Case Summary (BLD) | | | 11/20/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/23/2002 | | DONE |
|
|
|
|
Fee Review-notes | 6/12/2000 | 6/12/2000 | 4/25/2001 | | DONE |
|
|
|
additional value from subs
|
Permanent Occupancy | | 10/5/2000 | 10/5/2000 | | DONE |
|
|
|
|
BLD-Final | 10/4/2000 | 10/5/2000 | 10/5/2000 | A | PASS |
Carl Dependahl
|
|
|
larry ###-####
|
Permanent occupancy UNPAID FEE | | | 10/5/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8429 issued 10-5-00 to thw Winn Restaurant.
|
FIRE-Final Inspection | 10/3/2000 | 10/4/2000 | 10/4/2000 | P | PASS |
Joe Tawney
|
|
|
###-#### Larry Reinsp OK for permanant occupancy 10/5/2000 8:00:53 AM
|
FIRE-Final Inspection | 10/2/2000 | 10/2/2000 | 10/2/2000 | P | FAIL |
Joe Tawney
|
|
|
###-#### Final Fail C/N issued 10/3/2000 7:37:39 AM
|
FIRE-Final Inspection | 9/27/2000 | 9/28/2000 | 9/28/2000 | A | CANC |
Joe Tawney
|
|
|
LARRY ###-#### FIRE FN Not ready 9/28/2000 1:02:11 PM
|
BLD-Framing/Rough-in | 9/1/2000 | 9/1/2000 | 9/1/2000 | P | PART |
|
|
|
ceiling grid-- carl-- ###-#### ceiling grid-- Grid appears OK carl-- ###-#### 9/1/2000 12:03:17 PM
|
BLD-Framing/Rough-in | 8/16/2000 | 8/16/2000 | 8/16/2000 | P | PART |
Carl Dependahl
|
|
|
CARL ###-#### RE-INSP R/I, shaft ok 8/16/2000 12:12:50 PM
|
BLD-Framing/Rough-in | 8/14/2000 | 8/14/2000 | 8/14/2000 | P | PART |
Carl Dependahl
|
|
|
CARL ###-#### FR; ext sha 8/14/2000 11:48:43 AM ft wallsok add gyp at int ok to continue 8/14/2000 11:49:14 AM
|
BLD-Framing/Rough-in | 8/10/2000 | 8/11/2000 | 8/11/2000 | A | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 08/10/2000 at 14:14:12. Contact: ###-####. need assm for shafts cn posted 8/11/2000 10:37:18 AM
|
BLD-Framing/Rough-in | 8/8/2000 | 8/8/2000 | 8/8/2000 | P | NR |
Tom Arcoraci
|
|
|
CARL= ###-#### -FIRE SHAFT INSP
|
BLD-Framing/Rough-in | 8/2/2000 | 8/3/2000 | 8/3/2000 | P | PART |
Carl Dependahl
|
|
|
KARL ###-#### FR INSP; ok pend elec at booths and partitions; recall for shaft wall, etc. 8/3/2000 11:36:28 AM
|
Routing - PLAN CHECK | 7/20/2000 | | 7/20/2000 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/20/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/20/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/20/2000 | | DONE |
|
|
|
|
Telephone call | | | 7/20/2000 | | DONE |
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 7/20/2000 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 6/16/2000 | | 7/20/2000 | | PASS |
Jason Blais
|
|
|
7/20/2000 08:18:45 JCB - activity updated through activity BLDA022 from case BLD00-01681.
|
Routing - FIRE | 7/19/2000 | 7/19/2000 | 7/19/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 7/18/2000 | | 7/19/2000 | | PEND |
|
|
|
Plan and permit approval dependent on Fire Dept. approval. Plans routed to Fire Dept.
|
Routing - FIRE | 7/14/2000 | 7/18/2000 | 7/18/2000 | | FAIL |
Bill Alexander
|
|
|
Need hydrant flow information and location/s.
|
Plan resubmittals received | | | 7/17/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM COLE ASSOCIATES , TWO SETS OF SHEETS A3.O. FORWARDED SAME TO JASON BLAIS. 7/17/00 DAR
|
Plan Reviewer's activity | | | 7/14/2000 | | FAIL |
|
|
|
Resubmittals did not address one requirement of providing a detail section for the Type I hood and duct with all relevant details. Submittal of this item required prior to a permit being issued. Also, Type of Construction has been changed from a Type III-N building to a Type V-N building so the Fire Dept. needs to look at it again for fireflow adequacy. Plans routed to Fire Dept.
|
Routing - PLAN CHECK | 7/6/2000 | | 7/14/2000 | | FAIL |
|
|
|
All items not addressed from plan review report. See notes under Plan Reviewer's Activity (7/14/2000)
|
Plan resubmittals received | | | 7/12/2000 | | DONE |
|
|
|
RESUBMITTAL LETTER AND SHEETS A1.0, A2.0, A3.0, A4.0 AND A5.0 RECEIVED AND FORWARDED TO JASON B.
|
Plan Review Completed(1st rev) | | | 7/6/2000 | | FAIL |
|
|
|
failed BLDG review
|
Routing - FIRE | 7/3/2000 | | 7/6/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 6/21/2000 | | 7/3/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to fire dept.
|
Plan resubmittals requested | | | 7/3/2000 | | PEND |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLUMBING | 6/16/2000 | | 6/21/2000 | | PASS |
|
|
|
provide a vent downstream of grease interceptor, if an automatic soap dispensor is used at the mop sink provide a water supply for it, pan drain and t& p drain line may be required at the water heater, no floor sinks to be inclosed under cabinets
|
Plan resubmittals received | | | 6/16/2000 | | DONE |
|
|
|
TWO COPIES OF REVISED PLANS. ROUTED TOPW TO ROUTE WITH ORIGINAL PLANS. KMM
|
Plan routing begun/TENANTS | | | 6/16/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE. Formerly signed off by Deb Moran from Central District Health.
|
Routing - PUBLIC WORKS | 6/16/2000 | | 6/16/2000 | | PASS |
|
|
|
|
Pending Assignment by MYS | 6/16/2000 | | 6/16/2000 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/14/2000 | | PASS |
|
|
|
|
Received Certificate of Value | | | 6/12/2000 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/12/2000 | | DONE |
|
|
|
|
Application received | | | 6/12/2000 | | |
|
|
|
|