Permit Information
Permit NumberBLD00-01305
StatusFinaled
Name ADA VISION CENTER
Site Address 1333 W JEFFERSON ST
Project Name 
Customer Number 
ePlanReviewNo
Description
To remodel the 1st floor and basement floor of an existing office building per approved plans on file. 1st floor is 1,500 sq.ft./Basement is 1,458 sq.ft. Work to include, remove interior nonbearing walls and relocate interior walls, construct one fully accessible restroom, create new office area on the first floor and three new offices in the basement, reverse swing of front door to make an accessible approach. Construct new counter at reception area, (the accessible portion will be located at the reception side of counter), Install 5/8 type x gypboard on basement ceiling and construct a wall with 5/8 type x gyboard with a 20 minute fire rated door assembly to separate the basement from the floor above. Miscelaneous related interior finishes. (P.C.#341-00)*RMH*
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes5/9/20005/9/20004/11/2001 DONE
additional valus from subs
BLD-Final9/15/20009/18/20009/18/2000AFAIL
Details
Gib Ogata ###-#### ceilng system not per the listing 9/18/2000 11:13:35 AM
BLD-Final9/18/20009/18/20009/18/2000PPASS
Details
Added by Inspector: 338 On 9/18/2000 c/n removed
Permanent Occupancy 9/18/20009/18/2000 DONE
Details
Permanent occupancy UNPAID FEE  9/18/2000 DONE
Perm. Occ. Cert. #8382 issued 9-18-00 to the Ada Vision Center.
BLD-Final9/12/20009/12/20009/12/2000PFAIL
Details
FN OCC-- JILL ###-####--CELL ###-#### c/n issued hardware, occ seperation 9/12/2000 2:46:50 PM ceiling and drywall. gave verbal as of friday proceedure to vacae building will start
9/12/2000 2:47:50 PM
FIRE-Final Inspection9/12/20009/12/20009/12/2000PPASS
DetailsRick Jackson
JILL ###-#### & CELL ###-#### FIRE FN -ALSO FN OCC
FIRE-Final Inspection9/8/20009/11/20009/11/2000AFAIL
DetailsJoe Tawney
Jill ###-#### Reinsp Fail C/N not completed 9/11/2000 12:27:08 PM
FIRE-Final Inspection9/8/20009/8/20009/8/2000PFAIL
DetailsRick Jackson
Scheduled by Inspector: 409 On 9/8/2000 emergency light not working; basement door not latching; hard lid under stairs has large gaps; wrong hardware on bathroom door; sign above main exit for key locking; handicap sign on bathroom
BLD-Framing/Rough-in9/7/20009/8/20009/8/2000APART
Details
###-#### pending install of rated ceiling system in the basement 9/8/2000 11:45:34 AM
BLD-Final9/7/20009/8/20009/8/2000AFAIL
Details
Skip ###-#### need c/n of 9/7/2k corrected first 9/8/2000 11:45:59 AM
FIRE-Final Inspection9/8/20009/8/20009/8/2000PNR
DetailsRick Jackson
Jill ###-#### Ogata called and said they won't be ready until 9/11/2000 9/8/2000 12:39:36 PM
Print Occupancy Form  9/8/2000 DONE
FIRE-Final Inspection9/6/20009/7/20009/7/2000AFAIL
DetailsRick Jackson
Tara ###-#### plans call for 1 hr ceiling in basement - not done; door hardware needed; ADA bathroom not complete; c/n issued for many items 9/7/2000 10:20:39 AM
BLD-Final9/6/20009/7/20009/7/2000AFAIL
DetailsTony Young
Tara ###-####
trades not signed off,, c/n posted 9/7/2000 11:59:02 AM
Issue PAID IN FULL permit  7/3/2000 DONE
Inspection Record Card- Bld  6/8/2000 DONE
Print Occupancy Form  6/8/2000 DONE
Telephone call  6/8/2000 DONE
left mess for bill matter that permit is ready
Plan assigned to (R_H)5/10/2000 6/6/2000 PASS
Details
6/6/2000 08:13:43 RMH - activity updated through activity BLDA022 from case BLD00-01305.
Case Summary (BLD)  6/6/2000 DONE
Case Summary (BLD)  6/6/2000 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/6/2000 DONE
Plan Review Completed(1st rev)  5/26/2000 FAIL
failed bldg review
Routing - FIRE5/23/2000 5/26/2000 PASS
Plan Reviewer's activity  5/22/2000 FAIL
DetailsRon Hill
Emailed requirements to Bill Matter. Route to fire department.
Case Summary (BLD)  5/22/2000 DONE
Routing - PLAN CHECK5/12/2000 5/22/2000 PEND
DetailsRon Hill
Additional plans submitted  5/15/2000 DONE
RECEIVED NEW SHEETS A-1, INCOPORATED THEM WITH ORIGINAL PLANS. 5/15/00 DAR
Application received  5/12/2000 DONE
Routing - PUBLIC WORKS5/10/2000 5/12/2000 DONE
Plan routing begun/TENANTS  5/10/2000 DONE
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  5/10/2000 DONE
SENT FAX TO BILL MATTER LISTING REQUIRED SUBMITTALS FOUND ON SCREENING REVIEW. 5/10/00 DAR
Recd Pcfee & Taken To Pln CK     
Routing - PLAN CHECK5/26/2000   PEND