BLD-Final | 6/27/2002 | 6/28/2002 | 6/28/2002 | A | CANC |
Russ Owen
|
|
|
###-#### . This number listed has nothing to do with this project also it would appear that fire/life safety needs to sign off prior to structural. 6/28/2002 11:18:17 AM
|
BLD-Final | 6/24/2002 | 6/25/2002 | 6/25/2002 | A | CANC |
Tom Arcoraci
|
|
|
###-#### joe this permit has already expired see sec 106 ubc 6/25/2002 8:02:15 AM
|
BLD-Final | 9/11/2000 | 9/11/2000 | 9/11/2000 | P | FAIL |
|
|
|
###-#### 9-8-2k c/n not completed 9/11/2000 5:32:34 PM
|
FIRE-Final Inspection | 9/5/2000 | 9/5/2000 | 9/5/2000 | P | FAIL |
Joe Tawney
|
|
|
###-#### Fail C/N issued 9/6/2000 12:15:47 PM
|
BLD-Final | 8/24/2000 | 8/25/2000 | 8/25/2000 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/24/2000 at 13:25:30. Contact: ###-####...NEED FIRE, OTHER SIG'S. NO OTHER INSP PE 8/25/2000 10:36:03 AM FORMED 8/25/2000 10:36:10 AM
|
BLD-Framing/Rough-in | 7/20/2000 | 7/21/2000 | 7/21/2000 | A | PASS |
Tom Arcoraci
|
|
|
Monty ###-#### Ok after elec. R/I 7/24/00 1:01:55 PM
|
BLD-Conference | 7/21/2000 | 7/21/2000 | 7/21/2000 | A | CANC |
|
|
|
Scheduled by Inspector: 338 On 7/21/2000
|
BLD-Conference | 7/21/2000 | 7/21/2000 | 7/21/2000 | A | CANC |
|
|
|
Added by Inspector: 338 On 7/21/2000
|
BLD-Framing/Rough-in | 7/20/2000 | 7/20/2000 | 7/20/2000 | P | NR |
Carl Dependahl
|
|
|
###-####; left msg 7/21/2000 8:35:17 AM
|
Issue PAID IN FULL permit | | | 7/6/2000 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 6/8/2000 | | 7/5/2000 | | PASS |
Jason Blais
|
|
|
7/5/2000 13:01:50 JCB - activity updated through activity BLDA022 from case BLD00-01571.
|
Routing - PLAN CHECK | 6/22/2000 | | 7/5/2000 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/5/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/5/2000 | | DONE |
|
|
|
|
Telephone call | | | 7/5/2000 | | DONE |
|
|
|
called Dave Bliss ###-####
|
Plan resubmittals received | | | 6/30/2000 | | |
|
|
|
Plan resubmittal sheets A1 received.
|
Routing - FIRE | 6/19/2000 | | 6/21/2000 | | PASS |
|
|
|
Alarm info requested.
|
Plan Review Completed(1st rev) | | | 6/21/2000 | | FAIL |
|
|
|
failed Bldg.
|
Plan resubmittals requested | | | 6/19/2000 | | PEND |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLAN CHECK | 6/8/2000 | | 6/19/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Response and resubmittals needed for further review. Plans routed to fire dept.
|
Pending Assignment by MYS | 6/8/2000 | | 6/8/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 6/8/2000 | | DONE |
|
|
|
Route to PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 6/5/2000 | | PEND |
|
|
|
I HAVE ASKED DAVE BLISS TO SUPPLY OCCUPANT LOADS AND CORRECT OCCUPANCY GROUP. PLANS STATE M RETAIL APPLICATION STATES B. FAXED DAVE FOR ABOVE INFORMATION. KMM
|
Received Certificate of Value | | | 6/2/2000 | | DONE |
|
|
|
|
Application received | | | 6/2/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/2/2000 | | DONE |
|
|
|
|
Fee Review-notes | 6/2/2000 | 6/2/2000 | | | |
|
|
|
|