Framing/Rough-in | 9/11/2000 | 9/12/2000 | 9/12/2000 | A | PART |
Russ Owen
|
|
|
rein jim ###-#### call first please ok to rock allof house upper flor rear wall needs more staples nails. 9/12/2000 12:29:04 PM
|
BLD-Energy code compliance | 9/5/2000 | 9/6/2000 | 9/6/2000 | A | FAIL |
Russ Owen
|
|
|
jim Jensen ###-#### please call first
|
BLD-Energy code compliance | 9/1/2000 | 9/5/2000 | 9/5/2000 | P | CANC |
Russ Owen
|
|
|
###-####
|
BLD-Framing/Rough-in | 8/30/2000 | 8/30/2000 | 8/30/2000 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/30/2000 at 07:08:04. Contact: .C/N posted, 8/30/2000 6:54:10 PM
|
BLD-Framing/Rough-in | 8/28/2000 | 8/29/2000 | 8/29/2000 | P | CANC |
Russ Owen
|
|
|
call first please\\###-#### jim or ###-#### unable to do. 8/30/2000 9:06:00 AM
|
BLD-Framing/Rough-in | 8/24/2000 | 8/25/2000 | 8/25/2000 | P | FAIL |
|
|
|
jim-- ###-#### re-insp fr c/n and 42$ reinspection fee due 8/25/2000 6:24:23 PM
|
BLD-Framing/Rough-in | 8/23/2000 | 8/23/2000 | 8/23/2000 | P | NR |
Russ Owen
|
|
|
###-#### Need to complete all engineering .left c/n no insp done. 8/24/2000 8:02:30 AM
|
Issue PAID IN FULL permit | | | 6/14/2000 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/1/2000 | | DONE |
|
|
|
|
BLD-Foundation | 5/15/2000 | 5/15/2000 | 5/15/2000 | A | PART |
Russ Owen
|
|
|
Early start, no approved plans, no property pins located on right side due to the dirt mountain.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/15/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/15/2000 | | DONE |
|
|
|
|
Telephone call | | | 5/15/2000 | | DONE |
|
|
|
left a mess that permit is ready
|
Plan assigned to (SAM) | 5/10/2000 | | 5/15/2000 | | PASS |
Steve Munroe
|
|
|
5/15/2000 12:00:08 SAM - activity updated through activity BLDA022 from case BLD00-01070.
|
BLD-Footing | 5/10/2000 | 5/10/2000 | 5/10/2000 | P | CANC |
Russ Owen
|
|
|
###-#### Unable to make this today. 5/12/00 9:03:43 AM
|
Pending Assignment by DJO | 4/19/2000 | | 5/10/2000 | | DONE |
Dan Overy
|
|
|
|
BLD-Footing | 5/1/2000 | 5/2/2000 | 5/3/2000 | P | FAIL |
Russ Owen
|
|
|
###-#### No plans, not ready, setbacks unable to determine hill of dirt. 5/4/00 11:30:03 AM
|
Early Start Permit | | | 4/28/2000 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 4/19/2000 | 4/19/2000 | 4/21/2000 | | DONE |
|
|
|
|
Routing - PLANNING | 4/19/2000 | 4/19/2000 | 4/20/2000 | | DONE |
|
|
|
|
Application received | | | 4/19/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 4/21/2000 | 4/21/2000 | | | PEND |
|
|
|
|
Plan Reviewer's activity | | | | | PEND |
|
|
|
5/10/00 3:50 Called and talked to the designer about the plan. I then called and left a message for the engineering to call me regarding the back wall.
5/15/00 11:00 The engineer and I finally talked about the concerns I had.
|
Print Pending Permit.LaserJet4 | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|