Permit NumberBLD00-01478
StatusFinaled
Name WYNDEMERE COMPANY THE AND
Site Address 1450 W CAMELBACK LN
Project NameCAMELBACK APARTMENTS
Customer Number 
ePlanReviewNo
Description
BUILDING TYPE "A" * TO CONSTRUCT A NEW 5,300 SQ.FT. TWO STORY, WOOD FRAMED, TYPE V-N 8 UNIT APARTMENT BUILDING. THE FIRST FLOOR CONTAINS 4 TYPE B UNITS AT 619 SQ.FT EACH AND THE SECOND FLOOR CONTAINS 4 TYPE A-1 UNITS WITH A LOFT AT 744 SQ.FT. EACH. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST AND CABO/ANSI A117.1. DRH99-0150 CUP99-0101 & CFH99-0022 MJP
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/25/20036/25/20036/25/2003 DONE
Permanent occupancy  8/26/2002 DONE
Perm. Occ. Cert. #9319 issued 8-26-02 to the Camelback Apts.
BLD-Final8/14/20028/14/20028/14/2002PPASS
DetailsTony Young
Permanent Occupancy 8/14/20028/14/2002 DONE
Details
BLD-Final7/25/20027/26/20027/26/2002AFAIL
DetailsTony Young
joe; Phone #: ###-####
c/n posted, need trades and other items 7/26/2002 10:38:21 AM
Temporary occupancy  11/19/2001 PART
Temp. Occ. Cert. #4649 issued 11-19-01 to the Camelback Apts.
FIRE-Final Inspection11/8/200111/9/200111/9/2001APASS
DetailsTroy Cobbley
OK for perm occ 11/9/2001 4:32:00 PM
BLD-Framing/Rough-in11/8/200111/9/200111/9/2001PPART
DetailsTony Young
###-#### CHRIS
temp ok pending trades 11/13/2001 8:56:30 AM
BLD-Wall cover5/16/20015/17/20015/17/2001PPASS
DetailsTony Young
look at fire wall on north end, verify f/b in upper units 5/16/2001 1:27:09 PM
BLD-Energy code compliance5/15/20015/16/20015/16/2001PPASS
DetailsTony Young
verify 1 hr fire sep., and insulation 5/15/2001 2:35:11 PM
insulation ok, firewall ok on so. main floor 5/16/2001 1:31:32 PM
BLD-Framing/Rough-in5/15/20015/15/20015/15/2001PPART
DetailsTony Young
chris ###-####,,,wip, ok so far, also insulation is about done, ok so far,, ext. stairs not in yet 5/15/2001 2:33:57 PM
BLD-Framing/Rough-in5/9/20015/9/20015/9/2001ANR
DetailsTony Young
Scheduled by a contractor via Hello! on 05/09/2001 at 07:21:44. Contact: ###-####.
BLD-Framing/Rough-in5/9/20015/9/20015/9/2001PPART
DetailsTony Young
c/n posted on insulation sticker, firewall vertical and horizontal, strap top plates, etc. 5/9/2001 2:46:27 PM
BLD-Framing/Rough-in5/7/20015/8/20015/8/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 05/07/2001 at 16:57:20. Contact: ###-####.ext. shear ok w/ verbal corrections, ok to insulate upstairs, need straps, seal fire wall, etc. 5/8/2001 10:45:51 AM
BLD-Footing2/14/20012/15/20012/15/2001APART
DetailsTony Young
###-####
int. ftg. wip 2/15/2001 11:36:20 AM
(F) Reprint permit  12/13/2000 DONE
BLD-Foundation11/27/200011/28/200011/28/2000PPART
DetailsTony Young
Chris ###-####
wip, ok w/ verbal corrections 11/28/2000 1:35:29 PM
BLD-Footing11/9/200011/13/200011/13/2000APART
DetailsTony Young
FT INSP CHRIS ###-####
wip, ok w/ verbal corrections 11/13/2000 10:06:08 AM
Issue PAID IN FULL permit  11/9/2000 DONE
Routing Off Site - A.C.H.D11/8/200011/8/200011/8/2000 DONE
cert. #01-00066-by Nan 24 units $18,744.00-
Inspection Record Card- Bld  8/29/2000 DONE
Print Occupancy Form  8/29/2000 DONE
Telephone call  8/29/2000 DONE
Called John Price at###-####
Routing - PLAN CHECK8/10/2000 8/28/2000 DONE
Plan Reviewer's activity  8/28/2000 PASS
Print Pending Permit.LaserJet4  8/28/2000 DONE
PLANS/APPL TAKEN TO FRONT DESK  8/28/2000 DONE
Plan assigned to (M_P)5/25/2000 8/28/2000 PASS
DetailsMike Phillips
8/28/2000 09:58:01 M_P - activity updated through activity BLDA022 from case BLD00-01478.
Plan Reviewer's activity  8/23/2000 FAIL
Need additional information for follow up review.
Routing - FIRE8/8/20008/9/20008/9/2000 PASS
DetailsBill Alexander
Routing - PUBLIC WORKS8/8/20008/8/20008/8/2000 PASS
Routing - PLAN CHECK7/25/2000 8/8/2000 PEND
Routing - PLAN CHECK7/24/2000 7/24/2000  
routing to plumbing
Routing - PLUMBING7/24/2000 7/24/2000 PASS
Routing - FIRE7/19/20007/21/20007/21/2000 FAIL
DetailsBill Alexander
UBC issues related to UFC requirements.
Plan Review Completed(1st rev)  7/21/2000 FAIL
Plan Reviewer's activity  7/19/2000 FAIL
ADDITIONAL INFORMAITON REQUIRED FOR FURTHER REVIEW.
Plan resubmittals received  7/13/2000 DONE
RECEIVED THREE COPIES OF REVISED SHEETS C6.0, P1.0, P1.1, P2.0, P2.1 ROUTED TO MIKE P. KMM
Plan resubmittals received  6/30/2000 DONE
RECEIVED THREE SETTS SHEETS A3.7, A3.8, A4.0, A4.1, A4.2, A4.3, A4.4, A4.5, A4.7 A4.9, A4.10, A6.0, A10.1 TWO COPIES OF CALCS. ROUTED TO MIKE P. KMM
Routing - PLUMBING6/20/2000 6/21/2000 FAIL
Routing - PLANNING6/12/2000 6/20/2000 PASS
Approve per DRH99-150 & CUP98-146
Routing Off Site - STRUCTURAL6/6/2000 6/16/2000 FAIL
faxing comment to architect.
Routing - PUBLIC WORKS6/5/2000 6/12/2000 FAIL
REQUIRES HILLSIDE GRADING APPROVAL. KMM
Received partial PAYMENT  6/5/2000 DONE
Application received  5/25/2000  
Routing - PLAN CHECK6/22/2000   MJP
ROUTING TO FIRE
Print Pending Permit.LaserJet4