Fee Review-notes | 5/23/2000 | 5/23/2000 | 4/11/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/2/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8418 issued 10-2-00 to the Rent A Center in the Shopko Plaza.
|
Permanent Occupancy | | 9/29/2000 | 9/29/2000 | | DONE |
|
|
|
|
BLD-Final | 9/28/2000 | 9/29/2000 | 9/29/2000 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/28/2000 at 14:02:03. Contact: ###-####.
|
BLD-Conference | 9/28/2000 | 9/28/2000 | 9/28/2000 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 9/28/2000 w/ builder re final: htg ok w/o permit per Alan H
|
BLD-Final | 9/25/2000 | 9/27/2000 | 9/27/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 09/25/2000 at 15:44:09. Contact: ###-####.
|
FIRE-Final Inspection | 9/25/2000 | 9/26/2000 | 9/26/2000 | A | PASS |
Joe Tawney
|
|
|
###-####. Reinsp OK for Occ or certificate of completion 9/26/2000 12:18:12 PM
|
BLD-Final | 9/14/2000 | 9/15/2000 | 9/15/2000 | A | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 09/14/2000 at 08:29:26. Contact: ###-####.
fire not signed off 9/15/2000 8:52:24 AM
|
FIRE-Final Inspection | 9/14/2000 | 9/14/2000 | 9/14/2000 | P | FAIL |
Joe Tawney
|
|
|
###-####. Reinsp Fail Manual Flush
bolts 9/15/2000 7:46:58 AM
|
FIRE-Final Inspection | 9/7/2000 | 9/8/2000 | 9/8/2000 | A | FAIL |
Joe Tawney
|
|
|
###-####. Final Fail C/N issued 9/8/2000 4:30:20 PM
|
FIRE-Final Inspection | 8/30/2000 | 8/31/2000 | 8/31/2000 | P | CANC |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 08/30/2000 at 16:16:45. Contact: ###-####. Cancelled to be resched at contr request 8/31/2000 3:38:11 PM
|
BLD-Final | 8/30/2000 | 8/31/2000 | 8/31/2000 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/30/2000 at 16:18:23. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/10/2000 | 8/10/2000 | 8/10/2000 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 08/10/2000 at 10:13:38. Contact: ###-####. need arch approval and grid not per plan 8/11/2000 8:18:17 AM
|
FIRE-Final Inspection | 8/4/2000 | 8/7/2000 | 8/7/2000 | A | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 08/04/2000 at 16:06:05. Contact: ###-####. Ok to occupy expanded area. Final to be done when all work complete 8/7/00 3:23:02 PM
|
BLD-Final | 8/4/2000 | 8/7/2000 | 8/7/2000 | A | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 08/04/2000 at 16:07:40. Contact: ###-####. not ready for final ok for wip 8/7/2000 11:59:37 AM
|
Routing - FIRE | 8/4/2000 | 8/4/2000 | 8/4/2000 | | PASS |
Bill Alexander
|
|
|
Fire sprinkler head layout plans (3) from W.A. Steele provided (did not see fire notes of requirement). Fire department notes added and 2 sets returned with notes for field inspector review.
|
FIRE-Final Inspection | 8/1/2000 | 8/3/2000 | 8/3/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 08/01/2000 at 09:52:28. Contact: ###-####. Reinsp. fail sprinkler submittals not on site 8/7/00 8:34:55 AM
|
BLD-Final | 8/1/2000 | 8/3/2000 | 8/3/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/01/2000 at 09:54:23. Contact: ###-####.need fire 8/3/2000 2:52:17 PM
|
BLD-Other | 7/14/2000 | 7/17/2000 | 7/17/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 07/14/2000 at 15:45:41. Contact: ###-####. Need elec. for clg. & taut pod wires. 7/18/00 2:08:47 PM
|
FIRE-Sprinkler Rough-in | 7/14/2000 | 7/17/2000 | 7/17/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 07/14/2000 at 15:47:10. Contact: ###-####. No approved spklr. submittal on site. 7/18/00 2:02:35 PM
|
BLD-Framing/Rough-in | 6/21/2000 | 6/22/2000 | 6/22/2000 | A | PART |
Carl Dependahl
|
|
|
wes ###-#### Ok to cover office walls 6/23/00 11:20:05 AM
|
BLD-Framing/Rough-in | 6/20/2000 | 6/21/2000 | 6/21/2000 | A | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 06/20/2000 at 17:24:47. Contact: ###-####. Left msg. 6/22/00 9:36:01 AM
|
Issue PAID IN FULL permit | | | 6/8/2000 | | DONE |
|
|
|
|
Routing - FIRE | 6/5/2000 | 6/7/2000 | 6/7/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 6/7/2000 | | FAIL |
Bill Alexander
|
|
|
UBC issues
|
Routing - PLAN CHECK | 6/7/2000 | | 6/7/2000 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2000 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/7/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/7/2000 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 5/26/2000 | | 6/7/2000 | | PASS |
Jason Blais
|
|
|
|
Plan resubmittals received | | | 6/6/2000 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM WES STEELE, TWO SETS OF A-1 AND A-2, FORWARDED SAME TO JASON BLAIS. 6/6/00 DAR
|
Routing - PLAN CHECK | 5/31/2000 | | 6/5/2000 | | FAIL |
|
|
|
Plan review report faxed to architect. Plan resubmittals and response required for further review. Plans routed to fire dept.
|
Plan resubmittals requested | | | 6/5/2000 | | PEND |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PUBLIC WORKS | 5/26/2000 | | 5/31/2000 | | DONE |
|
|
|
|
Pending Assignment by MYS | 5/26/2000 | | 5/26/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 5/26/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 5/24/2000 | | DONE |
|
|
|
|
Application received | | | 5/23/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/23/2000 | | DONE |
|
|
|
|
Telephone Call | | | | | |
|
|
|
left mess for wes steele that permit is ready
|