Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD00-01530
StatusFinaled
Name SCP GLOBAL TECHNOLOGIES (BLDG 456)
Site Address 8455 W WESTPARK ST
Project NameSCP GLOBAL TECH-#456
Customer Number 
ePlanReviewNo
Description
SCP GLOBAL TECHNOLOGIES (BLDG 456) PHASE I - Interior demolition of walls & finishes done under BLD00-01363. To remodel interior by increasing the clean room area & relocate the access stairs to the lower level clean room mechanical / air return; relocate return air chases in clean room; expand the assembly fabrication area into the previous lunch / breakroom / office / restroom areas; relocate D/I Plan Filter Wall and double doors / infill wall opening; add BCF Room; relocate or upgrade process piping & testing equipment, electrical, plumbing, mechanical, sprinkler and alarm systems for needs & code compliance; suspended ceiling system and upgrades to remaining men,s & women,s restrooms for full accessibility compliance. NOTE: This building is fully fire sprinklered for area increase. THE NEW ADDITION(S) TO THE NORTH AND CONNECTION BETWEEN BUILDINGS 455 & 456 WITH ANY INTERIOR WORK SHOWN ON ANY PLANS ARE NOT PART OF THIS PROJECT SCOPE. SEPARATE APPLICATION AND PLANS ARE CURRENTLY BEING REVIEWED. (P.C.#00-389)/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  11/17/2000 DONE
Letter of Compliance #20020 issued 11-17-00.
FIRE-Final Inspection11/15/200011/16/200011/16/2000APASS
DetailsJoe Tawney
###-#### Final OK for permanant occupancy or cert of completion 11/17/2000 7:58:43 AM
BLD-Final11/7/200011/8/200011/8/2000PPASS
DetailsDave Hannah
FN OCC JEFF ###-####
BLD-Final11/6/200011/7/200011/7/2000ANR
DetailsTom Arcoraci
###-#### jeff 11/7/2000 9:50:29 AM need sigs on card will recall 11/7/2000 9:56:51 AM
FIRE-Final Inspection8/22/20008/23/20008/23/2000ANR
DetailsCarl Dependahl
Jeff ###-####, for fire 8/22/2000 3:22:38 PM
FIRE-Final Inspection8/22/20008/23/20008/23/2000APART
DetailsJoe Tawney
###-#### OK on rough in of relocation of spklr heads away from cable trays 8/23/2000 12:48:30 PM
BLD-Framing/Rough-in8/2/20008/3/20008/3/2000APART
DetailsCarl Dependahl
fire structure draft stop Gregg ###-####draft stop ok; rec'd specs and details req'd 8/3/2000 12:11:01 PM
FIRE-Final Inspection8/1/20008/2/20008/2/2000APART
DetailsJoe Tawney
jeff ###-#### Ok on sprinkler in southwall area ok to cover 8/2/00 3:06:54 PM
BLD-Framing/Rough-in8/1/20008/2/20008/2/2000APART
DetailsCarl Dependahl
GREG ###-#### CEILING GRID INSP; south portion ok 8/2/2000 10:17:12 AM
BLD-Framing/Rough-in7/27/20007/28/20007/28/2000APART
Details
ceiling grid ###-#### jeff ok to drop n tiles in the two center bays all diffusers are connected properly waiting for mech signoff 7/28/2000 2:11:25 PM
FIRE-Final Inspection7/26/20007/27/20007/27/2000PPART
DetailsJoe Tawney
Jeff ###-#### Spklr. R/I 2 middle areas 2 column obstructions & install 2 heads. 7/28/00 10:04:33 AM
BLD-Framing/Rough-in7/26/20007/27/20007/27/2000APART
Details
ceiling grid Greg ###-#### ok on the center bay for tile drop in with 406 blessing 7/27/2000 12:41:23 PM
BLD-Final7/25/20007/26/20007/26/2000AFAIL
DetailsCarl Dependahl
###-####; ok to use NW corner of bldg; phased project. 7/26/2000 11:00:45 AM
FIRE-Final Inspection7/24/20007/25/20007/25/2000APART
DetailsJoe Tawney
Jeff ###-#### Ok to occupy NW corner of building. 7/26/00 10:46:59 AM
BLD-Final7/25/20007/25/20007/25/2000PFAIL
DetailsCarl Dependahl
art-- ###-#### ck wall; ok to cover 7/25/2000 4:23:57 PM
FIRE-Final Inspection7/21/20007/24/20007/24/2000AFAIL
DetailsJoe Tawney
###-#### Reinsp. fail approved spklr. submittals not on site. 7/25/00 9:37:48 AM
FIRE-Final Inspection7/24/20007/24/20007/24/2000PFAIL
DetailsJoe Tawney
Jeff ###-#### after 3 Reinsp. not ready spklr. submittals not on site. 7/24/00 1:22:48 PM
FIRE-Final Inspection7/20/20007/21/20007/21/2000AFAIL
DetailsJoe Tawney
partial Jeff ###-#### sprinkler R/I fail C/N issued. 7/21/00 1:03:15 PM
BLD-Framing/Rough-in7/18/20007/19/20007/19/2000APART
DetailsCarl Dependahl
CEILING GRID--GREG HUNTER ###-#### kee C/N; plenum "smoke/flame", etc. Clg. ok if ok with htg. & elec. 7/20/00 2:00:25 PM
BLD-Framing/Rough-in7/7/20007/10/20007/10/2000APART
DetailsCarl Dependahl
Greg ###-#### Verify elec. ok @ ceiling- add. "Pods" C/N walls ok. 7/10/00 2:49:58 PM
Inspection Record Card- Bld  6/22/2000 DONE
Print Occupancy Form  6/22/2000 DONE
Override - Parcel Holds  6/22/2000  
Issue PAID IN FULL permit  6/22/2000 DONE
Override - Parcel Holds  6/22/2000  
Routing - FIRE6/15/20006/21/20006/21/2000 PASS
DetailsBill Alexander
Plan assigned to (DRS)5/31/2000 6/21/2000 PASS
DetailsDan Stuart
Plan Review Completed(1st rev)  6/21/2000 PASS
DetailsBill Alexander
Routing - PLAN CHECK6/21/2000 6/21/2000 PASS
APPROVED AS NOTED AND ATTACHED PLAN REVIEW COMMENTS
PLANS/APPL TAKEN TO FRONT DESK  6/21/2000 PASS
ROUTING TO PERMIT DESK FOR ISSUANCE.
Routing - PLAN CHECK6/1/2000 6/15/2000 PEND
Preliminary plan review complete. Determination of additional information dependant on if BLD98-00507 was finaled per plan review comments at that time. The computer does not indicate inspections or finals past one frame for one wall. Perry Paine will follow up with Russell Corp to verify. Routing plans to Fire Code Analysts for review. Will visit site today with Fire Code personel at 1:30 p.m. as scheduled with Mike Capshaw.
Override - Parcel Holds  6/14/2000  
Telephone call  6/13/2000 DONE
Set up appointment with Moke Capshaw to visit site and review process of manufacturing & testing done. Past permit BLD98- not finaled for completetion of manufacturing & assembly additions.
Routing - PLUMBING6/1/2000 6/2/2000 DONE
Routing - PUBLIC WORKS5/31/2000 6/1/2000 DONE
Plan routing begun/TENANTS  5/31/2000 DONE
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE.
Pending Assignment by MYS5/31/2000 5/31/2000 DONE
DetailsMarlene Southard
Application received  5/30/2000  
Plans ACCEPTED BY PLAN TECH  5/30/2000 DONE
Received Certificate of Value  5/25/2000 DONE
Waiting for Cert. of Value  5/24/2000 DONE
Plans ACCEPTED BY PLAN TECH  5/24/2000 FAIL
RECEIVED ONE APPLICATION FOR TWO BUILDINGS. HAD MIKE SEPARATE INTO TWO PERMITS. KMM