Fee Review-notes | 5/19/2000 | 5/19/2000 | 4/11/2001 | | DONE |
|
|
|
had changes need final cert at end of job
|
Permanent occupancy UNPAID FEE | | | 12/8/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8497 issued 12-8-00 to Bonneville Blueprint.
|
Permanent Occupancy | | 12/7/2000 | 12/7/2000 | | DONE |
|
|
|
|
BLD-Final | 12/1/2000 | 12/4/2000 | 12/4/2000 | A | PASS |
Russ Owen
|
|
|
###-#### harvey fn.still needs zoning approval,all other items ok. 12/4/2000 9:43:25 AM
|
BLD-Final | 11/30/2000 | 11/30/2000 | 11/30/2000 | P | PART |
Russ Owen
|
|
|
###-####ok temp need final p/z zoning and fire caulk penit thru 1 hr wall also roof joist. 11/30/2000 2:34:29 PM
|
Code Occupancy Approval | | | 11/30/2000 | | FAIL |
|
|
|
Bonded $412.00 for sod - Temporary signed.
|
BLD-Final | 11/22/2000 | 11/28/2000 | 11/28/2000 | A | NR |
Tom Arcoraci
|
|
|
###-####
|
Code Occupancy Approval | | | 11/28/2000 | | FAIL |
|
|
|
Still have landscaping to finish relevant to laying sod and putting in bark - also the canopies are not on the structure. Harvey indicates they will have this done tomorrow - I will recheck.
|
FIRE-Final Inspection | 11/22/2000 | 11/27/2000 | 11/27/2000 | A | PASS |
Rick Jackson
|
|
|
###-#### /// doors in occupancy separation wall will have closures installed for structural inspector 11/27/2000 10:46:48 AM
|
PubWorks Occupancy Approval | | | 11/16/2000 | | DONE |
|
|
|
Signed Permanent Occupancy 11/16/00. S. Landaluce
|
BLD-Framing/Rough-in | 11/15/2000 | 11/15/2000 | 11/15/2000 | P | PART |
Tom Arcoraci
|
|
|
###-#### ceiling inspection grid ok 11/15/2000 4:47:01 PM
|
BLD-Framing/Rough-in | 9/29/2000 | 10/2/2000 | 10/2/2000 | A | PART |
Alan Hauser
|
|
|
no inspection of rated wall 10/2/2000 12:09:59 PM
|
BLD-Foundation | 8/16/2000 | 8/17/2000 | 8/17/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/16/2000 at 14:02:39. Contact: ###-####. Met Gary w/ K2 onsite...pend spec insp reports (MTI) 8/17/2000 11:16:37 AM
|
BLD-Footing | 8/10/2000 | 8/11/2000 | 8/11/2000 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 08/10/2000 at 13:35:39. Contact: ###-####. spec insp 8/11/2000 10:17:35 AM
|
(F) Reprint permit | | | 8/9/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/8/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/8/2000 | | DONE |
|
|
|
|
Telephone call | | | 8/8/2000 | | DONE |
|
|
|
plans are ready again called Rod Gardener at ###-####
|
Issue PAID IN FULL permit | | | 8/8/2000 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 7/28/2000 | | 8/7/2000 | | PASS |
Mike Otto
|
|
|
8/7/2000 16:25:26 MYS - activity updated through activity BLDA022 from case BLD00-01426.
|
Routing - PLAN CHECK | 8/7/2000 | | 8/7/2000 | | PASS |
|
|
|
Taken to front desk for issuance.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2000 | | DONE |
|
|
|
Taken to front desk for issuance on behalf of Mike Otto.
|
Routing - FIRE | 8/4/2000 | 8/4/2000 | 8/4/2000 | | PASS |
Bill Alexander
|
|
|
Resubmittal sheets C1.1 and C-2 (access shift).
|
Routing - PUBLIC WORKS | 8/1/2000 | | 8/4/2000 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/27/2000 | | DONE |
|
|
|
Resubmittal sheets C1.1 and C-2 received and forwarded to Mike O.
|
Telephone call | | | 7/24/2000 | | DONE |
|
|
|
called rocky--adjusted fees for drainage-$300.00 lower-
|
Routing - PLAN CHECK | 7/10/2000 | | 7/11/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/11/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/11/2000 | | DONE |
|
|
|
|
Telephone call | | | 7/11/2000 | | DONE |
|
|
|
LEFT MESS FOR ROCKY THAT PERMIT IS READY--ALSO NEED ACHD
|
Plan assigned to (MLO) | 5/22/2000 | | 7/11/2000 | | PASS |
Mike Otto
|
|
|
7/11/2000 08:43:01 MLO - activity updated through activity BLDA022 from case BLD00-01426.
|
Routing - FIRE | 7/5/2000 | 7/9/2000 | 7/9/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 7/7/2000 | | PEND |
|
|
|
RECEIVED ADDITIONAL ENGINEERING FOR THE FOUNDATION BOLTS.
|
Routing - PLUMBING | 7/5/2000 | | 7/5/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/30/2000 | | 7/3/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 6/28/2000 | | 6/28/2000 | | FAIL |
|
|
|
IT WAS NOTED THAT THE LENGTH OF THE FOUNDATION BOLTS HAS BEEN OVER LOOKED BY THE ENGINEERS. ARCHITECT CONTACTED BY PHONE AND WILL PROVIDE ADDITIONAL CALCS AND LENGTHS FOR 3/4 AND 1 INCH ANCHOR BOLTS. MLO
|
Plan resubmittals received | | | 6/27/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED DRAWINGS C1.1, A1.1, A2.1, A3.1, P1.1, E1.1. ONE COPY OF HIGH PILE STORAGE LETTER. ROUTED TO MIKE O. KMM
|
Plan resubmittals received | | | 6/27/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEET C-2
ONE COPY OF SHEET C1.1
ONE COPY OF SET OF SHOP DRAWINGS FOR BUILDING
ONE COPY OF SET OF FOUNDATION CALCULATIONS.
ONE COPY OF SET OF BUILDING CALCULATIONS.
ROUTED TO MIKE O. KMM
|
Routing - FIRE | 6/14/2000 | 6/19/2000 | 6/19/2000 | | FAIL |
Bill Alexander
|
|
|
UFC questions on hydrands, access, storage, warehouse commodity classifications, etc.
|
Plan Review Completed(1st rev) | | | 6/19/2000 | | FAIL |
Bill Alexander
|
|
|
plans returned to plan check
|
Plan resubmittals requested | | | 6/14/2000 | | FAIL |
|
|
|
UBC CORRECTIONS
|
Routing - PLAN CHECK | 6/12/2000 | | 6/14/2000 | | FAIL |
|
|
|
CORRECTIONS MAILED TO ARCHITECT. MLO
|
Routing Off Site - STRUCTURAL | 5/30/2000 | | 6/13/2000 | | PASS |
|
|
|
FORWARDED PLANS TO CONSULATING STRUCTURAL ENGINEER VIA PDQ. DAR 5/30/00 DAR,
SENT SHOP DRAWINGS OF THE BUILDING TO THE CONSULATING ENGINEER VIA PDQ. 6/5/00 DAR
|
Routing - PLANNING | 5/30/2000 | | 6/12/2000 | | PASS |
|
|
|
Approve per revised site/landscape plan and elevations dated 6/9/00. X-ref. DRH00-49.
|
Plan resubmittals received | | | 6/9/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEET C1.1 ROUTED TO MIKE O. KMM
|
Additional plans submitted | | | 6/5/2000 | | PASS |
|
|
|
RECEIVED TWO SETS OF SHOP DRAWINGS FROM ROCKY. ATTACHED ONE SET TO CIRCULATING PLANS IN TKW'S OFFICE. SENT SECOND SET TO CONSUALTATING ENGINEER.
|
Routing - PLUMBING | 5/26/2000 | | 5/30/2000 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 5/22/2000 | | 5/26/2000 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/22/2000 | | DONE |
|
|
|
REQUESTED SHOP DRAWINGS FOR BUILDING FROM ROCKY TOWLE. WILL SEND PLANS TO CONSULTING ENGINEER WHEN THAT INFORMATION IS RECEIVED. 5/22/00 DAR
RECEIVED BUILDING PLANS AND SPECIFICATIONS, PLANS ARE NOT MINIMUM SIZE CALLED ROCKY TO ADVISE HIM OF SAME.
|
Application received | | | 5/19/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/19/2000 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | | | |
|
|
|
|