BLD-Final | 8/1/2000 | 8/1/2000 | 8/1/2000 | A | PASS |
|
|
|
plans revised to match the projectc/c# 19743
|
BLD-Final | 7/11/2000 | 7/11/2000 | 7/11/2000 | P | FAIL |
Jim Storey
|
|
|
rob ###-#### c/n not done exit will not open. 7/11/00 1:40:42 PM
|
FIRE-Final Inspection | 6/29/2000 | 6/29/2000 | 6/30/2000 | A | PASS |
Rick Jackson
|
|
|
requested letter indicating time frame the hood system will comply with UMC - not welded seams at present
|
BLD-Final | 6/29/2000 | 6/29/2000 | 6/29/2000 | P | FAIL |
|
|
|
###-#### str is ok need other agencies sign of 7/3/00 8:38:20 AM
|
FIRE-Final Inspection | 6/23/2000 | 6/23/2000 | 6/23/2000 | P | PART |
Rick Jackson
|
|
|
###-#### john Spklr. inspection in dinning area only add head in entry to kitchen 6/26/00 11:39:52 AM
|
BLD-Framing/Rough-in | 6/22/2000 | 6/22/2000 | 6/22/2000 | A | FAIL |
|
|
|
Scheduled by Inspector: 338 On 6/22/00 ceiling grid seizmic fail; c/n issued 6/23/00 3:08:41 PM
|
BLD-Framing/Rough-in | 6/21/2000 | 6/21/2000 | 6/21/2000 | P | CANC |
Jim Storey
|
|
|
ROBERT ###-#### trans to p paine. 6/22/00 11:20:19 AM
|
BLD-Framing/Rough-in | 6/21/2000 | 6/21/2000 | 6/21/2000 | P | CANC |
Jim Storey
|
|
|
ROBERT ###-#### trans to p paine. 6/22/00 11:20:19 AM
|
Issue PAID IN FULL permit | | | 6/15/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/6/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/6/2000 | | DONE |
|
|
|
|
Telephone call | | | 6/6/2000 | | DONE |
|
|
|
talked to robert to verify plans are ready
|
Plan assigned to (DRS) | 6/5/2000 | 6/5/2000 | 6/5/2000 | | PASS |
Dan Stuart
|
|
|
6/5/2000 16:57:25 DRS - activity updated through activity BLDA022 from case BLD00-01609.
|
Routing - PLAN CHECK | 6/5/2000 | 6/5/2000 | 6/5/2000 | | PASS |
|
|
|
Suspended ceiling system and adjustment to electrical, mechanical & sprinkler system has evidently been completed by contractor and the city is now seeking a permit. Inspection and approval required. Visited with Sam Rogers, Fire Code analyst to see if he needed to review plan. Said the addition of new heads could be verified in field.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2000 | | PASS |
|
|
|
Routed to fron desk for issuance of permit.
|
Application received | | | 6/5/2000 | | |
|
|
|
|