(F) Reprint permit | | | 8/3/2001 | | DONE |
|
|
|
|
Fee Review-notes | 6/28/2000 | 6/28/2000 | 4/19/2001 | | DONE |
|
|
|
|
Permanent Occupancy | | 3/14/2001 | 3/14/2001 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 3/12/2001 | 3/14/2001 | 3/14/2001 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/12/2001 at 13:04:22. Contact: ###-####. c/o ok. 3/14/2001 2:28:40 PM
|
Permanent occupancy UNPAID FEE | | | 3/14/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8596 issued 3-14-01 to Micron Technology.
|
FIRE-Final Inspection | 3/7/2001 | 3/8/2001 | 3/8/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/07/2001 at 15:55:57. Contact: ###-####.
|
FIRE-Final Inspection | 3/2/2001 | 3/5/2001 | 3/5/2001 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 3/2/2001 3:54:53 PM will attempt paving for access on 3/06/01 3/5/2001 2:28:21 PM
|
FIRE-Final Inspection | 3/1/2001 | 3/2/2001 | 3/2/2001 | A | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/01/2001 at 09:08:16. Contact: ###-####.
|
Print Occupancy Form | | | 2/21/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 2/20/2001 | | |
|
|
|
At the request of the applicant, I have revised the building description to indicate that this building was constructed without any code complying control areas. The entire building is be considered as a control area and the amount of hazardous materials within this building are required to be maintained below the exempt amounts per UBC Tb. 3-E. (The building was constructed to comply with the approved plans.) JCM
|
BLD-Framing/Rough-in | 2/10/2001 | 2/12/2001 | 2/12/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/10/2001 at 11:13:01. Contact: ###-####. conf. plan review iuse of permit scope of work. pending responce. 2/12/2001 3:02:08 PM
|
FIRE-Final Inspection | 2/7/2001 | 2/9/2001 | 2/9/2001 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 02/07/2001 at 16:27:08. Contact: ###-####. exit signs; extinguishers; access roads not complete; door landings; hydrant in wrong position 2/9/2001 10:33:48 AM
|
BLD-Framing/Rough-in | 1/2/2001 | 1/3/2001 | 1/3/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/02/2001 at 14:33:37. Contact: ###-####. roof deck and struc. framing ok. 1/3/2001 3:02:54 PM
|
BLD-Framing/Rough-in | 1/2/2001 | 1/3/2001 | 1/3/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/02/2001 at 14:33:37. Contact: ###-####. roof deck and struc. framing ok. 1/3/2001 3:02:54 PM
|
BLD-Framing/Rough-in | 12/26/2000 | 12/27/2000 | 12/27/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/26/2000 at 15:09:58. Contact: ###-####. conf. with haedgrove and richardson to review roof details/ const. covered with special insp. pending reports for welding/ 12/27/2000 4:20:31 PM
|
BLD-Concrete | 10/24/2000 | 10/25/2000 | 10/25/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/24/2000 at 07:44:06. Contact: ###-####.
|
BLD-Concrete | 10/24/2000 | 10/25/2000 | 10/25/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/24/2000 at 07:44:06. Contact: ###-####.
|
BLD-Concrete | 10/24/2000 | 10/24/2000 | 10/24/2000 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/24/2000 at 07:43:19. Contact: ###-####.
|
BLD-Foundation | 10/2/2000 | 10/3/2000 | 10/3/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/02/2000 at 14:23:19. Contact: ###-####. placed w/si pending report. 10/3/2000 3:40:09 PM
|
BLD-Footing | 9/27/2000 | 9/28/2000 | 9/28/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/27/2000 at 13:59:41. Contact: . placed with special insp. pending report. 9/28/2000 11:17:11 AM
|
BLD-Footing | 9/21/2000 | 9/22/2000 | 9/22/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/21/2000 at 11:31:03. Contact: ###-####. placed with special insp. pending report. slab 2nd half. 9/22/2000 2:27:40 PM
|
BLD-Footing | 9/19/2000 | 9/20/2000 | 9/20/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/19/2000 at 17:12:16. Contact: . work in progess pending special insp. report. 9/20/2000 9:40:05 AM
|
BLD-Footing | 9/15/2000 | 9/18/2000 | 9/18/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/15/2000 at 15:27:02. Contact: ###-####. rebar ok pending s/i report. 9/18/2000 9:39:33 AM
|
BLD-Footing | 9/14/2000 | 9/15/2000 | 9/15/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/14/2000 at 13:10:14. Contact: ###-####.
|
(F) Reprint permit | | | 9/1/2000 | | DONE |
|
|
|
|
Issue & PRINT permit | | | 8/31/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/30/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/30/2000 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/28/2000 | | 8/29/2000 | | PASS |
|
|
|
FAXED A COPY OF THE STRUCTURAL REVISIONS TO THE CONSULTING ENGINEER FOR THEIR REVIEW. JCM PLANS WITH REVIEW CAME BACK FROM OUTSIDE ENG. TOOK TO JCM.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/25/2000 | | 8/29/2000 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 7/3/2000 | | 8/29/2000 | | PASS |
John Menard
|
|
|
8/29/00 14:24:33 JCM - activity updated through activity BLDA022 from case BLD00-01867.
|
Plan resubmittals received | | | 8/28/2000 | | DONE |
|
|
|
RECEIVED ONE FAXED COPY OF RESPONSE TO STRUCTURAL PLAN CHECK REVIEW COMMENTS. ROUTED TO JOHN M. KMM
|
Routing - PUBLIC WORKS | 8/23/2000 | | 8/25/2000 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 8/25/2000 | | |
|
|
|
E-MAILED FRANK KVAPIL TO REMIND HIM THAT I HAVE NOT YET RECEIVED THE STRUCTURAL RESUBMITTALS REQUESTED BY FAX 8/4/00. JCM
|
Routing - PLAN CHECK | 8/15/2000 | | 8/23/2000 | | PEND |
|
|
|
|
Routing - FIRE | 8/15/2000 | 8/15/2000 | 8/15/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing - FIRE | 7/31/2000 | 8/7/2000 | 8/7/2000 | | FAIL |
Bill Alexander
|
|
|
Need verification from Fire Department concerning F-2 occupancy and Hazardous materials quantities.
|
Plan Review Completed(1st rev) | | | 8/7/2000 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 8/7/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM MICRON TWO SETS OF SHEET A6.1 . FORWARDED SAME TO JOHN MENARD. 8/7/00 DAR
|
Plan resubmittals requested | | | 8/4/2000 | | |
|
|
|
FAXED FRANK KVAPIL A COPY OF THE COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS. JCM
|
Routing Off Site - STRUCTURAL | 7/20/2000 | | 8/4/2000 | | FAIL |
|
|
|
AM WAITING FOR STRUCTURAL CALCS. SPOKE WITH FRANK AGAIN ABOUT OBTAINING THEM. KMM
7/20/2000 CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
|
Routing - PLAN CHECK | 7/25/2000 | | 7/31/2000 | | PEND |
|
|
|
|
Plan resubmittals requested | | | 7/31/2000 | | |
|
|
|
E-MAILED FRANK KVAPIL AT MICRON REQUESTING REVISIONS. JCM
|
Routing - PLUMBING | 7/24/2000 | | 7/25/2000 | | PASS |
|
|
|
per plans and 97 upc
|
Routing - PUBLIC WORKS | 7/18/2000 | | 7/24/2000 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN REVISION PER BRIAN MURPHY. 7/24/00 DAR
|
Routing - PLANNING | 7/24/2000 | | 7/24/2000 | | PASS |
|
|
|
No Design Review Required. TALKED WITH TEMPRA AND SHE INDICATED THAT THERE WAS NO DESIGN REVIEW REQUIRED ON THIS PROJECT, THEREFORE SHE WOULD NOT BE SIGNING OFF ON THE PLANS. JCM
|
Plan routing begun/NEW & ADDTN | | | 7/18/2000 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/18/2000 | | PEND |
|
|
|
RECEIVED SOILS REPORT, STRUCT. CALCS. I AM ROUTING PLANS. AT THIS TIME, I WILL LET P&Z AND PW HANDEL ANY ITEMS THEY MAY NEED. KMM I STILL HAVE NOT RECEIVED SITE PLAN. KMM
|
Plan routing begun/NEW & ADDTN | | | 7/3/2000 | | |
|
|
|
PLANS IN MY HOLD BOX. I HAVE ROUTED ONE COPY OF THE THREE TO JOHN FOR OUTSIDE ENG. REQUEST. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 7/3/2000 | | HOLD |
|
|
|
REQUIRE 1. ARCH./ENG. RECORD FORM
2. SOILS REPOR. HAVE ASKED FOR SOILS BEARING PRESURE.
3. THREE ADDIDITONAL CIVIL SHEETS STAMPED AND SIGNED.
4. STAMPED AND SIGNED STRUCT. CALCS.
5. LANDSCAPE PLANS TWO COPIES
6. DRH# INFORMATION. IF HE DOES NOT HAVE A DR# THEN I SUGGESTED HE SPEAK WITH TEMPRA
7. SITE PLAN SHOWING ALL REQUIREMENTS.
FAXED FRANK THE ABOVE REQUESTED ITEMS. KMM
7/18/00 I AM GOING TO ROUTE PLANS. I SPOKE WITH FRANK STILL REQUESTING SOILS REPORT, STRUCT. CALCS. ARCH./ENG. RECORD FORM. I WILL LET TEMPRA AND BRIAN DEAL WITH THEIR REQUIREMENTS. KMM
7/19/2000 RECEIVED THREE COPIES OF STRUCT. CALCS AND SOILS REPORT. ONE COPY OF ARCH. ENG. DECLARATION FORM. ROUTED TO JOHN M. KMM
|
Application received | | | 6/28/2000 | | |
|
|
|
|
Pending Assignment by MYS | 6/28/2000 | | 6/28/2000 | | DONE |
Marlene Southard
|
|
|
|
Received Certificate of Value | | | 6/28/2000 | | DONE |
|
|
|
|