Case Summary (BLD) | | | 11/25/2008 | | |
|
|
|
|
Plan resubmittals received | | | 7/10/2002 | | DONE |
|
|
|
REVISED REPORT 3 COPIES AND SUPPORTING CALC. FROM JIM REESE OF MTC
|
Fee Review-notes | 6/21/2000 | 6/21/2000 | 5/9/2001 | | DONE |
|
|
|
|
Permanent Occupancy | | 9/20/2000 | 9/20/2000 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 9/20/2000 | | |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 9/20/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8388 issued 9-20-00 to the Riverstone Community School for a modular classroom bldg.
|
BLD-Final | 9/18/2000 | 9/18/2000 | 9/18/2000 | P | PART |
Russ Owen
|
|
|
###-####needs achd,public work. 9/19/2000 8:49:14 AM
|
Override - Parcel Holds | | | 9/18/2000 | | |
|
|
|
|
Routing - FIRE | 9/13/2000 | 9/13/2000 | 9/13/2000 | | PASS |
Bill Alexander
|
|
|
Plan Madifications.
|
BLD-Final | 8/31/2000 | 9/1/2000 | 9/1/2000 | P | PART |
Jim Storey
|
|
|
Tim Barret- ###-#### need others sign off. 9/1/2000 5:37:44 PM
|
FIRE-Final Inspection | 8/31/2000 | 9/1/2000 | 9/1/2000 | P | PASS |
Rick Jackson
|
|
|
Tim Barret- ###-####
|
Issue PAID IN FULL permit | | | 8/17/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/16/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/16/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/16/2000 | | DONE |
|
|
|
|
Telephone call | | | 8/16/2000 | | DONE |
|
|
|
called Andy Erstad ###-####
|
Plan assigned to (MLO) | 6/27/2000 | | 8/16/2000 | | PASS |
Mike Otto
|
|
|
8/16/2000 08:49:30 MLO - activity updated through activity BLDA022 from case BLD00-01804.
|
Routing - PLAN CHECK | 8/14/2000 | | 8/15/2000 | | PASS |
|
|
|
|
Routing - PLUMBING | 8/8/2000 | | 8/14/2000 | | PASS |
|
|
|
per plans and 97 upc
|
Plan resubmittals received | | | 8/14/2000 | | PEND |
|
|
|
RECEIVED THREE COPIES OF REVISED SHEET F1. ROUTED TO MIKE O. KMM
|
Plan resubmittals received | | | 8/8/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVSIED SHEETS A0.11 A1.11 A1.13, A2.12, A3.12, E1.1 ROUTED TO PLUMBING. KMM
|
Routing - FIRE | 8/4/2000 | 8/4/2000 | 8/4/2000 | | PASS |
Bill Alexander
|
|
|
With conditions
|
Routing - FIRE | 8/4/2000 | 8/4/2000 | 8/4/2000 | | PASS |
Bill Alexander
|
|
|
With condition
|
Routing - PLANNING | 8/4/2000 | | 8/4/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/1/2000 | | 8/3/2000 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/28/2000 | | DONE |
|
|
|
RECEIVED THREE COPIES OF REVISED SHEETS A1.11, A1.13, A2.11, A2.12, A2.31, A3.12, E1.1, E1.2, E1.3, ONE COPY OF RESPONSE LETTER AND ONE COPY OF INFORMATION DELIVERED TO THE DEQ. ROUTED TO MIKE O. KMM
|
Routing - PLANNING | 7/20/2000 | | 7/28/2000 | | FAIL |
|
|
|
DRH00-139, condition 1c not met; see letter in DRH00-139 file
|
Routing - PLAN CHECK | 7/25/2000 | | 7/27/2000 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT.
|
Plan resubmittals requested | | | 7/27/2000 | | FAIL |
|
|
|
UBC CORRECTIONS
|
Plan resubmittals received | | | 7/25/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM EARSTAD THORTON ARCHITECTS, FIVE SETS EACH OF A SHEETS AND E SHEETS, FORWARDED SAME TO MIKE OTTO. 7/25/00 DAR
|
Routing - FIRE | 7/17/2000 | 7/20/2000 | 7/20/2000 | | FAIL |
Bill Alexander
|
|
|
NO ADDITIONAL BUILDING/S ETC. ALLOWED UNDER THE CURRENT CONDITION OF FIRE FIGHTING SYSTEM (hydrant and water supply). Per Dave Miller-FPE, Boise Fire Department.
|
Plan Review Completed(1st rev) | | | 7/20/2000 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 7/17/2000 | | FAIL |
|
|
|
UBC CORRECTIONS
|
Routing - PLAN CHECK | 7/11/2000 | | 7/17/2000 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT
|
Additional plans submitted | | | 7/13/2000 | | DONE |
|
|
|
RECEIVED THREE COPIES OF STRUCTURAL ATTACHMENTS AND FOUNDATION DRAWINGS BY DEAN BRIGGS FOR THE MODULAR UNITS AT RIVERSTONE. ROUTED TO MIKE O. KMM
|
Routing - PLANNING | 7/5/2000 | | 7/11/2000 | | PEND |
|
|
|
PENDING DESIGN REVIEW APPROVAL.
|
Routing - PUBLIC WORKS | 6/27/2000 | | 6/28/2000 | | FAIL |
|
|
|
REQUIRES PROOF OF LEGAL LAND DIVISION.
|
Plan routing begun/TENANTS | | | 6/27/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/27/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 6/21/2000 | | DONE |
|
|
|
|
Application received | | | 6/21/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/21/2000 | | DONE |
|
|
|
|