BLD-Final | 9/18/2000 | 9/18/2000 | 9/18/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/18/2000 at 07:59:49. Contact: ###-####.
|
BLD-Final | 9/14/2000 | 9/15/2000 | 9/15/2000 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/14/2000 at 15:24:21. Contact: ###-####. C/N....Issued 9/15/2000 10:51:10 AM
|
BLD-Energy code compliance | 7/19/2000 | 7/20/2000 | 7/20/2000 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/19/2000 at 15:50:38. Contact: ###-####. R-19 underfloor- check at final frame pass. 7/20/00 2:08:30 PM
|
BLD-Framing/Rough-in | 7/18/2000 | 7/19/2000 | 7/19/2000 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/18/2000 at 15:39:05. Contact: ###-####. Need energy code statement. 7/19/00 9:18:26 AM
|
BLD-Foundation | 5/22/2000 | 5/23/2000 | 5/23/2000 | P | PART |
Jim Sly
|
|
|
logan ###-####
|
BLD-Footing | 5/19/2000 | 5/22/2000 | 5/22/2000 | A | FAIL |
Jim Sly
|
|
|
###-#### Early start footing- rebar & setbacks appear ok. 5/23/00 2:23:16 PM
|
Inspection Record Card- Bld | | | 5/19/2000 | | DONE |
|
|
|
|
Telephone call | | | 5/19/2000 | | DONE |
|
|
|
talked to sue to verify plans are ready
|
Plan assigned to (R_H) | 5/18/2000 | 5/18/2000 | 5/18/2000 | | PASS |
|
|
|
5/18/2000 14:40:38 RMH - activity updated through activity BLDA022 from case BLD00-01245.
|
Print Pending Permit.LaserJet4 | | | 5/18/2000 | | DONE |
|
|
|
|
Plan Review Report | | | 5/18/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/18/2000 | | DONE |
|
|
|
|
Early Start Permit | | | 5/18/2000 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 5/3/2000 | 5/3/2000 | 5/4/2000 | | DONE |
|
|
|
|
Routing - PLANNING | 5/3/2000 | 5/3/2000 | 5/4/2000 | | DONE |
|
|
|
|
Application received | | | 5/3/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 5/4/2000 | 5/4/2000 | | | PEND |
|
|
|
|
Pending Assignment by DJO | 5/3/2000 | | | | PEND |
Dan Overy
|
|
|
|
Inspection Record Card- Bld | | | | | |
|
|
|
|
Issue PAID IN FULL permit | | | | | |
|
|
|
|