Fee Review-notes | 6/27/2000 | 6/27/2000 | 5/9/2001 | | DONE |
|
|
|
|
Letter of compliance | | | 12/11/2000 | | DONE |
|
|
|
Letter of Compliance #20038 issued 12/11/00.
|
BLD-Final | 12/6/2000 | 12/7/2000 | 12/7/2000 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/06/2000 at 13:35:31. Contact: ###-####.
|
FIRE-Final Inspection | 12/5/2000 | 12/6/2000 | 12/6/2000 | A | PASS |
Joe Tawney
|
|
|
JC ###-#### Reinsp OK for certificate of completion 12/6/2000 5:13:51 PM
|
FIRE-Final Inspection | 11/17/2000 | 11/17/2000 | 11/17/2000 | P | FAIL |
Joe Tawney
|
|
|
Reinsp Fail Battery's and outside bell 11/17/2000 7:22:25 PM
|
BLD-Framing/Rough-in | 8/7/2000 | 8/7/2000 | 8/7/2000 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/07/2000 at 09:06:20. Contact: ###-####.int corridor framing ok to cover, chk firestops, etc at next insp. Tunnel corridor. 8/7/2000 12:15:39 PM
|
BLD-Framing/Rough-in | 7/25/2000 | 7/25/2000 | 7/25/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 7/25/2000 ok to cover walls at r.rm & corridor pend elec/ plbg. Need insp for tunnel lid
|
Issue PAID IN FULL permit | | | 7/13/2000 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 7/3/2000 | | 7/12/2000 | | PASS |
John Menard
|
|
|
7/12/00 08:19:52 JCM - activity updated through activity BLDA022 from case BLD00-01861.
|
Routing - PLAN CHECK | 7/10/2000 | | 7/12/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/12/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/12/2000 | | DONE |
|
|
|
|
Telephone call | | | 7/12/2000 | | DONE |
|
|
|
AMY LEFT MESS FOR SOMEONE THAT PERMIT IS READY & GAVE FEES
|
Plan resubmittals received | | | 7/11/2000 | | DONE |
|
|
|
SHEET A-2 AND RESPONSE LETTER RECEIVED AND FORWARDED TO J. MENARD. (MYS)
|
Routing - PLUMBING | 7/7/2000 | | 7/10/2000 | | PEND |
|
|
|
|
Plan Review Completed(1st rev) | | | 7/7/2000 | | FAIL |
|
|
|
BLD reviewer requesting add'l info.
|
Routing - FIRE | 7/5/2000 | | 7/7/2000 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 7/5/2000 | | PEND |
|
|
|
MAILED CORNEL LARSON A COPY OF THE COMMENT LIST REQUESTING REVISIONS. JCM
|
Routing - PLAN CHECK | 7/5/2000 | | 7/5/2000 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 7/3/2000 | | 7/5/2000 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 7/3/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Pending Assignment by MYS | 7/3/2000 | | 7/3/2000 | | DONE |
Marlene Southard
|
|
|
|
Received Certificate of Value | | | 6/27/2000 | | DONE |
|
|
|
|
Application received | | | 6/27/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/27/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | | | |
|
|
|
|