DOC - Permit Finaled | 12/18/2002 | 12/18/2002 | 12/18/2002 | A | PASS |
Tony Young
|
|
|
Finaled by inspector at 12/18/2002 7:58:30 AM
|
BLD-Aging Inspection | 12/11/2002 | 12/11/2002 | 12/11/2002 | | PASS |
Tony Young
|
|
|
|
FIRE-Final Inspection | 3/11/2002 | 3/12/2002 | 3/12/2002 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/11/2002 at 12:53:16. Contact: ###-####.
|
BLD-Final | 3/11/2002 | 3/12/2002 | 3/12/2002 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/11/2002 at 12:53:58. Contact: ###-####.
ok for temp. occ. pending trades,, ok for perm. occ. after final grading/ fire/ pw, etc. are ok 3/12/2002 12:03:26 PM
|
FIRE-Final Inspection | 3/4/2002 | 3/5/2002 | 3/5/2002 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/04/2002 at 14:30:19. Contact: ###-####. door hardware 3/5/2002 10:50:22 AM
|
BLD-Final | 3/4/2002 | 3/5/2002 | 3/5/2002 | P | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/04/2002 at 14:31:04. Contact: ###-####.needs fire/lifesafety before callibg for a final. 3/5/2002 4:31:50 PM
|
PubWorks Occupancy Approval | | | 2/4/2002 | | DONE |
|
|
|
Did not sign Perm Occ, found complete 02/04/02. M.Strasser
|
BLD-Aging Inspection | 1/16/2002 | 1/16/2002 | 1/16/2002 | | PART |
Tony Young
|
|
|
wip 1/16/2002 9:53:38 AM
|
BLD-Energy code compliance | 11/16/2001 | 11/16/2001 | 11/16/2001 | P | PASS |
Tony Young
|
|
|
###-#### CHRIS
|
BLD-Energy code compliance | 10/30/2001 | 10/31/2001 | 10/31/2001 | A | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 10/30/2001 at 16:10:27. Contact: ###-####.
trade sign offs not complete 10/31/2001 10:07:17 AM
|
BLD-Framing/Rough-in | 10/26/2001 | 10/29/2001 | 10/29/2001 | A | FAIL |
Tony Young
|
|
|
###-#### CHRIS
need mech sign off, then ok to insulate 10/29/2001 12:33:56 PM
|
BLD-Aging Inspection | 10/11/2001 | 10/11/2001 | 10/11/2001 | | PART |
Tony Young
|
|
|
wip 10/11/2001 10:04:19 AM
|
BLD-Foundation | 8/9/2001 | 8/10/2001 | 8/10/2001 | A | PART |
Tony Young
|
|
|
###-#### chris
wip, ok so far 8/10/2001 11:08:01 AM
|
BLD-Footing | 8/7/2001 | 8/8/2001 | 8/8/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 08/07/2001 at 15:42:26. Contact: ###-####.
|
(F) Reprint permit | | | 5/24/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/23/2001 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/13/2000 | | DONE |
|
|
|
|
Telephone call | | | 8/29/2000 | | DONE |
|
|
|
John Price ###-####
|
Inspection Record Card- Bld | | | 8/29/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/29/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/10/2000 | | 8/28/2000 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 8/28/2000 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/28/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/28/2000 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/28/2000 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 5/25/2000 | | 8/28/2000 | | PASS |
Mike Phillips
|
|
|
8/28/2000 14:12:12 M_P - activity updated through activity BLDA022 from case BLD00-01498.
|
Plan Reviewer's activity | | | 8/23/2000 | | FAIL |
|
|
|
Need additional information for follow up review.
|
Routing - FIRE | 8/8/2000 | 8/8/2000 | 8/9/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing - PUBLIC WORKS | 8/8/2000 | 8/8/2000 | 8/8/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/25/2000 | | 8/8/2000 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 7/24/2000 | | 7/24/2000 | | |
|
|
|
routing to plumbing
|
Routing - FIRE | 7/19/2000 | 7/21/2000 | 7/21/2000 | | FAIL |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 7/21/2000 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 6/22/2000 | | 7/19/2000 | | |
|
|
|
ROUTING TO FIRE
|
Plan Reviewer's activity | | | 7/19/2000 | | FAIL |
|
|
|
ADDITIONAL INFORMAITON REQUIRED FOR FURTHER REVIEW.
|
Plan resubmittals received | | | 7/13/2000 | | DONE |
|
|
|
RECEIVED THREE COPIES OF REVISED SHEETS C6.0, P1.0, P1.1, P2.0, P2.1 ROUTED TO MIKE P. KMM
|
Routing - PLUMBING | 6/20/2000 | | 6/21/2000 | | FAIL |
|
|
|
|
Routing - PLANNING | 6/12/2000 | | 6/20/2000 | | PASS |
|
|
|
Approve per CUP98-146 & DRH99-150.
|
Routing Off Site - STRUCTURAL | | | 6/19/2000 | | PASS |
|
|
|
Structural reviews completed by outside engineer and returned approved. Review given to Mike Phillips.
|
Routing Off Site - STRUCTURAL | 6/6/2000 | | 6/16/2000 | | FAIL |
|
|
|
faxing comments to architect.
|
Routing - PUBLIC WORKS | 6/5/2000 | | 6/12/2000 | | FAIL |
|
|
|
REQUIRES HILLSIDE GRADING APPROVAL. KMM
|
Plan resubmittals received | | | 6/8/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM JOHN PRICE, ARCHITECT, THREE SETS OF SHEETS A3.0 A3.1, A3.5AND A6.0. FORWORDED SAME TO MIKE PHILLIPS. 6/8/00 DAR
|
Received partial PAYMENT | | | 6/5/2000 | | DONE |
|
|
|
|
Application received | | | 5/25/2000 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | | | |
|
|
|
|
Plan Reviewer's activity | | | | | |
|
|
|
|