Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD00-01386
StatusExpired
Name STARBUCKS COFFEE
Site Address 2209 UNIVERSITY DR
Project NameCAPITOL VILLAGE BLDG. 1B
Customer Number 
ePlanReviewNo
Description
To construct a new 1,697 sq.ft. tenant space for assembly dining/coffee shop in shell building (BLD99-02669) per approved plans on file. Work to include accessible restrooms, new one-hour rated tenant demising wall, new interior walls and doors, interior finish, suspended ceiling areas, kitchen/workroom/service area, possible fire sprinkler adjustments, new mechanical including rooftop unit, new plumbing, and new electrical work. NOTE: THIS BUILDING IS FULLY FIRE SPRINKLERED FOR AREA INCREASE. (P.C.#361-00) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection9/27/20009/27/20009/27/2000APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/27/2000 at 06:18:55. Contact: ###-####. need assembly permit 9/27/2000 4:09:56 PM
BLD-Final9/27/20009/27/20009/27/2000PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/27/2000 at 06:20:25. Contact: ###-####.
BLD-Final9/25/20009/26/20009/26/2000PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/25/2000 at 21:22:52. Contact: ###-####. pending health and fire insp. 9/26/2000 5:03:46 PM
BLD-Other9/21/20009/21/20009/21/2000APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/21/2000 at 06:04:21. Contact: ###-####. ceilling ok for cover upon others signing off. 9/21/2000 10:18:39 AM
BLD-Framing/Rough-in9/5/20009/6/20009/6/2000APART
Details
Scheduled by a contractor via Hello! on 09/05/2000 at 20:01:18. Contact: ###-####. ok to cover framing 9/6/2000 4:23:32 PM
BLD-Framing/Rough-in9/5/20009/5/20009/5/2000PFAIL
Details
###-#### ok to cover 1-side pending plmg appovals and re frame insp 9/5/2000 3:14:27 PM
Issue PAID IN FULL permit  8/21/2000 DONE
Routing - PLAN CHECK7/25/2000 7/27/2000 PASS
Plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  7/27/2000 PASS
Inspection Record Card- Bld  7/27/2000 DONE
Print Occupancy Form  7/27/2000 DONE
Telephone call  7/27/2000 DONE
called Steve Speidel at ###-#### permit ready for pickup
Plan assigned to (JCB)5/19/2000 7/27/2000 PASS
DetailsJason Blais
7/27/2000 13:29:22 JCB - activity updated through activity BLDA022 from case BLD00-01386.
Routing - FIRE7/20/2000 7/25/2000 PASS
Approved subject to required automatic sprinkler protection
Plan Review Completed(1st rev)  7/25/2000 PASS
Routing - PLAN CHECK7/20/2000 7/20/2000 PEND
Third time around, adequate plans have been provided. Permit and plan approval is dependent on Fire Department approval. Plans routed to Fire Dept.
Plan resubmittals received  7/17/2000 DONE
RECEIVED TWO COPIES OF REVISED SHEETS A3.1, A6.2. ROUTED TO JASON. KMM
Plan resubmittals received  7/5/2000 DONE
RECEIVED TWO COPIES OF REVISED SHEETS A1.0, A3.1, A3.2, A4.0, A4.1, A5.0, A5.1, A6.0, A6.2. ROUTED TO JASON B. KMM
Plan Reviewer's activity  7/5/2000 HOLD
Plan resubmittals were inadequate. Accessibility issues were not fully addressed and are not shown in compliance. More resubmittal drawings are required for further review.
Plan resubmittals requested  7/5/2000 PEND
More resubmittal drawings required for further review to address accessibility issues.
Routing - PLAN CHECK5/24/2000 6/1/2000 HOLD
Plan review report faxed to architect, tenant, and other interested party. Plan resubmittals and response required for further review. Major items to be addressed and resubmitted. Plans being put on hold until resubmittals come in. Fire Dept. cannot do review without new information.
Plan resubmittals requested  6/1/2000  
Plan resubmittals and response required for further review.
Routing - PLUMBING5/23/2000 5/24/2000 PASS
Routing - PUBLIC WORKS5/22/2000 5/23/2000 DONE
Plans ACCEPTED BY PLAN TECH  5/22/2000 PASS
Pending Assignment by MYS5/19/2000 5/19/2000 DONE
DetailsMarlene Southard
Plan routing begun/TENANTS  5/19/2000 DONE
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  5/19/2000 PEND
REQUIRES BUILDING CODE DATA ON FRONT STREET CODES AND YEARS CONSTRUCTIONTYPE FIRE SPRINKLER , ALARM SYSTEM AND SMOKE CONTROL SYSTEM INFORMATION. FAXED TO GINGER STINCHFIELD AT ###-#### KMM
Received Certificate of Value  5/17/2000 DONE
Application received  5/17/2000  
Fee Review-notes5/17/20005/17/2000   
Recd Pcfee & Taken To Pln CK