Fee Review-notes | 6/25/2003 | 6/25/2003 | 6/25/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 8/25/2000 | 8/25/2000 | | DONE |
|
|
|
|
Permanent occupancy | | | 8/25/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8346 issued 8-25-00 to Budokan-IMIC.Com
|
BLD-Final | 8/23/2000 | 8/24/2000 | 8/24/2000 | A | PASS |
|
|
|
steve-- ###-#### fn occ signed the perm col 8/25/2000 9:59:02 AM
|
BLD-Final | 8/23/2000 | 8/24/2000 | 8/24/2000 | A | PASS |
|
|
|
steve-- ###-#### fn occ signed the perm col 8/25/2000 9:59:02 AM
|
BLD-Final | 8/16/2000 | 8/21/2000 | 8/21/2000 | A | FAIL |
|
|
|
STEVE-- ###-#### FN OCC need the mech signoff on the occ req card 8/21/00 11:10:07 AM
|
FIRE-Final Inspection | 8/15/2000 | 8/15/2000 | 8/15/2000 | P | PASS |
Rick Jackson
|
|
|
steve-- pager # ###-#### fire fn
|
BLD-Framing/Rough-in | 7/14/2000 | 7/18/2000 | 7/18/2000 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/14/2000 at 11:06:14. Contact: ###-####. need wall brasing above celling. 7/18/2000 2:14:12 PM
|
Issue PAID IN FULL permit | | | 6/28/2000 | | DONE |
|
|
|
|
Inspector's copy Bld permit | | | 6/19/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/19/2000 | | DONE |
|
|
|
|
Telephone call | | | 6/19/2000 | | DONE |
|
|
|
left mess for cathy rosera that permit is ready
|
Routing - PLAN CHECK | 6/16/2000 | | 6/16/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/16/2000 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 6/2/2000 | | 6/16/2000 | | PASS |
Carl Westfall
|
|
|
6/16/00 08:09:31 CJW - activity updated through activity BLDA022 from case BLD00-01523.
|
Routing - FIRE | 6/12/2000 | 6/15/2000 | 6/15/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 6/15/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 6/2/2000 | | 6/12/2000 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 6/9/2000 | | PASS |
|
|
|
UBC plan review started June 9, 2000 and finished June 12, 2000. The drawings were approved with conditions. See the conditions list.
|
Plan routing begun/TENANTS | | | 6/2/2000 | | DONE |
|
|
|
Route to PLAN CHECK and FIRE.
|
Additional plans submitted | | | 6/2/2000 | | DONE |
|
|
|
RECEIVED 2 SETS OF SHEET A1.0 FORWARDED THEM TO MARLENE. 6/2/00 DAR
|
Pending Assignment by MYS | 6/2/2000 | | 6/2/2000 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/31/2000 | | DONE |
|
|
|
SENT LIST OF DISCRIPENCIES TO BOTH BUILDING MANAGER AND ARCHITECT. 5/31/00 DAR
|
Application received | | | 5/26/2000 | | |
|
|
|
|