Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD00-01317
StatusFinaled
Name VANILLA FINISH (NO TENANT)
Site Address 9398 W OVERLAND RD
Project NameLYNX CENTER-1ST FLR
Customer Number 
ePlanReviewNo
Description
LYNX CENTER-1ST FLOOR "VANILLA FINISH" (NO TENANT) - Constructing a new 1,893 sq. ft. "Vanilla Finish" space in northwest corner of first floor per approved plans on file. Building Shell done under BLD97-1528. No Occupancy is allowed under this permit. A Letter of Completion is to be issued when done. A separate permit is to be obtained and a Certificate of Occupancy is required when the space is to be occupied. Work to include new accessible restrooms, new interior walls with doors, interior finish, new suspended ceiling, fire sprinkler work, new plumbing, new mechanical, and new electrical work. NOTE: This building is fully fire sprinklered for area increase. (P.C.#343-00) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes5/10/20005/10/20007/24/2000 DONE
Letter of compliance  7/13/2000 DONE
Letter of Compliance #18524 issued 7-13-00.
BLD-Final7/11/20007/11/20007/11/2000PPASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 07/11/2000 at 10:42:23. Contact: ###-####. Card to bldr. 7/12/00 10:32:12 AM
FIRE-Final Inspection7/7/20007/7/20007/7/2000PPASS
DetailsJoe Tawney
JC ###-#### OK for certificate of completion. 7/10/00 9:49:58 AM
BLD-Other6/30/20007/5/20007/5/2000APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 06/30/2000 at 11:48:23. Contact: ###-####.
BLD-Framing/Rough-in6/16/20006/16/20006/16/2000PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 06/16/2000 at 10:24:57. Contact: ###-####.
Issue PAID IN FULL permit  6/7/2000 DONE
Print Occupancy Form  6/2/2000 DONE
Plan Reviewer's activity  6/2/2000 DONE
left mess that permit is ready for ryan anderson
Routing - PLAN CHECK6/1/2000 6/1/2000 PASS
Plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  6/1/2000  
Plan assigned to (JCB)5/11/2000 6/1/2000 PASS
DetailsJason Blais
Routing - FIRE5/25/20005/31/20005/31/2000 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  5/31/2000 PASS
DetailsBill Alexander
Routing - PLAN CHECK5/12/2000 5/25/2000 PEND
Plan review report sent and faxed to architect. No response required. Permit approval dependent on fire department approval. Plans routed to fire dept.
Routing - PUBLIC WORKS5/12/2000 5/12/2000 DONE
Pending Assignment by MYS5/11/2000 5/11/2000 DONE
DetailsMarlene Southard
Plan routing begun/TENANTS  5/11/2000 DONE
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  5/11/2000 DONE
Received Certificate of Value  5/10/2000 DONE
Application received  5/10/2000  
Recd Pcfee & Taken To Pln CK     
Inspection Record Card- Bld