PRINT ACTIONS | | | 7/6/2000 | | DONE |
|
|
|
|
BLD-Final | 6/26/2000 | 6/27/2000 | 6/27/2000 | A | PASS |
Tom Arcoraci
|
|
|
the key is in the GFI or above the front door ###-#### L/C issued 6/27/00 2:09:05 PM
|
BLD-Final | 6/23/2000 | 6/26/2000 | 6/26/2000 | A | FAIL |
Alan Hauser
|
|
|
###-####
|
BLD-Energy code compliance | 5/30/2000 | 6/1/2000 | 6/1/2000 | P | PART |
Tom Arcoraci
|
|
|
###-#### R-19 floor required. 6/5/00 10:17:41 AM
|
BLD-Framing/Rough-in | 5/30/2000 | 5/31/2000 | 5/31/2000 | P | PASS |
Tom Arcoraci
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 5/16/2000 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/15/2000 | | DONE |
|
|
|
|
Plan Review Report | | | 5/15/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/15/2000 | | DONE |
Ron Hill
|
|
|
|
Inspection Record Card- Bld | | | 5/15/2000 | | DONE |
|
|
|
|
Telephone call | | | 5/15/2000 | | DONE |
|
|
|
talked to verna to verify plans are ready
|
BLD-Foundation | 5/12/2000 | 5/12/2000 | 5/12/2000 | P | PART |
Tom Arcoraci
|
|
|
###-####
|
Routing - PLANNING | 4/27/2000 | 4/27/2000 | 4/27/2000 | | DONE |
|
|
|
|
Application received | | | 4/27/2000 | | |
|
|
|
|
Routing - PUBLIC WORKS | 4/27/2000 | 4/27/2000 | | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/27/2000 | 4/27/2000 | | | PEND |
|
|
|
|
Early Start Permit | | | | | PEND |
|
|
|
early start issued over 7 working days/pe
|
Pending Assignment by DJO | 4/27/2000 | | | | PEND |
Dan Overy
|
|
|
|