BLD-Final | 8/30/2000 | 8/30/2000 | 8/30/2000 | P | PASS |
Jim Sly
|
|
|
###-####
|
BLD-Energy code compliance | 7/5/2000 | 7/6/2000 | 7/6/2000 | A | PASS |
Jim Sly
|
|
|
Micheal ###-####
|
BLD-Framing/Rough-in | 6/29/2000 | 6/30/2000 | 6/30/2000 | A | PASS |
Jim Sly
|
|
|
mike ###-####
|
BLD-Foundation | 5/12/2000 | 5/12/2000 | 5/12/2000 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 05/12/2000 at 07:13:06. Contact: ###-####. Rebar in wall ok. 5/15/00 10:51:06 AM
|
BLD-Footing | 5/10/2000 | 5/11/2000 | 5/11/2000 | A | FAIL |
Jim Sly
|
|
|
###-#### Footing appears ok but fireplace into 10' setback- notified contractor. 5/12/00 8:54:59 AM
|
BLD-Footing | 5/11/2000 | 5/11/2000 | 5/11/2000 | P | PASS |
Jim Sly
|
|
|
Nonhabitable area ok in setback, (fireplace).325
|
BLD-Footing | 5/9/2000 | 5/10/2000 | 5/10/2000 | A | FAIL |
Jim Sly
|
|
|
###-#### Jerry Not ready. 5/11/00 11:38:33 AM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/4/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/4/2000 | | DONE |
|
|
|
|
Pending Assignment by DJO | 5/1/2000 | | 5/4/2000 | | DONE |
Dan Overy
|
|
|
|
Plan assigned to (SAM) | 5/4/2000 | | 5/4/2000 | | PASS |
Steve Munroe
|
|
|
5/4/2000 10:24:48 SAM - activity updated through activity BLDA022 from case BLD00-01196.
|
Routing - PUBLIC WORKS | 5/1/2000 | 5/1/2000 | 5/2/2000 | | PASS |
|
|
|
|
Routing - PLANNING | 5/1/2000 | 5/1/2000 | 5/1/2000 | | DONE |
|
|
|
|
Application received | | | 5/1/2000 | | |
|
|
|
came in 4/27/00
|
Routing - PLAN CHECK | 5/2/2000 | 5/2/2000 | | | PEND |
|
|
|
|
Print Pending Permit.LaserJet4 | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | | | |
|
|
|
|
Issue PAID IN FULL permit | | | | | |
|
|
|
|