Fee Review-notes | 4/20/2000 | 4/20/2000 | 3/19/2001 | | DONE |
|
|
|
project 320,952. ele105,909. plm41,462. mec 39,370.00
|
BLD-Final | 8/23/2000 | 8/24/2000 | 8/24/2000 | A | PASS |
|
|
|
Scheduled by a contractor via Hello! on 08/23/2000 at 13:00:35. Contact: ###-####. c/c#19746 8/24/2000 10:51:32 AM
|
CHANGE STATUS TO (FNL) | | | 8/24/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/21/2000 | 8/23/2000 | 8/23/2000 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/21/2000 at 09:48:07. Contact: ###-####.
|
FIRE-Final Inspection | 8/14/2000 | 8/15/2000 | 8/15/2000 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/14/2000 at 13:35:44. Contact: ###-####. need NAC wired; test damper operation; sprinkler issues 8/15/2000 11:16:49 AM
|
BLD-Conference | 7/14/2000 | 7/14/2000 | 7/14/2000 | A | PASS |
|
|
|
Added by Inspector: 338 On 7/14/2000 in progress on site walkthrough
|
Received partial PAYMENT | | | 6/5/2000 | | DONE |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 5/25/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/24/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/24/2000 | | DONE |
|
|
|
|
Telephone call | | | 5/24/2000 | | DONE |
|
|
|
left mess that permit is ready
|
Routing - PLAN CHECK | 5/22/2000 | | 5/23/2000 | | PASS |
|
|
|
Approved as noted and plan review comments with architects response attached to plans.
|
Plan assigned to (DRS) | 5/1/2000 | | 5/23/2000 | | PASS |
Dan Stuart
|
|
|
5/23/2000 16:26:45 DRS - activity updated through activity BLDA022 from case BLD00-01087.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/23/2000 | | PASS |
|
|
|
Routed to permit desk for issuance.
|
Routing - FIRE | 5/17/2000 | 5/22/2000 | 5/22/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 5/22/2000 | | FAIL |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 5/22/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM OLSEN AND ASSOCIATES ALL A SHEETS. FORWARDED SAME TO DAN STUART. 5/22/00 DAR
|
Routing - PLAN CHECK | 5/9/2000 | | 5/16/2000 | | FAIL |
|
|
|
Reviewed plan on 5/ 15 / 16 and faxed and mailed copy of items needing response & correction to Russ Phillips @ Olson & Associates Architects. Forwarding plans to fire code analyst for review.
|
Plan resubmittals requested | | | 5/16/2000 | | FAIL |
|
|
|
Copy of plan review comments for response faxed & mailed to architect, Russ Phillips.
|
Routing - PLUMBING | 5/2/2000 | | 5/8/2000 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 5/1/2000 | | 5/2/2000 | | DONE |
|
|
|
|
Pending Assignment by MYS | 4/20/2000 | | 5/1/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 5/1/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE.
|
Plan resubmittals received | | | 4/28/2000 | | DONE |
|
|
|
PLAN RESUBMITTALS RECEIVED FROM OLSON AND ASSOCIATES. ATTACHED SHEETS A1.1 AND A2.3 TO SUBMITTED PLANS. 4/28/00 DAR
|
Plans ACCEPTED BY PLAN TECH | | | 4/25/2000 | | DONE |
|
|
|
FORWARDED PLAN SUBMITTAL REQUIREMENTS TO GREGG OSTROW 4/25/00
DAR
|
Application received | | | 4/20/2000 | | |
|
|
|
|