BLD-Final | 6/28/2000 | 6/29/2000 | 6/29/2000 | P | PASS |
Jim Storey
|
|
|
around 3:00 as per jim michelle ###-#### pending others. 6/29/00 4:05:14 PM
|
FIRE-Final Inspection | 6/27/2000 | 6/27/2000 | 6/27/2000 | P | FAIL |
Rick Jackson
|
|
|
emergency 4gnt 6/30/00 8:11:21 AM
|
FIRE-Final Inspection | 6/26/2000 | 6/26/2000 | 6/26/2000 | P | FAIL |
Rick Jackson
|
|
|
exit door hardware, emergency light not working; address; extinguishers;
|
FIRE-Final Inspection | 6/20/2000 | 6/21/2000 | 6/21/2000 | A | NR |
Rick Jackson
|
|
|
###-#### grinnel called- not ready for kitchen extinguishing system test 6/27/00 2:56:13 PM
|
FIRE-Final Inspection | 6/9/2000 | 6/12/2000 | 6/12/2000 | P | NR |
Rick Jackson
|
|
|
###-#### Contractor called on Friday- won't be ready on 6/12/00 6/13/00 2:38:26 PM
|
BLD-Final | 6/9/2000 | 6/12/2000 | 6/12/2000 | P | PASS |
Jim Storey
|
|
|
Michelle ###-####beam per plan ok 6/12/00 2:59:43 PM
|
Inspection Record Card- Bld | | | 6/1/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/1/2000 | | DONE |
|
|
|
|
Telephone call | | | 6/1/2000 | | DONE |
|
|
|
LEFT MESS FOR MICHELLE CHENG THAT PERMIT IS READY
|
Issue PAID IN FULL permit | | | 6/1/2000 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 5/2/2000 | | 5/31/2000 | | PASS |
Jason Blais
|
|
|
|
Routing - PLANNING | 5/30/2000 | | 5/31/2000 | | PASS |
|
|
|
approved per documents attached to building permit.
|
Routing - PLAN CHECK | 5/31/2000 | | 5/31/2000 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/31/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 5/17/2000 | | 5/30/2000 | | PEND |
|
|
|
With the resubmittal drawings, an exterior change is now shown at the entry. Planning approval is now required. I called the architect and let her know that south and east elevations and an exterior wall section are required. Awaiting these addendums.
|
Plan resubmittals received | | | 5/26/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM BARBARA BEIER ARCHITECT, TWO SETS OF SHEETS 1,2,3,4,5, M1, M2 AND M3, FORWARDED SAME TO JASON BLAIS. 5/26/00 DAr
|
Routing - FIRE | 5/15/2000 | 5/17/2000 | 5/17/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 5/17/2000 | | FAIL |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 5/8/2000 | | 5/15/2000 | | FAIL |
|
|
|
Plan review sent to architect. Plan resubmittals and response required for further review. Plans routed to fire dept.
|
Plan resubmittals requested | | | 5/15/2000 | | PEND |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLUMBING | 5/3/2000 | | 5/8/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/3/2000 | | 5/3/2000 | | DONE |
|
|
|
|
Pending Assignment by MYS | 5/2/2000 | | 5/2/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 5/2/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK AND FIRE. Previously signed by Deb Moran at Central District Health.
|
Plans ACCEPTED BY PLAN TECH | | | 4/28/2000 | | DONE |
|
|
|
VICINITY MAP MISSING , ADDED ONE FROM THE INTERNET AND ADVISED BARBARA BEIER THAT ONE WOULD BE REQUIRED IN THE FUTURE ON ALL PLANS. 4/29/00 DAR
|
Application received | | | 4/26/2000 | | |
|
|
|
|
Fee Review-notes | 4/26/2000 | 4/26/2000 | | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|