Fee Review-notes | 6/12/2000 | 6/12/2000 | 4/18/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 8/24/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8342 issued 8-24-00 to American Express in the River Quarry Bldg. C.
|
Permanent Occupancy | | 8/23/2000 | 8/23/2000 | | DONE |
|
|
|
|
BLD-Final | 8/23/2000 | 8/23/2000 | 8/23/2000 | P | PASS |
|
|
|
Scheduled by a contractor via Hello! on 08/23/2000 at 09:03:18. Contact: ###-####. signedthe perm col 8/24/2000 10:30:23 AM
|
FIRE-Final Inspection | 8/22/2000 | 8/22/2000 | 8/22/2000 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/22/2000 at 08:26:21. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/15/2000 | 8/16/2000 | 8/16/2000 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/15/2000 at 12:31:13. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/25/2000 | 7/25/2000 | 7/25/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/25/2000 at 11:17:32. Contact: ###-####. walls only ok / corridor recp cut in back to back/ 7/25/2000 2:43:45 PM
|
Issue PAID IN FULL permit | | | 7/11/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/7/2000 | | 7/7/2000 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/7/2000 | | PASS |
|
|
|
|
Print Occupancy Form | | | 7/7/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/7/2000 | | DONE |
|
|
|
|
Telephone call | | | 7/7/2000 | | DONE |
|
|
|
stan gave dollar amount
|
Plan assigned to (JCB) | 6/16/2000 | | 7/7/2000 | | PASS |
Jason Blais
|
|
|
7/7/2000 08:52:07 JCB - activity updated through activity BLDA022 from case BLD00-01689.
|
Plan Review Completed(1st rev) | | | 7/6/2000 | | FAIL |
|
|
|
failed bldg review
|
Routing - FIRE | 7/5/2000 | | 7/6/2000 | | PASS |
|
|
|
Approved with conditions
|
Plan resubmittals requested | | | 7/5/2000 | | PEND |
|
|
|
Written response to plan review report required.
|
Routing - PLAN CHECK | 6/16/2000 | | 7/5/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Written response needed to plan review report. Plans routed to fire dept.
|
Pending Assignment by MYS | 6/16/2000 | | 6/16/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 6/16/2000 | | DONE |
|
|
|
Route to PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 6/15/2000 | | PASS |
|
|
|
NEEDS TO REPLY TO FIRE ALARM AND SMOKE CONTROL SYSTEMS. FAXED TO ARCH. KMM
|
Received Certificate of Value | | | 6/12/2000 | | DONE |
|
|
|
|
Application received | | | 6/12/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|