Permit Information
Permit NumberBLD00-01872
StatusFinaled
Name STATEWIDE CONSTRUCTION
Site Address 5391 E QUARTERSAWN CT
Project NameFLOOD PLAIN
Customer Number362-5575
ePlanReviewNo
Description
To construct a 3203 sq. ft. two story single family residence (2188 sq. ft. first floor/1015 sq. ft. second floor) with a attached 786 sq. ft. three car garage. THIS LOT IS WITHIN THE FLOODPLAIN AREA. A ELEVATION CERTIFICATE IS REQUIRED BEFORE CALLING FOR A ROUGH FRAMING INSPECTION. JIM WYLLIE HAS RELEASED THE NON-BUILD IF CONSTRUCTED IN ACCORDANCE TO THE INFORMATION SUPPLIED BY QUADRANT. Per approved plans, engineering and requirement list. This is a solar and shade restricted lot. CUP98-0116 per Roger Jones. PC#573 (SAM)
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/16/20015/16/20015/16/2001PPASS
DetailsSteven Webb
Brian ###-#### C. of C. #20430 issued 5/16/2001 1:22:42 PM
DOC - Permit Finaled5/16/20015/16/20015/16/2001PPASS
DetailsSteven Webb
Finaled by inspector at 5/16/2001 1:22:49 PM
BLD-Final5/15/20015/15/20015/15/2001PFAIL
DetailsSteven Webb
Brian ###-#### No address posted--Did not go inside. 5/15/2001 1:05:44 PM
BLD-Final5/2/20015/2/20015/2/2001PNR
DetailsSteven Webb
###-#### C/n posted 5/2/2001 3:47:49 PM
BLD-Framing/Rough-in1/23/20011/23/20011/23/2001PPASS
DetailsSteven Webb
###-#### ok to cover 1/23/2001 1:07:45 PM
BLD-Energy code compliance1/19/20011/19/20011/19/2001PPART
DetailsSteven Webb
Scheduled by a contractor via Hello! on 01/19/2001 at 10:29:26. Contact: ###-####. Additional items required on posted c/n. ok to insulate, not to cover. 1/19/2001 2:46:54 PM
BLD-Framing/Rough-in1/17/20011/18/20011/18/2001AFAIL
DetailsSteven Webb
###-####: C/N issued:1) Air package needed; 2) Address is needed on building; 3) Eng. needed per prior c/n dated 12/8/00; 4) Draftstops needed at ceiling line; 5) Stari tread at bottom exceeds 3/8 tolerance; 6) Double M.lam at porch needs solid studs underneath.; 7) Insulation needed in crawl 1/18/2001 12:21:23 PM
BLD-Framing/Rough-in12/7/200012/8/200012/8/2000APART
DetailsDave Hannah
Duane ###-#### ok to cover all but sw corner bedroom 2 missing two straps need engineering 12/8/2000 10:41:16 AM
BLD-Foundation10/30/200010/30/200010/30/2000PPASS
DetailsRuss Owen
stem wall James ###-####
BLD-Footing10/26/200010/26/200010/26/2000PPASS
DetailsRuss Owen
around 3:00 James ###-####
Issue PAID IN FULL permit  10/23/2000 DONE
Telephone call  10/5/2000 DONE
talked to duane to verify plans are ready-will pick up next week
Inspection Record Card- Bld  8/3/2000 DONE
Telephone call  8/3/2000 DONE
left mess that permit is ready
Plan Reviewer's activity  8/2/2000 PASS
JIM WYLLIE APPROVED AND RELEASED THE NONBUILD AGREEMENT BASED ON ENGINEERING SUBMITTED BY QUADRANT.
PLANS/APPL TAKEN TO FRONT DESK  8/2/2000 DONE
Plan assigned to (SAM)7/14/2000 8/2/2000 PASS
DetailsSteve Munroe
8/2/2000 15:22:47 MYS - activity updated through activity BLDA022 from case BLD00-01872.
Override - Parcel Holds  7/19/2000  
Pending Assignment by DJO6/28/2000 7/14/2000 DONE
DetailsDan Overy
Routing - PUBLIC WORKS6/28/20006/28/20006/29/2000 PASS
Routing - PLANNING6/28/20006/28/20006/28/2000 PASS
Application received  6/28/2000  
Routing - PLAN CHECK6/29/20006/29/2000  PEND
Plan Review Report     
Plan Reviewer's activity    PEND
7/19/00 Plan review is DONE, waiting for Jim Wyllie to release / approved.