Permit Information
Permit NumberBLD00-01483
StatusFinaled
Name CAMELBACK APARTMENTS
Site Address 1402 W CAMELBACK LN
Project NameCAMELBACK APARTMENTS
Customer Number 
ePlanReviewNo
Description
BUILDING TYPE "A" * TO CONSTRUCT A NEW 5,300 SQ.FT. TWO STORY, WOOD FRAMED, TYPE V-N 8 UNIT APARTMENT BUILDING. THE FIRST FLOOR CONTAINS 4 TYPE B UNITS AT 619 SQ.FT EACH AND THE SECOND FLOOR CONTAINS 4 TYPE A-1 UNITS WITH A LOFT AT 744 SQ.FT. EACH. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST AND CABO/ANSI A117.1. DRH99-0150 CUP99-0101 & CFH99-0022 MJP
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/25/20036/25/20036/25/2003 DONE
Permanent occupancy  10/17/2002 DONE
Perm. Occ. Cert. #9404 issued 10-17-02 to the Camelback Apts.
Print Occupancy Form  10/15/2002 DONE
Case Summary (BLD)  10/8/2002  
BLD-Final8/30/20028/30/20028/30/2002PPASS
DetailsTony Young
Joe ###-####
Permanent Occupancy 8/30/20028/30/2002 DONE
Details
BLD-Final1/31/20022/1/20022/1/2002APART
DetailsTony Young
Scheduled by a contractor via Hello! on 01/31/2002 at 16:36:45. Contact: ###-####.ok for temp 2/1/2002 11:07:54 AM
FIRE-Final Inspection1/31/20021/31/20021/31/2002PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 01/31/2002 at 10:16:33. Contact: ###-####.
BLD-Energy code compliance8/3/20018/6/20018/6/2001APASS
DetailsTony Young
Scheduled by a contractor via Hello! on 08/03/2001 at 13:27:40. Contact: ###-####.
BLD-Framing/Rough-in7/31/20017/31/20017/31/2001PPASS
DetailsTony Young
Chris ###-####
BLD-Footing3/19/20013/19/20013/19/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 03/19/2001 at 08:38:29. Contact: ###-####.int. ftgs ok 3/20/2001 8:48:09 AM
(F) Reprint permit  12/13/2000 DONE
BLD-Foundation12/8/200012/11/200012/11/2000APART
DetailsTony Young
Scheduled by a contractor via Hello! on 12/08/2000 at 08:58:53. Contact: ###-####.
wip, ok w/ verbal corrections 12/11/2000 9:33:54 AM
BLD-Footing12/1/200012/4/200012/4/2000APART
DetailsTony Young
Scheduled by a contractor via Hello! on 12/01/2000 at 16:25:33. Contact: ###-####.wip, ok w/ verbal corrections 12/4/2000 10:23:54 AM
BLD-Footing11/30/200012/1/200012/1/2000PCANC
DetailsTony Young
Chris ###-####
Issue PAID IN FULL permit  11/9/2000 DONE
Routing Off Site - A.C.H.D11/8/200011/8/200011/8/2000 DONE
cert. #01-00066 Nan on 11/8/00-$18744.00-for 24 units
Inspection Record Card- Bld  8/29/2000 DONE
Print Occupancy Form  8/29/2000 DONE
Telephone call  8/29/2000 DONE
called John Price ###-####
Routing - PLAN CHECK8/10/2000 8/28/2000 DONE
Plan Reviewer's activity  8/28/2000 PASS
Print Pending Permit.LaserJet4  8/28/2000 DONE
Print Pending Permit.LaserJet4  8/28/2000 DONE
PLANS/APPL TAKEN TO FRONT DESK  8/28/2000 DONE
Case Summary (BLD)  8/28/2000 DONE
Plan assigned to (M_P)5/25/2000 8/28/2000 PASS
DetailsMike Phillips
8/28/2000 10:29:58 M_P - activity updated through activity BLDA022 from case BLD00-01483.
Plan Reviewer's activity  8/23/2000 FAIL
Need additional information for follow up review.
Plan Reviewer's activity  8/23/2000 FAIL
Need additional information for follow up review.
Routing - FIRE8/8/20008/8/20008/9/2000 PASS
DetailsBill Alexander
Routing - PUBLIC WORKS8/8/20008/8/20008/8/2000 PASS
Routing - PLAN CHECK7/25/2000 8/8/2000 PEND
Routing - PLAN CHECK7/24/2000 7/24/2000  
routing to plumbing
Routing - PLUMBING7/24/2000 7/24/2000 PASS
Routing - FIRE7/19/20007/21/20007/21/2000 FAIL
DetailsBill Alexander
UBC issues related to UFC requirements.
Plan Review Completed(1st rev)  7/21/2000 FAIL
Routing - PLAN CHECK6/22/2000 7/19/2000  
ROUTING TO FIRE
Plan Reviewer's activity  7/19/2000 FAIL
ADDITIONAL INFORMATION REQUIRED FOR FURTHER REVIEW.
Plan resubmittals received  7/13/2000 DONE
RECEIVED THREE COPIES OF REVISED SHEETS C6.0, P1.0, P1.1, P2.0, P2.1 ROUTED TO MIKE P
Routing - PLUMBING6/20/2000 6/21/2000 FAIL
Routing - PLANNING6/12/2000 6/20/2000 PASS
Approved per DRH99-150 & CUP98-146
Routing - PUBLIC WORKS6/5/2000 6/12/2000 FAIL
REQUIRES HILLSIDE GRADING APPROVAL KMM
Received partial PAYMENT  6/5/2000 DONE
Application received  5/25/2000  
Print Pending Permit.LaserJet4