Letter of compliance | | | 3/27/2001 | | DONE |
|
|
|
Letter of Compliance #21378 issued 3-27-01.
|
BLD-Final | 3/15/2001 | 3/16/2001 | 3/16/2001 | A | PASS |
Tom Arcoraci
|
|
|
###-#### fn ok for perm occ 3/16/2001 10:38:54 AM
|
Print Occupancy Form | | | 3/16/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/8/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/31/2000 | | DONE |
|
|
|
|
Telephone call | | | 7/31/2000 | | DONE |
|
|
|
###-####kent
|
Plan assigned to (DRS) | 6/29/2000 | | 7/29/2000 | | PASS |
Dan Stuart
|
|
|
7/29/2000 11:09:27 DRS - activity updated through activity BLDA022 from case BLD00-01825.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/29/2000 | | PASS |
|
|
|
Routed to permit desk for issuance of permit.
|
Routing - PLAN CHECK | 6/29/2000 | | 7/29/2000 | | PASS |
|
|
|
APPROVED PER PEER REVIEW AND REPORT FROM THIRD PARTY STRUCTURAL ENGINEERING FIRM CONTRACTED WITH BOISE CITY BUILDING DEPARTMENT TO PROVIDE STRUCTURAL PEER REVIEWS. COPY OF FINAL REPORT IN FILE & ATTACHED TO PLANS.
|
Routing Off Site - STRUCTURAL | 6/29/2000 | | 7/17/2000 | | PASS |
|
|
|
CONTACED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
7/17/2000 RECEIVED OUTSIDE ENG. PLANS BACK FROM OUTSIDE ENG. WITH COMENT LETTER. ROUTED TO DAN S. KMM
REPORT LETTER OF PEER REVIEW FOUND NO DEISCEPENCIES REQUIRING FURTHER SUBMITTAL OR REVIEW FOR THE PROPOSED VOLUNTARY SEISMIC UPGRADE.
|
Additional plans submitted | | | 7/3/2000 | | DONE |
|
|
|
RECEIVED THREE COPIES OF ARCH. SHEETS FOR REFERENCE ONLY. THEY ADDRESS THE REQUIREMENTS I WAS ASKING FOR IN ACTIVITY 006 DATED 6/28/2000. I SENT ONE COPY TO OUTSIDE ENG. AND PUT TWO WITH PLANS. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 7/3/2000 | | DONE |
|
|
|
|
Pending Assignment by MYS | 6/29/2000 | | 6/29/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 6/29/2000 | | DONE |
|
|
|
Route to outside engineering and PLAN CHECK.
|
Plans ACCEPTED BY PLAN TECH | | | 6/28/2000 | | PASS |
|
|
|
PLANS REQUIRE 1. RECORD DECLARATION FORM SIGNED
2. NEEDS TO DIMENSION GRID FOR SHEET S2.8 OR REFRENCE MECH. UP GRADE PLANS BLD00-00238 AND GET COPIES FROM THERE.
3. COVER SHEET REQUIRED WITH CODES AND YEARS, OCCUP. GROUP. CONSTRUCTION TYPE, DESIGN LOADS, TENANT SIZE AND FLOOR. 4. KEY/ SITE PLAN SHOWING SITE AND WHERE BLDG. 5 IS LOCATED.
FAXED TIM BASHFORD AND LEFT MESAGE FOR HIM. I NEED THREE OF EVERYTHING. KMM
Received copies of reference plans used for Phase II - BLD00-00238 , III - BLD00 -1050 & IV - BLD00-01051 for answer response to above noted defficiencies of plan submittals & received fax of signed copy of INVOLVED PARTIES form on 7/29/00. drs
|
Received Certificate of Value | | | 6/23/2000 | | DONE |
|
|
|
|
Application received | | | 6/23/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/23/2000 | | DONE |
|
|
|
|