Fee Review-notes | 6/16/2000 | 6/16/2000 | 3/22/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 2/22/2002 | | DONE |
|
|
|
-Perm. Occ. Cert. #9036 issued 2-22-02 to St. Alphonsus Hospital for the meditation room and vestibule.
|
BLD-Final | 2/4/2002 | 2/4/2002 | 2/4/2002 | P | PASS |
Tom Arcoraci
|
|
|
cecil ###-#### ok for perm occ 2/4/2002 3:08:30 PM
|
Permanent Occupancy | | 2/4/2002 | 2/4/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 1/31/2002 | 2/1/2002 | 2/1/2002 | P | PASS |
Troy Cobbley
|
|
|
Fire life/safety OK. Fire alarm system tested OK. Fire sprinkler system OK. Ok for perm occ. 2/1/2002 3:36:15 PM
|
PubWorks Occupancy Approval | | | 2/1/2002 | | DONE |
|
|
|
Drainage project complete 02/01/02. R.Cummings
|
FIRE-Final Inspection | 1/22/2002 | 1/24/2002 | 1/24/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide fire extinguisher in penthouse and basement electrical room, elevator recall does not work, a bush is obstructing the FDC, paint curbing per sheet A1.0, place no parking signs per note 13, provide secondary containment verification for emergency generator, provide offsite sprinkler monitoring, provide floor signage and use stairs signs per note 28 and 29, install door at the ground level south shell exit, provide door on 2nd floor electrical room, verify life/safety and fire alarm and fire sprinklers at end of link and in Meditation room, provide "door to remain unlocked" sticker on both main exit doors 1/25/2002 3:06:12 PM
|
CHANGE STATUS TO (ISS) | | | 12/27/2001 | | DONE |
|
|
|
per george
|
Issue PAID IN FULL permit | | | 8/2/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/1/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/1/2000 | | DONE |
|
|
|
|
Telephone call | | | 8/1/2000 | | DONE |
|
|
|
TALKED TO STEVE GAVE DOLLAR AMOUNT
|
Routing - PLAN CHECK | 7/26/2000 | | 7/31/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2000 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 6/20/2000 | | 7/31/2000 | | PASS |
John Menard
|
|
|
7/31/00 14:53:42 JCM - activity updated through activity BLDA022 from case BLD00-01745.
|
Routing Off Site - STRUCTURAL | 6/20/2000 | | 7/31/2000 | | PASS |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
|
Routing - PUBLIC WORKS | 7/21/2000 | | 7/26/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/14/2000 | | 7/21/2000 | | |
|
|
|
|
Routing - FIRE | 7/11/2000 | 7/14/2000 | 7/14/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 7/14/2000 | | FAIL |
|
|
|
PLUMBING
|
Routing - PLAN CHECK | 7/3/2000 | | 7/11/2000 | | |
|
|
|
|
Plan resubmittals requested | | | 7/10/2000 | | PEND |
|
|
|
|
Routing - PLUMBING | 6/30/2000 | | 7/3/2000 | | PASS |
|
|
|
|
Routing - PLANNING | 6/23/2000 | | 6/30/2000 | | PASS |
|
|
|
OK per CUP00-00045 & CUP98-00121 (SAR).
Approved per DRH98-196 and DRH00-115 (MGS).
|
Routing - PUBLIC WORKS | 6/20/2000 | | 6/23/2000 | | FAIL |
|
|
|
REQUIRES THREE COPIES OF CIVIL PLANS. KMM
|
Plan routing begun/NEW & ADDTN | | | 6/20/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/20/2000 | | PASS |
|
|
|
|
Received Certificate of Value | | | 6/16/2000 | | DONE |
|
|
|
|
Application received | | | 6/16/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/16/2000 | | DONE |
|
|
|
|